Description
CONSTRUCT NEW 18,000 SQ FT TWO STORY TYPE II-1HR VOCATIONAL CLASSROOM BUILDING AT BSU. THE FIRST FLOOR WILL HAVE 14,448 SQ FT AND THE SECOND FLOOR WILL HAVE 4,512 SQ FT. THE BUILDING IS FULLY FIRE SPRINKLERED WITH SPRINKLERS BEING USED FOR ONE HOUR SUBSTITUTION. OTHER WORK INCLUDES GRADING, PAVING, LANDSCAPING AND ALL OTHER SITE IMPROVEMENTS. ALL WORK IS PER APPROVED PLANS PC98-291, CUP98-0029 MLO
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final1/10/20001/11/20001/11/2000APASS
DetailsJim Storey
Call 1st - Harry Allen @ ###-####. Final ok.
Permanent Occupancy 1/11/20001/11/2000 DONE
Details
BLD-Other10/27/199910/28/199910/28/1999APART
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/27/1999 at 14:21:02. Contact: ###-####. Ok for temp. C/N w/harry
FIRE-Final Inspection10/26/199910/27/199910/27/1999APASS
DetailsRick Jackson
Scheduled by a contractor via Hello! on 10/26/1999 at 15:05:22. Contact: ###-####. Occ. Approved
BLD-Final10/22/199910/26/199910/26/1999ACANC
DetailsJim Storey
Scheduled by a contractor via Hello! on 10/22/1999 at 14:26:46. Contact: ###-####. Harry called and canceled.
FIRE-Final Inspection10/25/199910/26/199910/26/1999ANR
DetailsRick Jackson
Scheduled by a contractor via Hello! on 10/25/1999 at 15:40:52. Contact: ###-####. Contractor to reschedule
BLD-Final10/22/199910/25/199910/25/1999ANR
DetailsJim Storey
Harry Allen ###-#### Harry called and canceled
FIRE-Final Inspection10/22/199910/22/199910/22/1999PFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 10/22/1999 at 10:09:08. Contact: ###-####. Met with State Farm Marshall to test alarms- alarms not ready- reinspected fee assessed
FIRE-Final Inspection10/5/199910/5/199910/5/1999PFAIL
DetailsRick Jackson
Forest ###-#### not a final - underground supply line hydro-pass; overhead sprinklers complete-awaiting fire alarm connection
FIRE-Final Inspection9/30/199910/1/199910/1/1999PFAIL
DetailsRick Jackson
Scheduled by a contractor via Hello! on 09/30/1999 at 15:35:39. Contact: ###-####. Need alarm plans; sprinlkers not complete
FIRE-Final Inspection9/30/199910/1/199910/1/1999PCANC
DetailsRick Jackson
Harry Allen ###-#### Double entry
FIRE-Final Inspection9/21/19999/22/19999/22/1999PFAIL
DetailsRick Jackson
forest ###-#### Sprinkler rough-in inspection- need spare head box; test alarms; repair leaking head; hydro test FDC
INSP-Supply line flush5/21/19995/21/19995/21/1999PPASS
DetailsRick Jackson
underground okay
INSP - Framing/Rough-in4/27/19994/28/19994/28/1999AFAIL
DetailsWes Worcester
04/28/99 342 - Scheduled by Hello!. Contact phone is [4264998]. unable
INSP - Framing/Rough-in3/30/19993/31/19993/31/1999APART
DetailsWes Worcester
03/31/99 342 - Scheduled by Hello!. repkace screws at door jambs, ck th
INSP-Conference3/8/19993/8/19993/8/1999APART
DetailsRick Jackson
with gen and 301 - reviewed plans and walk through of site
INSP - Foundation2/5/19992/5/19992/5/1999 PASS
DetailsJim Storey
/ / 301 - REVIEWED SPECIAL INSP REPORT AND ARCHOIVED TO CITY.
INSP - Foundation10/7/199810/8/199810/8/1998APART
DetailsRuss Owen
10/08/98 407 - stell in place looks good ,special insp required.
INSP - Foundation9/23/19989/24/19989/24/1998APART
DetailsWes Worcester
09/24/98 342 - poured, special inspector had already left 3898612].
INSP - Foundation9/17/19989/17/19989/17/1998 PART
DetailsJim Storey
/ / 301 - FTG -OK FOOTING 1-7 grid a, d.8 line special insp. on site pending repor
INSP - Foundation9/17/19989/17/19989/17/1998PCANC
DetailsRuss Owen
09/17/98 407 - trans to 301.Hello!. Contact phone is [3898612].