Permit Information
Permit NumberBLD98-01484
StatusFinaled
Name IDAHO ICE WORLD (INTERIOR FINISH)
Site Address 7072 S EISENMAN RD
Project NameIDAHO ICE WORLD-ICE RINKS
Customer Number 
ePlanReviewNo
Description
IDAHO ICEWORLD (TENANT IMPROVEMENT) TO CONSTRUCT THE TENANT IMPROVEMENT FINISHES FOR THE TWIN ICE RINK AREAS, INCLUDING THE INSTALLATION OF THE TWO ICE RINKS AND EQUIPMENT, AS WELL AS, ALL OF THE TENANT IMPROVEMENT FINISHES FOR ALL OF THE ICE RINK SUPPORT AREAS. THIS PERMIT ALSO INCLUDES THE FINISH OF ALL AREAS OF THE SECOND FLOOR. THIS PERMIT DOES NOT INCLUDE THE FINISH OF ANY OF THE INDIVIDUAL TENANT SPACES PROPOSED AT AREA "C" ON THE APPROVED PLANS. THIS PERMIT DOES NOT INCLUDE THE INSTALLATION OF ANY MOVABLE PANEL PARTITIONS AT THE SECOND FLOOR DINING/EXERCISE ROOM. ALL CONSTRUCTION PER THE APPROVED PLANS AND ATTACHED REQUIREMENT LIST. THIS PERMIT IS PART OF A PHASED BUILDING PROJECT. THE SHELL & CORE IS APPROVED UNDER PERMIT BLD98-1052. PC#327-98/JCM
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP - Final7/20/19997/20/19997/20/1999PPASS
DetailsRuss Owen
07/20/99 407 - this has been approved at prior date,has several permits.
INSP-Final Inspection7/20/19997/20/19997/20/1999PPASS
DetailsRick Jackson
phil ###-#### occ approved
INSP - Final3/10/19993/11/19993/11/1999AFAIL
DetailsRuss Owen
03/11/99 407 - phil ###-####
INSP - Final3/4/19993/4/19993/4/1999AFAIL
DetailsRuss Owen
CORRECTIONS.
INSP-Final Inspection2/25/19992/26/19992/26/1999ANR
DetailsJim Storey
02/26/99 301 - 407 is not able to do this today. NO PLAN ON SITE OR SIGN
INSP-Final Inspection12/4/199812/4/199812/4/1998PPART
DetailsRick Jackson
temp occ approved for 2nd floor; c/n issued
INSP-Final Inspection12/3/199812/3/199812/3/1998APART
DetailsRick Jackson
walk through to check for completion and status for final occupancy
INSP-Final Inspection12/1/199812/1/199812/1/1998PPART
DetailsRick Jackson
checked progress for final
INSP-Final Inspection11/30/199811/30/199811/30/1998PPART
DetailsRick Jackson
checked progress for final occ with George Slane
INSP - Final11/25/199811/25/199811/25/1998 PART
Details
/ / 333 - PROFIT WITH PHIL
INSP - Final11/25/199811/25/199811/25/1998 PART
Details
/ / 333 - PROFIT WITH PHIL
INSP-Final Inspection11/25/199811/25/199811/25/1998PPART
DetailsRick Jackson
temp occ approved for first floor only
INSP-Final Inspection11/24/199811/24/199811/24/1998PFAIL
DetailsRick Jackson
patrick ###-#### fn fire alarms not ready, construction still in progress
INSP-Final Inspection11/20/199811/20/199811/20/1998PPART
DetailsRick Jackson
temp occ approved for rink "a" for the weekend
INSP-Sprinkler Rough-in/Hydro11/19/199811/19/199811/19/1998PFAIL
DetailsRick Jackson
window sprinklers have heads within 6 feet
INSP-Final Inspection11/18/199811/18/199811/18/1998PFAIL
DetailsRick Jackson
rink "a" occ request met with project manager to discuss requirements for opening; all items on c/n will be ready?
INSP-Conference11/10/199811/10/199811/10/1998APART
DetailsRick Jackson
3 hour wall penetrations for dampers; corridor on 2nd floor dampers
INSP - Framing/Rough-in11/6/199811/6/199811/6/1998PPART
DetailsRuss Owen
went out to check progress,exterior flat work not yet done,they are in process of wanting to open rink west rink.
INSP-Conference10/26/199810/26/199810/26/1998APART
DetailsRick Jackson
profit for partial opening on 11/13. gave requirements to contractor
INSP-Sprinkler Rough-in/Hydro10/5/199810/5/199810/5/1998APART
DetailsRick Jackson
sprinkler piping not installed in new spaces