BLD-Concrete | 10/19/1999 | 10/20/1999 | 10/20/1999 | A | PART |
|
|
|
for columns--- a2, a3, b4, c5, d6 -----###-#### -dave - Made ok w/spec. insp. Blessing
|
BLD-Concrete | 10/18/1999 | 10/18/1999 | 10/18/1999 | P | PART |
|
|
|
grid line 2, columns k, l , m , n--dave-- ###-#### R-bar placed special insp. Ok
|
BLD-Concrete | 10/13/1999 | 10/13/1999 | 10/13/1999 | P | PART |
|
|
|
grid line G from 1.30 to 2 line Made ok with sp. Insp. Approval
|
BLD-Concrete | 10/7/1999 | 10/7/1999 | 10/7/1999 | P | PART |
|
|
|
grid line G from grid line 1 to 1.60 grid line N grid line 1 to 1.1 r-bar placed spec insp approval req
|
BLD-Concrete | 10/1/1999 | 10/4/1999 | 10/4/1999 | A | PART |
|
|
|
from grid line 2 to 1 on C line. grade beam 1 sp insp re bar placed
###-####
|
BLD-Concrete | 9/29/1999 | 9/29/1999 | 9/29/1999 | P | PART |
|
|
|
GRID LINES 1-A TO G GRID LINE 2 D TO G COLUMNS ###-#### R-bar placed, spec approval required
|
BLD-Concrete | 9/24/1999 | 9/27/1999 | 9/27/1999 | P | PART |
|
|
|
REBAR INSP- TOM- ###-#### R-Bar placed sp. Insp. Approval ok
|
BLD-Footing | 9/23/1999 | 9/24/1999 | 9/24/1999 | A | PART |
|
|
|
TOM ###-#### Made ok with spec. insp. Approval
|
BLD-Foundation | 9/23/1999 | 9/24/1999 | 9/24/1999 | A | PART |
|
|
|
TOM-- ###-#### FOUND WALL INSP Made ok with spec. insp. Approval/ R-bar replaced
|
BLD-Concrete | 9/20/1999 | 9/21/1999 | 9/21/1999 | P | PART |
|
|
|
tom-- ###-#### concrete wall insp-k1 to n 1 Made ok with special insp. Approval
|
BLD-Concrete | 9/17/1999 | 9/20/1999 | 9/20/1999 | A | PART |
|
|
|
made ok spill insp
|
BLD-Concrete | 9/17/1999 | 9/17/1999 | 9/17/1999 | P | PART |
|
|
|
CONCRETE WALLS DAVE ###-#### ELEVATOR BASEMENT AREAmade ok r-bar placed sp insp ok
|
BLD-Framing/Rough-in | 9/15/1999 | 9/16/1999 | 9/16/1999 | A | PART |
|
|
|
###-####- krisenbeck -grid 1 colums j k & l--- grid line 2 column b - MADE OK WITH SPCL INSPCTN APPROVAL
|
INSP - Foundation | 9/13/1999 | 9/13/1999 | 9/13/1999 | P | PART |
|
|
|
grid line 1 e-f-h-m ###-#### sp insp made ok
|
INSP - Concrete | 8/30/1999 | 8/30/1999 | 8/30/1999 | P | PART |
|
|
|
08/30/99 338 - DAVE ###-#### GRID LINES G 1-2 GRID LINE C 1-2 FOOTING ON 1 GRID LINE B madeok with sp insp approval
|
INSP - Concrete | 8/23/1999 | 8/23/1999 | 8/23/1999 | P | PART |
|
|
|
08/23/99 338 - TOM.###-####BETWEEN N6-G6 & N2-K2. PILE CAPSF6,E6,D6,B2.
|
INSP - Foundation | 8/17/1999 | 8/18/1999 | 8/18/1999 | A | PASS |
Jim Storey
|
|
|
08/18/99 301 - dave ###-#### footing, grid line1 c-f & elevator
|
INSP - Foundation | 8/16/1999 | 8/17/1999 | 8/17/1999 | P | CANC |
|
|
|
GRID LINES 1, C - G. canc at 11:34.
|
INSP - Foundation | 8/16/1999 | 8/16/1999 | 8/16/1999 | P | PART |
|
|
|
08/16/99 338 - FOOTING GRID LINES 1,H - N,r-bar placed per plan sp insp
|
INSP - Foundation | 8/10/1999 | 8/10/1999 | 8/10/1999 | P | FAIL |
Wes Worcester
|
|
|
08/10/99 342 - GRID LINE 2 C D E F G M N. DAVE ###-#### given to Perry
|
INSP - Concrete | 8/3/1999 | 8/6/1999 | 8/6/1999 | A | PART |
|
|
|
PIER CAP GRID LINE 6 THRU G / ###-####
|
INSP - Concrete | 8/4/1999 | 8/6/1999 | 8/5/1999 | P | PART |
|
|
|
08/06/99 338 - DAVE CASE ON CAPS ###-#### r-bar placed sp insp made ok
|
INSP - Foundation | 7/1/1999 | 7/1/1999 | 7/1/1999 | | |
|
|
|
cason pours continuing ok
|
INSP - Concrete | 6/28/1999 | 6/29/1999 | 6/28/1999 | A | PART |
|
|
|
06/29/99 338 - Grid line 2 north and south Grid line H left grid line 6 north grid line K right and left
|
INSP - Concrete | 6/25/1999 | 6/28/1999 | 6/28/1999 | A | PART |
|
|
|
06/28/99 338 - grid lines 2 south grid line L left and right ok with sp
|
INSP - Concrete | 6/28/1999 | 6/28/1999 | 6/28/1999 | P | PART |
|
|
|
06/28/99 338 - Grid line 2 north and south Grid line H right madeok with sp insp appr.
|
INSP - Concrete | 6/28/1999 | 6/28/1999 | 6/28/1999 | P | PART |
|
|
|
06/28/99 338 - grid line 6 north grid line L left made ok with sp insp a
|
INSP - Concrete | 6/25/1999 | 6/25/1999 | 6/25/1999 | P | PART |
|
|
|
06/25/99 338 - grid line 2 north and south grid line J left made ok with
|
INSP - Concrete | 6/24/1999 | 6/24/1999 | 6/24/1999 | P | PART |
|
|
|
06/24/99 338 - CAISONS//GRIDLINE 6 NORTH & SOUTH GRIDLINE L RIGHT r-bar
|
INSP - Concrete | 6/23/1999 | 6/24/1999 | 6/24/1999 | A | PART |
|
|
|
06/24/99 338 - grid line 2 north and south grid line J right ok to pour
|
INSP - Concrete | 6/22/1999 | 6/23/1999 | 6/23/1999 | A | PART |
|
|
|
06/23/99 338 - 06/23/99 338 - grid line 2 north grid line L left and rig ###-#### ok r-bar placed SP INSP
|
INSP - Foundation | 6/23/1999 | 6/23/1999 | 6/23/1999 | P | PART |
|
|
|
06/23/99 338 - ###-####//CAISONS GRIDLINE 6 NORTH GRIDLINE N RIGHT & LEFT SP INSP
|
INSP - Concrete | 6/21/1999 | 6/22/1999 | 6/22/1999 | A | PART |
|
|
|
06/22/99 338 - /CAISONS GRIDLINE 2 SOUTH GRIDLINE N LEFT & RIGHT
|
INSP - Concrete | 6/18/1999 | 6/21/1999 | 6/21/1999 | A | PART |
|
|
|
06/21/99 338 - CAISONS GRIDLINE 2 SOUTH GRIDLINE K LEFT & RIGHT sp insp ok
|
INSP - Foundation | 6/21/1999 | 6/21/1999 | 6/21/1999 | | |
|
|
|
starting 6 foot casons work proceeding on schedule perry i and dave reedar reviewd change in rebar placement on specific detail dave was getting engineer approval on
|
INSP - Concrete | 6/17/1999 | 6/18/1999 | 6/18/1999 | A | PART |
|
|
|
06/18/99 338 - grid line 2 north grid line K right and left ###-#### made ok sp insp appr.
|
INSP - Concrete | 6/18/1999 | 6/18/1999 | 6/18/1999 | P | |
|
|
|
###-#### DAVE// CAISONS GRIDLINE 2 CENTER GRIDLINE N LEFT GRIDLINE 6 SOUTH GRIDLINE N LEFT & RIGHT GRIDLINE 2 NORTH GRIDLINE K LEFT & RIGHT
|
INSP - Concrete | 6/17/1999 | 6/17/1999 | 6/17/1999 | P | PART |
|
|
|
grid line 6 south grid line K right grid line L left ###-#### made ok with sp insp approval
|
INSP - Concrete | 6/16/1999 | 6/17/1999 | 6/17/1999 | A | PART |
|
|
|
###-#### dave//caisons gridline 2 center & north gridline m left madeok to pour with sp insp approval
|
INSP - Concrete | 6/16/1999 | 6/16/1999 | 6/16/1999 | P | |
|
|
|
###-#### dave// caisons gridline 2 center & north gridline n right Resaigned by 325.
|
INSP - Concrete | 6/15/1999 | 6/16/1999 | 6/16/1999 | A | PART |
|
|
|
06/16/99 338 - grid line 6 north on a M line left and right made ok with
|
INSP - Concrete | 6/15/1999 | 6/15/1999 | 6/15/1999 | P | PART |
|
|
|
06/15/99 338 - ###-#### DAVE//CAISONS GRIDLINE 6 NORTH J RIGHT GRIDLINE LEFT
|
INSP - Concrete | 6/15/1999 | 6/15/1999 | 6/15/1999 | | PART |
|
|
|
06/15/99 338 - GRID LINE 2 GRID LINE M RIGHT made ok with sp insp approv
|
INSP - Concrete | 6/14/1999 | 6/15/1999 | 6/15/1999 | A | PART |
|
|
|
06/15/99 338 - GRID LINE 2 GRID LINE M RIGHT ok with sp insp app
|
INSP - Concrete | 6/14/1999 | 6/14/1999 | 6/14/1999 | P | PART |
|
|
|
Grid line 6 north and south Grid line J left and right made ok with sp insp approval
|
INSP - Concrete | 6/11/1999 | 6/14/1999 | 6/14/1999 | A | PART |
|
|
|
06/14/99 338 - made ok with sp insppapproval
|
INSP - Concrete | 6/11/1999 | 6/11/1999 | 6/11/1999 | P | PART |
Wes Worcester
|
|
|
06/11/99 342 - Grid line 6 South M left and right special inspector on s
|
INSP - Foundation | 6/11/1999 | 6/11/1999 | 6/11/1999 | P | PART |
Wes Worcester
|
|
|
06/11/99 342 - ###-####//CAISONS GRID LINE 6 NORTH G LINE RIGHT H LINE LEFT spec insp on site
|
INSP - Concrete | 6/10/1999 | 6/10/1999 | 6/10/1999 | P | PART |
Jim Storey
|
|
|
06/10/99 301 - grid lines 6 north grid line E right F left ###-#### pend
|
INSP - Foundation | 6/9/1999 | 6/10/1999 | 6/10/1999 | A | PART |
Wes Worcester
|
|
|
06/10/99 342 - ###-####//CAISONS GRIDLINE 6 NORTH & SOUTH GRIDLINE H RIGHT GRIDLINE J LEFT
|
INSP - Foundation | 6/9/1999 | 6/9/1999 | 6/9/1999 | P | PART |
Jim Storey
|
|
|
06/09/99 301 - Grid line A and 1 Grid line 6 north and grid D left and E
|
INSP - Foundation | 6/8/1999 | 6/9/1999 | 6/9/1999 | A | FAIL |
Wes Worcester
|
|
|
06/08/99 342 - no answer, spec insp to assess collapsed soils at caison
|
INSP - Foundation | 6/7/1999 | 6/8/1999 | 6/8/1999 | A | FAIL |
Wes Worcester
|
|
|
06/08/99 342 - ###-####//CAISONS*GRID 6 SO H LINE no answer, dirt has ca
|
INSP - Foundation | 6/7/1999 | 6/8/1999 | 6/8/1999 | P | PART |
Wes Worcester
|
|
|
06/08/99 342 - ###-####/no one at site, no answer/CAISONS GRID LINES A G
|
INSP - Foundation | 6/8/1999 | 6/8/1999 | 6/8/1999 | P | PART |
Jim Storey
|
|
|
06/08/99 301 - Dave ###-#### grid line A and 1 north 9 ft. Grid line A a
|
INSP - Concrete | 6/4/1999 | 6/7/1999 | 6/5/1999 | A | PART |
|
|
|
06/07/99 338 - grid line 6 grid line H South left and right madeok to po
|
INSP - Concrete | 6/4/1999 | 6/4/1999 | 6/4/1999 | P | PART |
|
|
|
06/04/99 338 - 3:00 PLEASE ###-#### GRID LINES 6 AND D SOUTH LEFT 6 AND F SOUTH RIGHT AND LEFT made ok to pour with sp inspapproval
|
INSP - Concrete | 6/3/1999 | 6/3/1999 | 6/3/1999 | P | PART |
|
|
|
06/03/99 338 - Dave ###-#### grid line A and 2.9 and 1.1 and .40 ft and grid line C .14 ft grid line 5.4 ft and B .9 ft made ok with sp insp approvals
|
INSP - Concrete | 5/28/1999 | 5/28/1999 | 5/28/1999 | P | PART |
|
|
|
05/28/99 338 - madeok for casson pour with sp insp approvals
|
INSP - Foundation | 8/23/1999 | 8/23/1999 | 3/23/1999 | P | PART |
|
|
|
08/23/99 338 - TOM###-####.BETWEEN N6-G6 & N2-K2.PILE CAPS F6,E6,D6,B2
|