Permit Information
Permit NumberBLD98-01483
StatusFinaled
Name ALL PRO FLOORS
Site Address 9543 W EMERALD ST
Project NameSAILFISH PLACE
Customer Number 
ePlanReviewNo
Description
To finish a 2 story 10,386 sq.ft. retail/office/warehouse tenant per approved plans on file. Work to include the construction of a second story floor (2916sf), interior bearing and nonload bearing walls to form offices, retail area, restrooms as shown on the approved plans. (1st floor=3675 sq.ft./2nd floor=2916 sq.ft.) NOTE: This building is fully fire sprinklered for area increase. PC#331-98 ads 4/16/99: For clarification this tenant now has 5,517 sq.ft. on the 1st floor and 4,156 sq.ft. on the 2nd floor. This totals 9,673 sq.ft. for this tenant. The balance of the building is leasable space. MYS
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final4/13/19994/13/19994/13/1999 PASS
madeok other agencies ok
Permanent Occupancy 4/13/19994/13/1999 DONE
Details
INSP - Final4/9/19994/9/19994/9/1999 PASS
DetailsJoe Tawney
/ / 406 - REINSP OK FOR PERM OCC
INSP-Conference4/1/19994/1/19994/1/1999 PART
DetailsJoe Tawney
/ / 406 - CONF W/DAVE TUCKER REG SIGN OFF OF PERMIT
INSP - Final12/21/199812/21/199812/21/1998 PART
Details
12/21/98 338 - signed the temp col of the occ req card, need shell final
INSP - Final12/18/199812/18/199812/18/1998 PART
DetailsJoe Tawney
/ / 406 - REINSP OK FOR TEMP OCC CONTROL VLV SUPR, ACCELERATOR
INSP-Final Inspection12/17/199812/17/199812/17/1998PFAIL
DetailsJoe Tawney
12/17/98 406 - dwayne- ###-#### re-insp fire fn REINSP FAIL ACCEL FAILED DUCT DET CONTROL VLV MONITORING
INSP-Final Inspection12/4/199812/7/199812/7/1998PFAIL
DetailsJoe Tawney
12/07/98 406 - dwayne ###-#### fn fire insp at 1 per joe REINSP FAIL SPKLR SYSTEM DUCT DET ALARM SYSTEM
INSP - Final12/2/199812/4/199812/4/1998ACANC
DetailsCarl Dependahl
DAVE ###-####
INSP-Final Inspection12/2/199812/3/199812/3/1998PFAIL
DetailsJoe Tawney
12/03/98 406 - dave ###-#### FINAL FAIL ALARM SYSTEM, SPKLR SYSTEM, EMERG LIGHTS, FIRE EXT, DOOR HDWR ì
INSP-Conference11/13/199811/13/199811/13/1998ACONF
DetailsMike Kinnear
FS Contractor reviewed what was to be finished, when and what is still pending (off site monitoring thru USWest phone line backlog delay). Expected any day. Wanted to know if it would hold up a Temp. Occ.? I indicated it probably would, but would be reviewed when asked for.
INSP - Framing/Rough-in11/9/199811/10/199811/12/1998APART
Details
11/10/98 338 - made ok to drop in the ceiling tiles.
INSP - Framing/Rough-in10/12/199810/13/199810/14/1998APART
Details
10/15/98 338 - made ok to cover with 350 approval
INSP - Framing/Rough-in10/6/199810/7/199810/7/1998PPART
Details
10/07/98 338 - ok to cover
INSP - Framing/Rough-in10/2/199810/2/199810/2/1998 PART
Details
10/02/98 338 - THIS IS A CONFERENCE TO CHECK OUT THE STAIR REPAIR AND LI
INSP - Framing/Rough-in9/30/199810/2/199810/2/1998APART
Details
10/05/98 338 - conference made ok stair repair going well
INSP-Conference9/28/19989/29/19989/29/1998ANR
Details
09/29/98 338 - not ready for insp conf will have plans reviewers on site