Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberBLD99-01038
StatusExpired
Name BETSY LLOYD
Site Address 312 S 9TH ST
Project NameFOSTER GARAGE-FNDTN
Customer Number 
ePlanReviewNo
Description
FOSTER BLOCK PARKING GARAGE (FOUNDATION PERMIT) - TO DRILL AND POUR REINFORCED CONCRETE CAISSONS FOR THE FOUNDATION STRUCTURAL SUPPORT OF THE FUTURE PROPOSED EIGHT TIER FOSTER BLOCK PARKING GARAGE. ALL CONSTRUCTION PER THE APPROVED ENGINEERED PLANS ON FILE. WORK UNDER THIS PERMIT MAY NOT PROCEED BEYOND THE POUR OF CAISSONS UNTIL THE FINAL APPROVAL AND ISSUANCE OF THE FULL PARKING GARAGE BUILDING PERMIT. 06/08/99 PERMIT MODIFICATION - THIS PERMIT IS BEING MODIFIED TO INCLUDE THE CONSTRUCTION OF THE REINFORCED CONCRETE FOUNDATION/PILE CAPS AND BASEMENT WALL PORTIONS OF THIS PROJECT. WORK UNDER THIS PERMIT MAY NOT PROCEED BEYOND THE POUR OF THE FOUNDATION/PILE CAPS AND BASEMENT WALLS UNTIL THE FINAL APPROVAL AND ISSUANCE OF THE FULL PARKING GARAGE BUILDING PERMIT. AS OWNER OR DESIGNATED AGENT, I ACKNOWLEDGE THAT I AGREE TO MAKE ANY MODIFICATIONS TO THE EARLY FOUNDATION WORK, AS MAY BE REQUIRED, TO COMPLY WITH CITY CODES AND THE FINAL APPROVED BUILDING PLANS AND CONDITIONS. ALL PER ENGINEERED PLANS ON FILE. DRH98-0244/PC#273-99/GRADING PERMIT BLD99-1262/JCM.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
BLD-Concrete10/19/199910/20/199910/20/1999APART
Details
for columns--- a2, a3, b4, c5, d6 -----###-#### -dave - Made ok w/spec. insp. Blessing
BLD-Concrete10/18/199910/18/199910/18/1999PPART
Details
grid line 2, columns k, l , m , n--dave-- ###-#### R-bar placed special insp. Ok
BLD-Concrete10/13/199910/13/199910/13/1999PPART
Details
grid line G from 1.30 to 2 line Made ok with sp. Insp. Approval
BLD-Concrete10/7/199910/7/199910/7/1999PPART
Details
grid line G from grid line 1 to 1.60 grid line N grid line 1 to 1.1 r-bar placed spec insp approval req
BLD-Concrete10/1/199910/4/199910/4/1999APART
Details
from grid line 2 to 1 on C line. grade beam 1 sp insp re bar placed
###-####
BLD-Concrete9/29/19999/29/19999/29/1999PPART
Details
GRID LINES 1-A TO G GRID LINE 2 D TO G COLUMNS ###-#### R-bar placed, spec approval required
BLD-Concrete9/24/19999/27/19999/27/1999PPART
Details
REBAR INSP- TOM- ###-#### R-Bar placed sp. Insp. Approval ok
BLD-Footing9/23/19999/24/19999/24/1999APART
Details
TOM ###-#### Made ok with spec. insp. Approval
BLD-Foundation9/23/19999/24/19999/24/1999APART
Details
TOM-- ###-#### FOUND WALL INSP Made ok with spec. insp. Approval/ R-bar replaced
BLD-Concrete9/20/19999/21/19999/21/1999PPART
Details
tom-- ###-#### concrete wall insp-k1 to n 1 Made ok with special insp. Approval
BLD-Concrete9/17/19999/20/19999/20/1999APART
Details
made ok spill insp
BLD-Concrete9/17/19999/17/19999/17/1999PPART
Details
CONCRETE WALLS DAVE ###-#### ELEVATOR BASEMENT AREAmade ok r-bar placed sp insp ok
BLD-Framing/Rough-in9/15/19999/16/19999/16/1999APART
Details
###-####- krisenbeck -grid 1 colums j k & l--- grid line 2 column b - MADE OK WITH SPCL INSPCTN APPROVAL
INSP - Foundation9/13/19999/13/19999/13/1999PPART
Details
grid line 1 e-f-h-m ###-#### sp insp made ok
INSP - Concrete8/30/19998/30/19998/30/1999PPART
Details
08/30/99 338 - DAVE ###-#### GRID LINES G 1-2 GRID LINE C 1-2 FOOTING ON 1 GRID LINE B madeok with sp insp approval
INSP - Concrete8/23/19998/23/19998/23/1999PPART
Details
08/23/99 338 - TOM.###-####BETWEEN N6-G6 & N2-K2. PILE CAPSF6,E6,D6,B2.
INSP - Foundation8/17/19998/18/19998/18/1999APASS
DetailsJim Storey
08/18/99 301 - dave ###-#### footing, grid line1 c-f & elevator
INSP - Foundation8/16/19998/17/19998/17/1999PCANC
Details
GRID LINES 1, C - G. canc at 11:34.
INSP - Foundation8/16/19998/16/19998/16/1999PPART
Details
08/16/99 338 - FOOTING GRID LINES 1,H - N,r-bar placed per plan sp insp
INSP - Foundation8/10/19998/10/19998/10/1999PFAIL
DetailsWes Worcester
08/10/99 342 - GRID LINE 2 C D E F G M N. DAVE ###-#### given to Perry
INSP - Concrete8/3/19998/6/19998/6/1999APART
Details
PIER CAP GRID LINE 6 THRU G / ###-####
INSP - Concrete8/4/19998/6/19998/5/1999PPART
Details
08/06/99 338 - DAVE CASE ON CAPS ###-#### r-bar placed sp insp made ok
INSP - Foundation7/1/19997/1/19997/1/1999
Details
cason pours continuing ok
INSP - Concrete6/28/19996/29/19996/28/1999APART
Details
06/29/99 338 - Grid line 2 north and south Grid line H left grid line 6 north grid line K right and left
INSP - Concrete6/25/19996/28/19996/28/1999APART
Details
06/28/99 338 - grid lines 2 south grid line L left and right ok with sp
INSP - Concrete6/28/19996/28/19996/28/1999PPART
Details
06/28/99 338 - Grid line 2 north and south Grid line H right madeok with sp insp appr.
INSP - Concrete6/28/19996/28/19996/28/1999PPART
Details
06/28/99 338 - grid line 6 north grid line L left made ok with sp insp a
INSP - Concrete6/25/19996/25/19996/25/1999PPART
Details
06/25/99 338 - grid line 2 north and south grid line J left made ok with
INSP - Concrete6/24/19996/24/19996/24/1999PPART
Details
06/24/99 338 - CAISONS//GRIDLINE 6 NORTH & SOUTH GRIDLINE L RIGHT r-bar
INSP - Concrete6/23/19996/24/19996/24/1999APART
Details
06/24/99 338 - grid line 2 north and south grid line J right ok to pour
INSP - Concrete6/22/19996/23/19996/23/1999APART
Details
06/23/99 338 - 06/23/99 338 - grid line 2 north grid line L left and rig ###-#### ok r-bar placed SP INSP
INSP - Foundation6/23/19996/23/19996/23/1999PPART
Details
06/23/99 338 - ###-####//CAISONS GRIDLINE 6 NORTH GRIDLINE N RIGHT & LEFT SP INSP
INSP - Concrete6/21/19996/22/19996/22/1999APART
Details
06/22/99 338 - /CAISONS GRIDLINE 2 SOUTH GRIDLINE N LEFT & RIGHT
INSP - Concrete6/18/19996/21/19996/21/1999APART
Details
06/21/99 338 - CAISONS GRIDLINE 2 SOUTH GRIDLINE K LEFT & RIGHT sp insp ok
INSP - Foundation6/21/19996/21/19996/21/1999
starting 6 foot casons work proceeding on schedule perry i and dave reedar reviewd change in rebar placement on specific detail dave was getting engineer approval on
INSP - Concrete6/17/19996/18/19996/18/1999APART
Details
06/18/99 338 - grid line 2 north grid line K right and left ###-#### made ok sp insp appr.
INSP - Concrete6/18/19996/18/19996/18/1999P
Details
###-#### DAVE// CAISONS GRIDLINE 2 CENTER GRIDLINE N LEFT GRIDLINE 6 SOUTH GRIDLINE N LEFT & RIGHT GRIDLINE 2 NORTH GRIDLINE K LEFT & RIGHT
INSP - Concrete6/17/19996/17/19996/17/1999PPART
Details
grid line 6 south grid line K right grid line L left ###-#### made ok with sp insp approval
INSP - Concrete6/16/19996/17/19996/17/1999APART
Details
###-#### dave//caisons gridline 2 center & north gridline m left madeok to pour with sp insp approval
INSP - Concrete6/16/19996/16/19996/16/1999P
Details
###-#### dave// caisons gridline 2 center & north gridline n right Resaigned by 325.
INSP - Concrete6/15/19996/16/19996/16/1999APART
Details
06/16/99 338 - grid line 6 north on a M line left and right made ok with
INSP - Concrete6/15/19996/15/19996/15/1999PPART
Details
06/15/99 338 - ###-#### DAVE//CAISONS GRIDLINE 6 NORTH J RIGHT GRIDLINE LEFT
INSP - Concrete6/15/19996/15/19996/15/1999 PART
Details
06/15/99 338 - GRID LINE 2 GRID LINE M RIGHT made ok with sp insp approv
INSP - Concrete6/14/19996/15/19996/15/1999APART
Details
06/15/99 338 - GRID LINE 2 GRID LINE M RIGHT ok with sp insp app
INSP - Concrete6/14/19996/14/19996/14/1999PPART
Details
Grid line 6 north and south Grid line J left and right made ok with sp insp approval
INSP - Concrete6/11/19996/14/19996/14/1999APART
Details
06/14/99 338 - made ok with sp insppapproval
INSP - Concrete6/11/19996/11/19996/11/1999PPART
DetailsWes Worcester
06/11/99 342 - Grid line 6 South M left and right special inspector on s
INSP - Foundation6/11/19996/11/19996/11/1999PPART
DetailsWes Worcester
06/11/99 342 - ###-####//CAISONS GRID LINE 6 NORTH G LINE RIGHT H LINE LEFT spec insp on site
INSP - Concrete6/10/19996/10/19996/10/1999PPART
DetailsJim Storey
06/10/99 301 - grid lines 6 north grid line E right F left ###-#### pend
INSP - Foundation6/9/19996/10/19996/10/1999APART
DetailsWes Worcester
06/10/99 342 - ###-####//CAISONS GRIDLINE 6 NORTH & SOUTH GRIDLINE H RIGHT GRIDLINE J LEFT
INSP - Foundation6/9/19996/9/19996/9/1999PPART
DetailsJim Storey
06/09/99 301 - Grid line A and 1 Grid line 6 north and grid D left and E
INSP - Foundation6/8/19996/9/19996/9/1999AFAIL
DetailsWes Worcester
06/08/99 342 - no answer, spec insp to assess collapsed soils at caison
INSP - Foundation6/7/19996/8/19996/8/1999AFAIL
DetailsWes Worcester
06/08/99 342 - ###-####//CAISONS*GRID 6 SO H LINE no answer, dirt has ca
INSP - Foundation6/7/19996/8/19996/8/1999PPART
DetailsWes Worcester
06/08/99 342 - ###-####/no one at site, no answer/CAISONS GRID LINES A G
INSP - Foundation6/8/19996/8/19996/8/1999PPART
DetailsJim Storey
06/08/99 301 - Dave ###-#### grid line A and 1 north 9 ft. Grid line A a
INSP - Concrete6/4/19996/7/19996/5/1999APART
Details
06/07/99 338 - grid line 6 grid line H South left and right madeok to po
INSP - Concrete6/4/19996/4/19996/4/1999PPART
Details
06/04/99 338 - 3:00 PLEASE ###-#### GRID LINES 6 AND D SOUTH LEFT 6 AND F SOUTH RIGHT AND LEFT made ok to pour with sp inspapproval
INSP - Concrete6/3/19996/3/19996/3/1999PPART
Details
06/03/99 338 - Dave ###-#### grid line A and 2.9 and 1.1 and .40 ft and grid line C .14 ft grid line 5.4 ft and B .9 ft made ok with sp insp approvals
INSP - Concrete5/28/19995/28/19995/28/1999PPART
Details
05/28/99 338 - madeok for casson pour with sp insp approvals
INSP - Foundation8/23/19998/23/19993/23/1999PPART
Details
08/23/99 338 - TOM###-####.BETWEEN N6-G6 & N2-K2.PILE CAPS F6,E6,D6,B2