INSP - Final | 7/20/1999 | 7/20/1999 | 7/20/1999 | P | PASS |
Russ Owen
|
|
|
07/20/99 407 - this has been approved at prior date,has several permits.
|
INSP-Final Inspection | 7/20/1999 | 7/20/1999 | 7/20/1999 | P | PASS |
Rick Jackson
|
|
|
phil ###-#### occ approved
|
INSP - Final | 3/10/1999 | 3/11/1999 | 3/11/1999 | A | FAIL |
Russ Owen
|
|
|
03/11/99 407 - phil ###-####
|
INSP - Final | 3/4/1999 | 3/4/1999 | 3/4/1999 | A | FAIL |
Russ Owen
|
|
|
CORRECTIONS.
|
INSP-Final Inspection | 2/25/1999 | 2/26/1999 | 2/26/1999 | A | NR |
Jim Storey
|
|
|
02/26/99 301 - 407 is not able to do this today. NO PLAN ON SITE OR SIGN
|
INSP-Final Inspection | 12/4/1998 | 12/4/1998 | 12/4/1998 | P | PART |
Rick Jackson
|
|
|
temp occ approved for 2nd floor; c/n issued
|
INSP-Final Inspection | 12/3/1998 | 12/3/1998 | 12/3/1998 | A | PART |
Rick Jackson
|
|
|
walk through to check for completion and status for final occupancy
|
INSP-Final Inspection | 12/1/1998 | 12/1/1998 | 12/1/1998 | P | PART |
Rick Jackson
|
|
|
checked progress for final
|
INSP-Final Inspection | 11/30/1998 | 11/30/1998 | 11/30/1998 | P | PART |
Rick Jackson
|
|
|
checked progress for final occ with George Slane
|
INSP - Final | 11/25/1998 | 11/25/1998 | 11/25/1998 | | PART |
|
|
|
/ / 333 - PROFIT WITH PHIL
|
INSP - Final | 11/25/1998 | 11/25/1998 | 11/25/1998 | | PART |
|
|
|
/ / 333 - PROFIT WITH PHIL
|
INSP-Final Inspection | 11/25/1998 | 11/25/1998 | 11/25/1998 | P | PART |
Rick Jackson
|
|
|
temp occ approved for first floor only
|
INSP-Final Inspection | 11/24/1998 | 11/24/1998 | 11/24/1998 | P | FAIL |
Rick Jackson
|
|
|
patrick ###-#### fn fire alarms not ready, construction still in progress
|
INSP-Final Inspection | 11/20/1998 | 11/20/1998 | 11/20/1998 | P | PART |
Rick Jackson
|
|
|
temp occ approved for rink "a" for the weekend
|
INSP-Sprinkler Rough-in/Hydro | 11/19/1998 | 11/19/1998 | 11/19/1998 | P | FAIL |
Rick Jackson
|
|
|
window sprinklers have heads within 6 feet
|
INSP-Final Inspection | 11/18/1998 | 11/18/1998 | 11/18/1998 | P | FAIL |
Rick Jackson
|
|
|
rink "a" occ request met with project manager to discuss requirements for opening; all items on c/n will be ready?
|
INSP-Conference | 11/10/1998 | 11/10/1998 | 11/10/1998 | A | PART |
Rick Jackson
|
|
|
3 hour wall penetrations for dampers; corridor on 2nd floor dampers
|
INSP - Framing/Rough-in | 11/6/1998 | 11/6/1998 | 11/6/1998 | P | PART |
Russ Owen
|
|
|
went out to check progress,exterior flat work not yet done,they are in process of wanting to open rink west rink.
|
INSP-Conference | 10/26/1998 | 10/26/1998 | 10/26/1998 | A | PART |
Rick Jackson
|
|
|
profit for partial opening on 11/13. gave requirements to contractor
|
INSP-Sprinkler Rough-in/Hydro | 10/5/1998 | 10/5/1998 | 10/5/1998 | A | PART |
Rick Jackson
|
|
|
sprinkler piping not installed in new spaces
|