INSP - Final | 4/13/1999 | 4/13/1999 | 4/13/1999 | | PASS |
|
|
|
madeok other agencies ok
|
Permanent Occupancy | | 4/13/1999 | 4/13/1999 | | DONE |
|
|
|
|
INSP - Final | 4/9/1999 | 4/9/1999 | 4/9/1999 | | PASS |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR PERM OCC
|
INSP-Conference | 4/1/1999 | 4/1/1999 | 4/1/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - CONF W/DAVE TUCKER REG SIGN OFF OF PERMIT
|
INSP - Final | 12/21/1998 | 12/21/1998 | 12/21/1998 | | PART |
|
|
|
12/21/98 338 - signed the temp col of the occ req card, need shell final
|
INSP - Final | 12/18/1998 | 12/18/1998 | 12/18/1998 | | PART |
Joe Tawney
|
|
|
/ / 406 - REINSP OK FOR TEMP OCC CONTROL VLV SUPR, ACCELERATOR
|
INSP-Final Inspection | 12/17/1998 | 12/17/1998 | 12/17/1998 | P | FAIL |
Joe Tawney
|
|
|
12/17/98 406 - dwayne- ###-#### re-insp fire fn REINSP FAIL ACCEL FAILED DUCT DET CONTROL VLV MONITORING
|
INSP-Final Inspection | 12/4/1998 | 12/7/1998 | 12/7/1998 | P | FAIL |
Joe Tawney
|
|
|
12/07/98 406 - dwayne ###-#### fn fire insp at 1 per joe REINSP FAIL SPKLR SYSTEM DUCT DET ALARM SYSTEM
|
INSP - Final | 12/2/1998 | 12/4/1998 | 12/4/1998 | A | CANC |
Carl Dependahl
|
|
|
DAVE ###-####
|
INSP-Final Inspection | 12/2/1998 | 12/3/1998 | 12/3/1998 | P | FAIL |
Joe Tawney
|
|
|
12/03/98 406 - dave ###-#### FINAL FAIL ALARM SYSTEM, SPKLR SYSTEM, EMERG LIGHTS, FIRE EXT, DOOR HDWR ì
|
INSP-Conference | 11/13/1998 | 11/13/1998 | 11/13/1998 | A | CONF |
Mike Kinnear
|
|
|
FS Contractor reviewed what was to be finished, when and what is still pending (off site monitoring thru USWest phone line backlog delay). Expected any day. Wanted to know if it would hold up a Temp. Occ.? I indicated it probably would, but would be reviewed when asked for.
|
INSP - Framing/Rough-in | 11/9/1998 | 11/10/1998 | 11/12/1998 | A | PART |
|
|
|
11/10/98 338 - made ok to drop in the ceiling tiles.
|
INSP - Framing/Rough-in | 10/12/1998 | 10/13/1998 | 10/14/1998 | A | PART |
|
|
|
10/15/98 338 - made ok to cover with 350 approval
|
INSP - Framing/Rough-in | 10/6/1998 | 10/7/1998 | 10/7/1998 | P | PART |
|
|
|
10/07/98 338 - ok to cover
|
INSP - Framing/Rough-in | 10/2/1998 | 10/2/1998 | 10/2/1998 | | PART |
|
|
|
10/02/98 338 - THIS IS A CONFERENCE TO CHECK OUT THE STAIR REPAIR AND LI
|
INSP - Framing/Rough-in | 9/30/1998 | 10/2/1998 | 10/2/1998 | A | PART |
|
|
|
10/05/98 338 - conference made ok stair repair going well
|
INSP-Conference | 9/28/1998 | 9/29/1998 | 9/29/1998 | A | NR |
|
|
|
09/29/98 338 - not ready for insp conf will have plans reviewers on site
|