BLD-Final | 1/10/2000 | 1/10/2000 | 1/10/2000 | P | PART |
Russ Owen
|
|
|
Pending engineers approval of special inspection report.
|
BLD-Final | 1/6/2000 | 1/7/2000 | 1/7/2000 | P | PART |
Russ Owen
|
|
|
mike ###-#### call first to meet there. Need engineers approval of special inspection reports.
|
BLD-Framing/Rough-in | 9/17/1999 | 9/20/1999 | 1/7/2000 | A | PASS |
Russ Owen
|
|
|
mike-- ###-#### fr insp
|
BLD-Final | 12/23/1999 | 12/23/1999 | 12/23/1999 | P | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 12/23/1999 at 08:46:09. Contact: ###-####. Need public works.
|
FIRE-Final Inspection | 12/9/1999 | 12/10/1999 | 12/10/1999 | A | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/09/1999 at 09:43:12. Contact: ###-####. Occupancy approved.
|
FIRE-Sprinkler Rough-in | 12/2/1999 | 12/2/1999 | 12/2/1999 | P | FAIL |
Rick Jackson
|
|
|
alan ###-#### hydro stat test unit 100 Hydro okay; sway bracing not complete; FDC.
|
BLD-Conference | 11/23/1999 | 11/24/1999 | 11/24/1999 | A | PART |
Russ Owen
|
|
|
Mike ###-#### Pre-inspection only.
|
BLD-Conference | 11/2/1999 | 11/3/1999 | 11/2/1999 | A | PART |
Rick Jackson
|
|
|
mike ###-#### conf insp Address problems; sprinkler issues.
|
BLD-Conference | 9/27/1999 | 9/27/1999 | 9/27/1999 | P | FAIL |
Bob Archibald
|
|
|
Returned and Left phone message w/Scott that any wood framing would result in SWO.
|
BLD-Framing/Rough-in | 9/27/1999 | 9/27/1999 | 9/27/1999 | A | FAIL |
Bob Archibald
|
|
|
Conference w/Mike at job site wood framing to cease and any wood framing will result in SWO of entire job. Framers pulled off roof.
|
BLD-Framing/Rough-in | 9/21/1999 | 9/21/1999 | 9/21/1999 | P | PART |
Carl Dependahl
|
|
|
###-#### mike upper parapet ok to cover center building.
|
INSP - Foundation | 5/14/1999 | 5/14/1999 | 5/14/1999 | P | PART |
Russ Owen
|
|
|
05/14/99 407 - special insp.ok.
|
INSP - Concrete | 5/10/1999 | 5/11/1999 | 5/11/1999 | A | PART |
Russ Owen
|
|
|
05/11/99 407 - subject to special inspection.
|
INSP - Concrete | 5/6/1999 | 5/6/1999 | 5/6/1999 | P | PART |
Russ Owen
|
|
|
05/06/99 407 - rebar clearance needed,corrections being made,special ins
|
INSP - Foundation | 4/27/1999 | 4/28/1999 | 4/28/1999 | A | PART |
Russ Owen
|
|
|
04/28/99 407 - ok subject to special inspector,who is on site now.
|