Permanent Occupancy | | 3/31/2000 | 3/31/2000 | | DONE |
|
|
|
|
Permanent Occupancy | | 3/31/2000 | 3/31/2000 | | DONE |
|
|
|
|
BLD-Final | 3/29/2000 | 3/30/2000 | 3/30/2000 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/29/2000 at 16:21:06. Contact: ###-####. Card to cont. 3/31/00 8:53:06 AM
|
FIRE-Final Inspection | 3/27/2000 | 3/28/2000 | 3/28/2000 | P | PASS |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 03/27/2000 at 16:57:25. Contact: ###-####. Reinsp. ok for perm. occ. 3/29/00 10:11:08 AM
|
BLD-Final | 3/24/2000 | 3/27/2000 | 3/27/2000 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/24/2000 at 15:22:06. Contact: ###-####. N/R 3/28/00 9:16:31 AM
|
FIRE-Final Inspection | 3/24/2000 | 3/27/2000 | 3/27/2000 | A | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 03/24/2000 at 15:21:09. Contact: ###-####. Reinsp. fail alarm system problems 3/27/00 4:22:25 PM
|
FIRE-Final Inspection | 3/23/2000 | 3/24/2000 | 3/24/2000 | A | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 03/23/2000 at 09:41:15. Contact: ###-####. Final fail C/N issued. 3/24/00 1:09:45 PM
|
FIRE-Supply Line Hydro | 3/10/2000 | 3/10/2000 | 3/10/2000 | P | PART |
Joe Tawney
|
|
|
terry nelson ###-#### Ok on underground & above ground hydro tests. 3/14/00 11:21:59 AM
|
BLD-Other | 2/21/2000 | 2/22/2000 | 2/22/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 02/21/2000 at 15:05:39. Contact: ###-####. C/N; need detail for disontinuity. 2/23/00 11:27:01 AM
|
FIRE-Sprinkler Rough-in | 1/24/2000 | 1/24/2000 | 1/26/2000 | P | PART |
Joe Tawney
|
|
|
###-#### Terry Ok to cover hard lid area in south canopy. 1/26/00 2:18:35 PM
|
BLD-Framing/Rough-in | 12/10/1999 | 12/13/1999 | 12/13/1999 | A | PART |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 12/10/1999 at 14:56:51. Contact: ###-####. Insulation, ok to cover.
|
FIRE-Supply Line Flush | 12/9/1999 | 12/9/1999 | 12/9/1999 | P | PART |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 12/09/1999 at 08:32:22. Contact: ###-####. Ok supply line flush.
|
BLD-Framing/Rough-in | 12/2/1999 | 12/3/1999 | 12/3/1999 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 12/02/1999 at 15:53:30. Contact: ###-####. Need EFIS listing; ok to insulate ext. walls.
|
BLD-Framing/Rough-in | 11/24/1999 | 11/24/1999 | 11/24/1999 | P | PART |
Carl Dependahl
|
|
|
Need all listing/ install & er. report for EFIS.
|
BLD-Framing/Rough-in | 11/19/1999 | 11/19/1999 | 11/19/1999 | A | PART |
Carl Dependahl
|
|
|
Verbal request for EFIS (dryvit) listing for compliance w/UBC 1402; EFIS to be installed over OSB shear walls that are load bearing.
|
BLD-Framing/Rough-in | 11/15/1999 | 11/15/1999 | 11/16/1999 | P | FAIL |
Carl Dependahl
|
|
|
GREG ###-#### CELL R/I-- NAILING INSP C/N.. Hold downs @ mark 4, complete shear wall (int.) roof nailing; ok to begin cover @ ext.
|
BLD-Framing/Rough-in | 11/5/1999 | 11/8/1999 | 11/8/1999 | A | PART |
Carl Dependahl
|
|
|
GREG--- FR ###-#### Ext. "Pilasters" only- ok to delets sprinklers.
|
BLD-Framing/Rough-in | 11/3/1999 | 11/4/1999 | 11/4/1999 | A | FAIL |
|
|
|
GREG ###-#### Need eng. Written approval of the details submitted by same.
|
FIRE-Conference | 11/2/1999 | 11/2/1999 | 11/2/1999 | P | PART |
Joe Tawney
|
|
|
Conf. on costr. of columns to meet code expectation for spklr. protection.
|
BLD-Framing/Rough-in | 11/1/1999 | 11/1/1999 | 11/1/1999 | P | FAIL |
Carl Dependahl
|
|
|
GREG ###-#### Referred to fire insp. Re: sprinklers @ concealed space
|
BLD-Foundation | 10/11/1999 | 10/7/1999 | 10/8/1999 | A | PART |
Carl Dependahl
|
|
|
Pending special insp. report and eng's ok for shear wall construction
|
BLD-Conference | 9/23/1999 | 9/23/1999 | 9/23/1999 | P | PART |
Carl Dependahl
|
|
|
Keep C/N
|
INSP - Foundation | 9/14/1999 | 9/14/1999 | 9/14/1999 | P | PART |
Carl Dependahl
|
|
|
MTI ONSITE, PEND SPCL INSPCTN REPORT
|
INSP - Foundation | 9/8/1999 | 9/9/1999 | 9/9/1999 | A | PART |
Carl Dependahl
|
|
|
MT/onsite, prelim soils report (test) ok. Keep c/n, need engr's clarification for sheer walls.
|
INSP - Footings | 9/2/1999 | 9/2/1999 | 9/2/1999 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - NEED SPEC INS FTGS;CLARIFY CONST DETAILS: SHEAR WALLS
|
INSP - Foundation | 9/1/1999 | 9/2/1999 | 9/2/1999 | A | CANC |
Tom Arcoraci
|
|
|
09/02/99 408 - done by 340
|
INSP - Foundation | 9/1/1999 | 9/1/1999 | 9/1/1999 | P | FAIL |
Carl Dependahl
|
|
|
09/01/99 340 - GREGG ###-####, FOOTING; RECALL, WILL NEED ENG'S CLARIFIC
|