BLD-Final | 5/1/2000 | 5/4/2000 | 5/4/2000 | A | PASS |
|
|
|
###-#### Ron signed the perm col 5/4/00 4:34:25 PM
|
FIRE-Final Inspection | 5/1/2000 | 5/4/2000 | 5/4/2000 | A | PASS |
Rick Jackson
|
|
|
Ron ###-####
|
Permanent Occupancy | | 5/4/2000 | 5/4/2000 | | DONE |
|
|
|
|
BLD-Final | 3/3/2000 | 3/6/2000 | 3/6/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 03/03/2000 at 12:57:13. Contact: ###-####. made ok to occupy the fifth floor for 2-hours 3/7/00 7am to 9am 3/6/00 10:43:17 AM
|
FIRE-Final Inspection | 3/3/2000 | 3/6/2000 | 3/6/2000 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 03/03/2000 at 12:56:37. Contact: ###-####. Ok to use auditorium for 3/7/00 only. 3/6/00 1:49:56 PM
|
BLD-Final | 3/1/2000 | 3/2/2000 | 3/2/2000 | P | FAIL |
|
|
|
Scheduled by a contractor via Hello! on 03/01/2000 at 13:46:25. Contact: ###-####. 409 c/n in force ctr to recall when ready 3/2/00 3:49:56 PM
|
FIRE-Alarm Testing | 3/1/2000 | 3/2/2000 | 3/2/2000 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 03/01/2000 at 13:45:41. Contact: ###-####. Door houser relay not workin. 3/6/00 10:52:38 AM
|
FIRE-Final Inspection | 2/25/2000 | 2/28/2000 | 2/28/2000 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 02/25/2000 at 13:49:50. Contact: ###-####. Sprinkler r/I inspectionok to cove; miwar fire proofing. 2/28/00 2:42:46 PM
|
BLD-Wall cover | 2/11/2000 | 2/11/2000 | 2/11/2000 | P | PART |
|
|
|
Scheduled by a contractor via Hello! on 02/11/2000 at 10:16:35. Contact: ###-####. made ok to drop in ceiling tiles pending 409 signoff 2/11/00 5:25:09 PM
|
BLD-Conference | 2/3/2000 | 2/7/2000 | 2/7/2000 | A | PASS |
|
|
|
Scheduled by a contractor via Hello! on 02/03/2000 at 16:17:24. Contact: ###-####. need to have all systems working 2/10/00 10:10:08 AM
|
FIRE-Conference | 2/3/2000 | 2/7/2000 | 2/7/2000 | A | 409 |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 02/03/2000 at 16:18:06. Contact: ###-####. Discussed requirements for March 7 meeting
|
BLD-Final | 12/29/1999 | 1/3/2000 | 1/3/2000 | A | FAIL |
|
|
|
Scheduled by a contractor via Hello! on 12/29/1999 at 16:11:53. Contact: ###-####.this is to be a frame insp to review reqs for the ceiling system in area B north 1/2
|
BLD-Other | 1/3/2000 | 1/3/2000 | 1/3/2000 | A | PART |
|
|
|
MADE OK TO DROP IN TILES STILL TO RECIEVE INFO ON THE PERIMETER TRIM ON THE CLOUD AREAS
|
FIRE-Final Inspection | 12/29/1999 | 1/3/2000 | 1/3/2000 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/29/1999 at 16:12:40. Contact: ###-####. Sprinkler R/I inspection- ok to cover auditorium (North end).
|
BLD-Final | 12/29/1999 | 12/30/1999 | 12/30/1999 | A | PASS |
|
|
|
Scheduled by a contractor via Hello! on 12/29/1999 at 13:04:20. Contact: ###-####.made ok l/c #
|
BLD-Framing/Rough-in | 11/29/1999 | 11/29/1999 | 11/29/1999 | P | PART |
|
|
|
Scheduled by a contractor via Hello! on 11/29/1999 at 10:49:09. Contact: ###-####. Ok to cover area "B".
|
BLD-Framing/Rough-in | 11/12/1999 | 11/15/1999 | 11/15/1999 | A | PART |
|
|
|
ron--- ###-#### fr insp Ok for "C" ura coffee bar @ high ceiling.
|
FIRE-Sprinkler Rough-in | 11/10/1999 | 11/10/1999 | 11/10/1999 | P | PART |
Rick Jackson
|
|
|
ron-- ###-#### r/I Ok to cover area by elevator.
|
BLD-Wall cover | 9/20/1999 | 9/21/1999 | 9/21/1999 | A | PART |
|
|
|
RON ###-#### made ok to cover "G"
|
INSP - Wall cover | 9/2/1999 | 9/3/1999 | 9/3/1999 | A | PART |
|
|
|
09/03/99 338 - madeok to cover "a" "g" "f"
|
INSP - Framing/Rough-in | 8/16/1999 | 8/17/1999 | 8/17/1999 | A | PART |
|
|
|
RON ###-#### made ok to cover south stair tower ceiling
|
INSP - Wall cover | 8/13/1999 | 8/13/1999 | 8/13/1999 | P | PART |
|
|
|
08/13/99 338 - NEED RECALL FOR 08-1699
|
INSP - Framing/Rough-in | 8/9/1999 | 8/10/1999 | 8/11/1999 | A | FAIL |
|
|
|
08/10/99 338 - verbal c/n issued
|