BLD-Conference | 8/15/2001 | 8/15/2001 | 8/15/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 8/15/2001 5:47:32 PM w/Tim, c/n ok.
|
Permanent Occupancy | | 8/15/2001 | 8/15/2001 | | DONE |
|
|
|
|
BLD-Final | 8/14/2001 | 8/14/2001 | 8/14/2001 | P | PASS |
Carl Dependahl
|
|
|
Tim Wilcomb, ###-#### - all items are now finished - reinspect; c/n ok...ok for c/o 8/16/2001 10:55:48 AM
|
BLD-Conference | 8/3/2001 | 8/3/2001 | 8/3/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 8/3/2001 8:13:49 AM w/ Cathy W. re status of c/n..will chk w/ contractor.
|
BLD-Conference | 7/11/2001 | 7/11/2001 | 7/11/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 7/11/2001 9:07:52 AM w/GS...need inform Wilcomb that c/n in effect and req's response ASAP.
|
BLD-Final | 6/20/2001 | 6/20/2001 | 6/20/2001 | A | FAIL |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 6/20/2001 9:21:33 AM c/n issued per G.S...ADA restrms 1st fl...boots at traps, w.c.to wall< 18" at 3rd fl; door at stair enclosure undercut at 3rd fl... astragal or? at 1st fl stair.
|
BLD-Conference | 6/6/2001 | 6/6/2001 | 6/6/2001 | A | CANC |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 6/6/2001 11:09:54 AM rec'd eng's letter
|
BLD-Conference | 5/24/2001 | 5/24/2001 | 5/24/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 5/24/2001 4:19:09 PM w/ Mike of Jordan-Wilcomb
|
BLD-Final | 5/21/2001 | 5/24/2001 | 5/24/2001 | P | FAIL |
Carl Dependahl
|
|
|
Please call Tim Wilcomb @ ###-#### 1st so he can meet you there...c/n need all plans/ notes 5/25/2001 11:03:26 AM
|
FIRE-Final Inspection | 5/7/2001 | 5/14/2001 | 5/14/2001 | A | PASS |
Rick Jackson
|
|
|
###-####
|
BLD-Framing/Rough-in | 3/23/2001 | 3/26/2001 | 3/26/2001 | A | PASS |
Jim Storey
|
|
|
###-#### ceilling on 1 and 4 floors at main entry ceilling ok. 3/26/2001 9:55:44 AM
|
BLD-Conference | 3/15/2001 | 3/16/2001 | 3/16/2001 | A | PASS |
Carl Dependahl
|
|
|
ceiling insp and conference ###-####...submit as built for floor/curtain wall detail by arch. 3/16/2001 12:13:49 PM
|
BLD-Framing/Rough-in | 3/16/2001 | 3/16/2001 | 3/16/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/16/2001 12:19:27 PM north side elev lobby grid & walls ok
|
BLD-Framing/Rough-in | 3/13/2001 | 3/14/2001 | 3/14/2001 | A | CANC |
Tony Young
|
|
|
ceiling seismic Mike Mason ###-####
Carl will do 3/14/2001 1:02:14 PM
|
BLD-Conference | 3/12/2001 | 3/12/2001 | 3/12/2001 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/12/2001 4:39:24 PM w/ arch, Steve Turney re curtain wall/ floor firestop, keep c/n....Contractor to recall insp
|
BLD-Framing/Rough-in | 3/9/2001 | 3/12/2001 | 3/12/2001 | A | CANC |
Tony Young
|
|
|
###-####
Carl has scheduled to go this afternoon per contractor, thanks Carl !!!! 3/12/2001 12:30:20 PM
|
BLD-Conference | 1/2/2001 | 1/2/2001 | 1/2/2001 | P | PASS |
George Slane
|
|
|
PROPANE EXPLOSION REAR STORAGE PORTION OF NEW ELKS REHAB BUILDING. WALL IN CONOPY AREA DISPLACED OVER 3 FEET, ONE SET OF DOUBLE DOORS BLOWN OFF WALL, MAJOR DAMAGE TO 2 EXTERIOR WALLS AND 2 INTERIOR WALLS AND CEILING. OK TO CLEAR AND STATE REBUILD ONCE FIRE AND POLICE COMPLETE INVESTIGATIONS AND RELEASE. OSHA IS ALSO IVOLVED. ONE WORKMAN INJURED.
|
FIRE-Conference | 5/17/2000 | 5/17/2000 | 5/17/2000 | A | PART |
Rick Jackson
|
|
|
|
BLD-Final | 5/12/2000 | 5/16/2000 | 5/16/2000 | A | PART |
|
|
|
###-#### GREEN MARKED AREAS OK FOR TEMP POOL AREA STILL NEED FINAL ON THE POOL 5/17/00 2:57:17 PM
|
FIRE-Final Inspection | 5/12/2000 | 5/16/2000 | 5/16/2000 | A | PART |
Rick Jackson
|
|
|
###-#### Shell okay; exiting issued. 5/17/00 1:53:56 PM
|
FIRE-Sprinkler Rough-in | 5/9/2000 | 5/11/2000 | 5/11/2000 | A | NR |
Rick Jackson
|
|
|
Mike ###-#### Will reschedule. 5/12/00 8:42:50 AM
|
BLD-Final | 4/12/2000 | 4/14/2000 | 4/14/2000 | P | PART |
|
|
|
Scheduled by Inspector: 338 On 04/12/2000 per mike made ok for temp on this section of 2rd and 2nd floors 04/17/2000
|
FIRE-Final Inspection | 4/14/2000 | 4/14/2000 | 4/14/2000 | P | PART |
Rick Jackson
|
|
|
okay to occupy 2nd floor a nad b areas only
|
FIRE-Conference | 4/12/2000 | 4/13/2000 | 4/13/2000 | A | NR |
Rick Jackson
|
|
|
Mike ###-#### Contractor called- not ready- door hardware 4/14/00 11:00:46 AM
|
BLD-Final | 4/7/2000 | 4/12/2000 | 4/12/2000 | A | FAIL |
|
|
|
###-#### need other agencies signoffs 04/12/2000
|
FIRE-Final Inspection | 4/7/2000 | 4/11/2000 | 4/11/2000 | A | FAIL |
Rick Jackson
|
|
|
###-#### Rated doors; exit signs; extinguishers; stail enclosures. 4/17/00 1:55:45 PM
|
BLD-Conference | 3/28/2000 | 3/29/2000 | 3/29/2000 | P | PART |
|
|
|
###-#### conf with 337, mike (jw) rob (me), rep of (tml) on the return air in the corridors, all area above ceiling cannot be used as a plenun -no execptions 3/30/00 10:11:29 AM
|
FIRE-Conference | 3/28/2000 | 3/29/2000 | 3/29/2000 | P | PART |
Rick Jackson
|
|
|
###-#### OK to keep fire damper at elevator machine room 3/30/00 11:03:02 AM
|
BLD-Conference | 3/24/2000 | 3/27/2000 | 3/27/2000 | A | PART |
|
|
|
mike mason ###-#### with 409 and mike on the temp occ of portions of the 2nd and 3rd floors, exit signage etc 03/27/2000 3:46:56 PM
|
FIRE-Conference | 3/27/2000 | 3/27/2000 | 3/27/2000 | A | PART |
Rick Jackson
|
|
|
discussed exit signs for 2 and 3 floors for phasing occupancy
|
BLD-Final | 3/17/2000 | 3/20/2000 | 3/20/2000 | A | PART |
|
|
|
###-#### exit sign clarification needed 03/20/2000 1:25:05 PM
|
BLD-Final | 3/20/2000 | 3/20/2000 | 3/20/2000 | P | PART |
|
|
|
blue markings on the ele plans are ok per discussion with drs each plan sheet is signed by me 03/21/2000 7:11:51 AM
|
FIRE-Final Inspection | 3/17/2000 | 3/17/2000 | 3/17/2000 | P | PART |
Rick Jackson
|
|
|
###-#### mike Phase 1 ok. 3/20/00 10:27:34 AM
|
BLD-Final | 3/13/2000 | 3/16/2000 | 3/16/2000 | A | FAIL |
|
|
|
Mike Mason ###-#### no one on site for insp 03/17/2000 9:08:19 AM
|
FIRE-Final Inspection | 3/13/2000 | 3/16/2000 | 3/16/2000 | A | PART |
Rick Jackson
|
|
|
Mike Mason ###-#### phase 1 okay
|
BLD-Framing/Rough-in | 2/2/2000 | 2/4/2000 | 2/4/2000 | A | PART |
|
|
|
ceiling grid insp--mike ###-#### ok to start laying in tiles as work proceeds in the first phase 2/10/00 10:17:50 AM
|
FIRE-Conference | 1/20/2000 | 1/21/2000 | 1/21/2000 | A | PART |
Rick Jackson
|
|
|
Mike Mason ###-#### Dampers require access doors; some not working. 1/21/00 1:54:25 PM
|
BLD-Conference | 1/14/2000 | 1/18/2000 | 1/18/2000 | A | PART |
|
|
|
at 9am Mike Mason ###-#### with mike and tim with jordan, with ymc and with bargreen ellison also isi 1/18/00 12:01:56 PM
|
BLD-Conference | 1/14/2000 | 1/18/2000 | 1/18/2000 | A | PASS |
|
|
|
###-####--mike for conf
|
BLD-Conference | 11/28/1999 | 12/28/1999 | 12/28/1999 | P | PART |
|
|
|
with mike with jordan wilcomb and ken with ymc the mech contractor, on the requirements for the domestic close dryer duct/vent penetrations of the 2-hour rated shaft. some protective work was done without approvals or resubmittals to the building dept. We discussed the required submittals for these changes. Contractors are submit assemblies for the penetrations and the type of ducting that is allowed for a domestic dryer with a booster fan. also the proper terminatio of the required rated construction of the shaft protection as the duct cannot have a fire/smoke damper.
|
BLD-Conference | 12/8/1999 | 12/8/1999 | 12/8/1999 | A | FAIL |
|
|
|
with arch steve turney on the submittals from the mech eng stating that with the eng seal that all would be well. I asked before I approved the submittal that the calculations done to arrive at the conclusion that the booster fan for the oversized over length to this date un approved spiral ducting that is proposed would be acceptable per the uniform mechanical code 1997. Also discussion on the rejection of the submittal for u.l. assembly for the penetration of this same duct through an required 2-hour shaft. it is ul/cul system no. wl7040. As this system utilizes #8x 3/4 sheet metal screws, and the umc states in 504.3.2 that " ducts for exausting clothes dryers shall not be connected or installed with sheet metal screws or fasteners which will obstruct the flow. Mr Turney suggested that rivits would be used. This is not acceptable without being part of the tested assy.
|
BLD-Other | 12/2/1999 | 12/2/1999 | 12/2/1999 | P | FAIL |
|
|
|
recieved submittal of penetration protection for 2-hour shaft wall using a square duct. as the duct has screws in it, it will not meet the requirements of a dryer duct which must be smooth. the fax submittal was marked not approved and re-faxed to steve t with zga arch. with a copy of the code section in chapter 5.
|
BLD-Conference | 11/29/1999 | 12/1/1999 | 12/1/1999 | P | PART |
|
|
|
with architect Steve on the assemblies and duct and shaft types and the assemblies required. He is to do research on the availability of an approved assembly for duct through a 2-hour rated shaft wall assy. Agreed that the new 3-m wrap material built shaft can terminate at the location just above the wall of the dryer/washer room and just above the booster fan as to not require demolition of the existing wall.
|
BLD-Conference | 11/30/1999 | 11/30/1999 | 11/30/1999 | A | PART |
|
|
|
questions on the dryer duct and penetrations of the 2-hour mech shaft.
|
BLD-Conference | 11/29/1999 | 11/29/1999 | 11/29/1999 | A | PART |
|
|
|
with mech contractor discussion of the rated system by 3M company. he is to get mech eng blessing before any more work done
|
FIRE-Sprinkler Rough-in | 10/21/1999 | 10/25/1999 | 10/25/1999 | A | FAIL |
Rick Jackson
|
|
|
MIKE-- ###-#### FIRE R/I Verified damper locations & sprinkler R/I
|
INSP - Framing/Rough-in | 8/23/1999 | 8/24/1999 | 8/24/1999 | A | PART |
|
|
|
madeo k to cover with other agencies approvals 08/24/99 407 - MIKE ###-####
|
INSP - Framing/Rough-in | 8/18/1999 | 8/19/1999 | 8/23/1999 | A | PEND |
|
|
|
jorden ###-#### cell fr insp-- NO ACTION TAKEN FOR CALLED INSP BY 407 THIS IS UPDATE BY 338 CONTR WILL CALL FOR INSP FOR 08/24/99
|
INSP - Framing/Rough-in | 6/14/1999 | 6/14/1999 | 6/14/1999 | P | CANC |
Russ Owen
|
|
|
06/14/99 407 - trans to 338.
|
INSP - Framing/Rough-in | 5/7/1999 | 5/7/1999 | 5/10/1999 | P | PART |
|
|
|
05/07/99 338 - ok to cover with ele div blessing
|
INSP-Conference | 4/7/1999 | 4/7/1999 | 4/7/1999 | P | PART |
Rick Jackson
|
|
|
profit meeting
|
INSP-Conference | 4/2/1999 | 4/2/1999 | 4/2/1999 | P | |
|
|
|
he just wants you to call him so he know when to get everything together mike mason/###-####
|