BLD-Final | 5/17/2000 | 5/18/2000 | 5/18/2000 | A | PASS |
Tom Arcoraci
|
|
|
Scheduled by a contractor via Hello! on 05/17/2000 at 11:02:23. Contact: ###-####. ok for perm. 5/18/00 3:16:13 PM
|
BLD-Final | 5/17/2000 | 5/17/2000 | 5/17/2000 | P | CANC |
Carl Dependahl
|
|
|
###-#### Recall per. cont. 5/18/00 3:04:23 PM
|
BLD-Final | 5/15/2000 | 5/16/2000 | 5/16/2000 | A | NR |
Carl Dependahl
|
|
|
###-#### recall when ready 5/17/00 1:56:21 PM
|
FIRE-Final Inspection | 5/11/2000 | 5/12/2000 | 5/12/2000 | A | PASS |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 05/11/2000 at 09:09:51. Contact: ###-####. Reinsp. ok for perm. occ. 5/12/00 2:05:59 PM
|
FIRE-Final Inspection | 2/16/2000 | 2/17/2000 | 2/17/2000 | A | FAIL |
Joe Tawney
|
|
|
###-#### food court Final fail smoke evac system. 2/17/00 2:15:37 PM
|
BLD-Conference | 2/3/2000 | 2/3/2000 | 2/3/2000 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 02/03/2000 at 10:34:50. Contact: ###-####. W/supt. (EKC) still has alarm problems w/simplex, will call when resolved. Rec'd arch's letter. 2/4/00 11:52:15 AM
|
BLD-Conference | 9/23/1999 | 9/23/1999 | 9/23/1999 | P | PASS |
Carl Dependahl
|
|
|
Complete all door hardware, etc. at corridor w/bldr and Joe Tawney re: final
|
BLD-Conference | 9/21/1999 | 9/21/1999 | 9/21/1999 | P | PART |
Carl Dependahl
|
|
|
CONF W/ BLDR RE ENG'G REQUESTED FOR STRUCT STEEL.
|
FIRE-Final Inspection | 9/15/1999 | 9/16/1999 | 9/16/1999 | P | FAIL |
Joe Tawney
|
|
|
COMPLETE EXIT CORRIDOR, SCHEDULE TEST OF SMOKE EVAC SYSTEM, ADD 1 FIRE EXIT
|
INSP - Framing/Rough-in | 8/30/1999 | 8/31/1999 | 8/31/1999 | A | NR |
Carl Dependahl
|
|
|
08/31/99 340 - CEILING TILE ###-####; 1hr grid, need listing info
|
INSP - Framing/ Rough-in | 8/27/1999 | 8/27/1999 | 8/27/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - OK TO COVER BACK CORR WALLS; TO BE 1HR GRID PER SUPT.
|
INSP - Framing/ Rough-in | 8/18/1999 | 8/18/1999 | 8/18/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - OK TO 1 SIDE CORRIDOR AT SOUTH SIDE (TO STORAGE AREA)
|
INSP - Framing/ Rough-in | 8/17/1999 | 8/17/1999 | 8/17/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - MAIN SEATING AREA OK, PEND ENGS REPORT FOR STRUCTURAL STEEL
|
INSP - Framing/ Rough-in | 8/10/1999 | 8/10/1999 | 8/10/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - REVIEWED SPEC INSP, NEED ENG'S OK PER REPORT( STEEL CONNECTI
|
INSP - Framing/ Rough-in | 7/16/1999 | 7/16/1999 | 7/16/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - GYP OK, NEED RESOLVE CORR. LID & ENG'S CONNECTION REQ'S. OK
|
INSP-Conference | 7/12/1999 | 7/12/1999 | 7/12/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - CONF W/ B ALEXANDER ON SPKLR COVERAGE
|
INSP - Framing/Rough-in | 6/23/1999 | 6/29/1999 | 6/29/1999 | A | PART |
Carl Dependahl
|
|
|
06/29/99 340 - ###-####; ok to continue soffits, need eng's "list" for s
|
INSP - Framing/Rough-in | 6/23/1999 | 6/28/1999 | 6/28/1999 | A | FAIL |
Carl Dependahl
|
|
|
06/28/99 340 - ###-#### need seal smoke barrier, codrridor, & eng's lett
|
INSP-Sprinkler Rough-in/Hydro | 6/28/1999 | 6/28/1999 | 6/28/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON PARTIAL ROUGH IN
|
INSP - Framing/Rough-in | 6/23/1999 | 6/25/1999 | 6/25/1999 | A | PART |
Carl Dependahl
|
|
|
06/25/99 340 - ###-####; ok to continue soffit cover, need eng's" list"
|
INSP - Framing/Rough-in | 6/23/1999 | 6/24/1999 | 6/24/1999 | A | PART |
Carl Dependahl
|
|
|
06/24/99 340 - ###-#### back of bulkhead, braces installed at perimeter,
|
INSP-Sprinkler Rough-in/Hydro | 6/24/1999 | 6/24/1999 | 6/24/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON PARTIAL ROUGH IN
|
INSP - Framing/Rough-in | 6/23/1999 | 6/23/1999 | 6/24/1999 | P | PART |
Carl Dependahl
|
|
|
06/23/99 340 - ###-####; OK TO COVER LOWER SOFFIT/ KEEP C/N
|
INSP - Framing/ Rough-in | 6/23/1999 | 6/23/1999 | 6/23/1999 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - INSTALL KICKERS, BRACES; SEAL SMOKE BARRIERS
|
INSP - Framing/Rough-in | 6/21/1999 | 6/22/1999 | 6/22/1999 | A | PART |
Carl Dependahl
|
|
|
06/22/99 340 - FOOD COURT CARL ###-#### soffit area up to "steak" shop;
|
INSP - Framing/Rough-in | 6/21/1999 | 6/21/1999 | 6/21/1999 | P | PART |
Carl Dependahl
|
|
|
06/21/99 340 - CARL ###-####; OK TO BEGIN COVER SOFFIT AREA; KEEP C/N FO
|
INSP-Sprinkler Rough-in/Hydro | 6/17/1999 | 6/17/1999 | 6/17/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - OK ON PARTIAL SPKLR ROUGH IN DOME AREA
|
INSP - Framing/ Rough-in | 6/14/1999 | 6/14/1999 | 6/14/1999 | | PART |
Carl Dependahl
|
|
|
/ / 340 - CONF W/ FRAMER; AWAITING DETAIL. NO COVER TIL ELEC & FIRE
|
INSP - Framing/Rough-in | 6/11/1999 | 6/11/1999 | 6/11/1999 | P | FAIL |
Carl Dependahl
|
|
|
keep c/n; conf w/ framer, will fax detail for review
|
INSP - Framing/Rough-in | 6/9/1999 | 6/10/1999 | 6/10/1999 | A | FAIL |
Carl Dependahl
|
|
|
06/10/99 340 - ###-#### KARL//FRAMING; NEED ENG'S LIST FOR STRUCT STEEL;
|
INSP - Foundation | 5/27/1999 | 5/28/1999 | 5/28/1999 | A | PART |
Carl Dependahl
|
|
|
pouring at 8 Karl ###-####
|
INSP-Conference | 5/13/1999 | 5/13/1999 | 5/13/1999 | | PART |
Joe Tawney
|
|
|
/ / 406 - CONF W/ BRIAN ELLSWORTH REG NOT FINDING WATCH SERVICE AT FOO
|
INSP-Conference | 4/27/1999 | 4/27/1999 | 4/27/1999 | | PART |
|
|
|
CONF W/BRIAN ELLSWORTH OF EKC CONSTR ON DEMO SAFETY ISSUES. WILL ADV ON SCAFFOLDING
|