BLD-Final | 9/28/1999 | 9/29/1999 | 9/30/1999 | A | PASS |
Jim Storey
|
|
|
Dan ###-#### ok for perm. Occ.
|
Permanent Occupancy | | 9/29/1999 | 9/29/1999 | | DONE |
|
|
|
|
FIRE-Final Inspection | 9/27/1999 | 9/28/1999 | 9/28/1999 | A | PASS |
Rick Jackson
|
|
|
RE-INSP FN-DAN ###-#### Occupancy approved
|
INSP - Final | 9/10/1999 | 9/10/1999 | 9/10/1999 | P | PART |
Jim Storey
|
|
|
safety glazing not installed for sidelights
|
INSP - Final | 9/9/1999 | 9/9/1999 | 9/9/1999 | A | NR |
|
|
|
CONTRACTOR NOT READY
|
INSP-Final Inspection | 9/8/1999 | 9/9/1999 | 9/9/1999 | P | FAIL |
Rick Jackson
|
|
|
EXIT DOOR HARDWARE; EXTINGUISHERS
|
INSP - Concrete | 6/15/1999 | 6/15/1999 | 6/15/1999 | | PASS |
Jim Storey
|
|
|
06/15/99 301 - ###-#### JOEL//REBAR
|
INSP - Foundation | 6/4/1999 | 6/7/1999 | 6/7/1999 | A | PART |
Jim Storey
|
|
|
06/07/99 301 - EAST FOOTING AND NORTH BLBG FOOTING OK PENDING SPECIAL IN
|
INSP - Foundation | 6/2/1999 | 6/2/1999 | 6/2/1999 | | PASS |
Jim Storey
|
|
|
06/02/99 301 - Joel ###-####
|
INSP - Foundation | 5/18/1999 | 5/19/1999 | 5/19/1999 | P | PART |
Jim Storey
|
|
|
05/19/99 301 - ok for cover pending strata report.
|