INSP - Final | 12/29/1998 | 12/30/1998 | 12/30/1998 | P | FAIL |
Wes Worcester
|
|
|
12/30/98 342 - TIM ###-#### given back to Carl
|
INSP - Final | 12/30/1998 | 12/30/1998 | 12/30/1998 | P | PASS |
Carl Dependahl
|
|
|
tim 3838384, lc issued.
|
INSP - Energy code compliance | 12/3/1998 | 12/3/1998 | 12/3/1998 | P | PART |
Carl Dependahl
|
|
|
need check underfloor for insul at final.
|
INSP - Framing/Rough-in | 12/3/1998 | 12/3/1998 | 12/3/1998 | A | PART |
Carl Dependahl
|
|
|
REPAIRS MADE, CHECK UNDERFLOOR AT FINAL (INSUL & BLOCKING.) OK TO COVER
|
INSP - Energy code compliance | 11/27/1998 | 11/27/1998 | 11/27/1998 | P | PART |
Carl Dependahl
|
|
|
tim ###-####...ok to cover, has frame c/n. check floor insul at final.
|
INSP - Framing/Rough-in | 11/27/1998 | 11/27/1998 | 11/27/1998 | P | PART |
Carl Dependahl
|
|
|
tim ###-####; add'l c/n, header missed at brg wall, add rotation & squash blocks at brg pony wall. header installed while onsite...ok to cover, check under floor at final.
|
INSP - Framing/Rough-in | 11/25/1998 | 11/25/1998 | 11/25/1998 | | FAIL |
Tom Arcoraci
|
|
|
/ / 408 - cn issued no plans on site
|
INSP - Framing/Rough-in | 11/24/1998 | 11/25/1998 | 11/25/1998 | A | FAIL |
Wes Worcester
|
|
|
11/25/98 342 - not even close to being ready pt lds, shr, stairs not brn tji's, brng of trusses, not nailed off, etc
|
INSP - Framing/Rough-in | 11/24/1998 | 11/24/1998 | 11/24/1998 | P | CANC |
Jim Sly
|
|
|
11/24/98 316 - Done by Tom A.
|
INSP - Foundation | 10/26/1998 | 10/27/1998 | 10/27/1998 | A | PART |
Carl Dependahl
|
|
|
DANE ###-#### poured looks ok
|