BLD-Final | 10/20/2000 | 10/20/2000 | 10/20/2000 | P | PASS |
|
|
|
c/n removed
|
Permanent Occupancy | | 10/20/2000 | 10/20/2000 | | DONE |
|
|
|
|
BLD-Final | 7/13/2000 | 7/13/2000 | 7/13/2000 | P | CANC |
|
|
|
ottie ###-#### resched for 6/14/2k 7/13/2000 2:12:13 PM
|
BLD-Final | 7/13/2000 | 7/13/2000 | 7/13/2000 | P | CANC |
|
|
|
Scheduled by Inspector: 338 On 7/13/2000 odie867-10 7/13/2000 2:11:30 PM
|
BLD-Final | 6/7/2000 | 6/8/2000 | 6/8/2000 | P | FAIL |
|
|
|
tim 8677610 rated doors must latch at the bottom 6/8/00 9:59:46 AM
|
FIRE-Final Inspection | 6/7/2000 | 6/8/2000 | 6/8/2000 | A | PASS |
Rick Jackson
|
|
|
tim ###-####
|
BLD-Framing/Rough-in | 9/22/1999 | 9/22/1999 | 2/15/2000 | P | PASS |
|
|
|
ok tfor the shaft wall
|
BLD-Final | 2/11/2000 | 2/11/2000 | 2/11/2000 | P | PART |
|
|
|
Scheduled by a contractor via Hello! on 02/11/2000 at 10:35:29. Contact: ###-####. signed the occ req card temp col for str. still need code enforcement and achd 2/11/00 5:41:54 PM
|
FIRE-Final Inspection | 2/9/2000 | 2/10/2000 | 2/10/2000 | A | FAIL |
Rick Jackson
|
|
|
per rick 10:30---lea elec ###-#### mark--fn fire. Need to test audible /visual alarms.
|
BLD-Final | 2/8/2000 | 2/8/2000 | 2/8/2000 | P | FAIL |
|
|
|
Scheduled by a contractor via Hello! on 02/08/2000 at 11:17:24. Contact: ###-####. need door hardware adjustment 2/10/00 10:01:51 AM
|
BLD-Other | 2/3/2000 | 2/8/2000 | 2/8/2000 | P | FAIL |
|
|
|
Scheduled by a contractor via Hello! on 02/03/2000 at 13:43:22. Contact: ###-####. still need fire alarm system in service and all door hardware must operate 2/10/00 10:01:18 AM
|
FIRE-Final Inspection | 2/7/2000 | 2/7/2000 | 2/7/2000 | P | 409 |
Rick Jackson
|
|
|
russ ###-#### not a final sprinkler R/I hydro okay on 6th floor
|
FIRE-Hydro test above ground | 2/3/2000 | 2/4/2000 | 2/4/2000 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 02/03/2000 at 13:41:26. Contact: ###-####. 6th floor hydro ok. 2/7/00 8:48:08 AM
|
FIRE-Conference | 1/6/2000 | 1/6/2000 | 1/6/2000 | A | PART |
Rick Jackson
|
|
|
met with owner, architect, Perry, Carl Westphal, Dave Miller, Ren Ross to determine occupancy requirements. alarms to be complete and pump controller installed within a few weeks - it doesn't appear any items won't be complete. will keep Dave Miller up to date as needed.
|
FIRE-Sprinkler Rough-in | 12/27/1999 | 12/27/1999 | 12/28/1999 | P | PART |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/27/1999 at 09:05:57. Contact: ###-####. Ok to cover hard lids; need sway bracing on stand pipes.
|
BLD-Framing/Rough-in | 11/22/1999 | 11/22/1999 | 11/23/1999 | P | FAIL |
|
|
|
floor inspection odie ###-#### Need to protect raised floor- full non combustable fill required in raised floors.
|
FIRE-Sprinkler Rough-in | 11/3/1999 | 11/3/1999 | 11/3/1999 | P | PART |
Rick Jackson
|
|
|
Ok to cover east wing- suites only. Verify spacing/sprinkler heads for N. wing
|
BLD-Framing/Rough-in | 11/2/1999 | 11/3/1999 | 11/2/1999 | A | CANC |
Rick Jackson
|
|
|
###-#### Not for fire inspection
|
BLD-Framing/Rough-in | 11/1/1999 | 11/2/1999 | 11/2/1999 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 11/01/1999 at 13:45:55. Contact: ###-####. made ok to cover with fire approvals
|
BLD-Framing/Rough-in | 10/11/1999 | 10/12/1999 | 10/13/1999 | A | PART |
|
|
|
odie--- ###-#### 3 hr shaft insp Shaft walls ok
|
INSP - Framing/Rough-in | 8/25/1999 | 8/25/1999 | 8/25/1999 | | PART |
|
|
|
08/24/99 338 - for the ext wall firrunf
|
INSP-Conference | 8/25/1999 | 8/25/1999 | 8/25/1999 | A | PART |
Rick Jackson
|
|
|
went with Perry to check status - plans are on 6th floor; reviewed conditions for occupancy with Steed
|