Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberBLD98-02646
StatusExpired
Name A T & T (3RD FLOOR)
Site Address 619 W BANNOCK ST
Project NameAT&T BUILDING-3RD FL
Customer Number 
ePlanReviewNo
Description
To provide mechanical and electrical upgrades to the third & fifth floors and install new structural support base for a new chiller unit on the fourth level roof and all mechanical & electrical components to support the new systems. Work to include demolition of interior nonbearing walls and construction of new nonbearing walls of noncombustible one-hour construction to create new mechanical rooms, offices and storage. Under sprinkler ommissions allowed in section 3804 ('91 UBC) & Letter of agreement on file, the third floor will have a 1-hour occupancy separation wall with protection of penetrations & openings for all areas not a part of the telecommunications room(s) as indicated on plans. Telecomm Room is not sprinkled and has a complying smoke detection system throughout as regulated by the Fire Dept. The fifth floor is noted as being fully sprinkled. All per approved plans & agreement on file of Aug. 20, 1992. NOTE: Building is is in process of having code complying sprinkler, alarm & smoke detection systems, to be completed as a condition of final approval sign off of this permit.(P.C.#613-98)/drs
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Final5/17/20005/18/20005/18/2000APASS
Details
###-#### c/c#19340 5/19/00 8:29:25 AM
FIRE-Final Inspection5/17/20005/18/20005/18/2000APASS
DetailsRick Jackson
###-####
BLD-Final1/6/20001/7/20001/7/2000AFAIL
Details
CLIFF-- ###-#### FN OCC WITH 408 AND ALL CONTRS
FIRE-Final Inspection1/6/20001/7/20001/7/2000AFAIL
DetailsRick Jackson
CLIFF ###-#### FN OCC FIRE. Need items under permit Bld99-00224 completed first.
FIRE-Final Inspection1/3/20001/6/20001/6/2000AFAIL
DetailsRick Jackson
cliff ###-####. Need to complete items under BLD99-00224 for final. Tested vesda detection system- ok.
BLD-Conference11/1/199911/1/199911/1/1999APART
Details
Spoke with Don (super w/McAlcam) have been waiting on new doors and hardware- should call for final in next 10-20 days
INSP-Conference1/11/19991/11/19991/11/1999APART
DetailsRick Jackson
checked status of alarms told them to get approved plans; requested resubmittal on 1 hour wall by corridor
INSP - Framing/Rough-in12/3/199812/4/199812/4/1998APASS
Details
12/04/98 333 - FRAM-OK FRAMING