BLD-Final | 8/28/2000 | 8/29/2000 | 8/29/2000 | P | PASS |
Tony Young
|
|
|
Mark ###-####
c. of c. # 19715 issued 8/29/2000 2:58:47 PM
|
BLD-Grading Inspection | 8/29/2000 | 8/29/2000 | 8/29/2000 | | PASS |
Rita DeYoung
|
|
|
Grading and drainage completed completed in substantial compliance to approved plan, with 2 exceptions. The driveway was not extended into the adjacent lot and the proposed swimming pool was not built. Both of these reduced the amount of grading and have been approved by the engineer. Therefore the final grading and drainage is approved by Public Works.
|
BLD-Final | 8/23/2000 | 8/24/2000 | 8/24/2000 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/23/2000 at 13:06:49. Contact: ###-####.
all ok except need one smoke detector in lower hall way, need to look under floor when reinspect 8/24/2000 10:29:41 AM
also verify Terry Records sign off 8/24/2000 10:37:43 AM
|
BLD-Conference | 8/10/2000 | 8/11/2000 | 8/11/2000 | A | PASS |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/10/2000 at 17:10:58. Contact: ###-####.
pre final. 8/11/2000 12:05:35 PM
|
BLD-Energy code compliance | 1/7/2000 | 1/10/2000 | 1/10/2000 | A | PASS |
Russ Owen
|
|
|
mark ###-####
|
BLD-Energy code compliance | 1/6/2000 | 1/6/2000 | 1/6/2000 | P | FAIL |
Russ Owen
|
|
|
mark ###-#### energy code insp Some areas at stair well, not done.
|
BLD-Framing/Rough-in | 1/6/2000 | 1/6/2000 | 1/6/2000 | P | FAIL |
Russ Owen
|
|
|
fr insp--- mark ###-#### Chase's not fire stopped.
|
BLD-Framing/Rough-in | 1/4/2000 | 1/5/2000 | 1/5/2000 | A | CANC |
Russ Owen
|
|
|
###-####
|
BLD-Framing/Rough-in | 1/5/2000 | 1/5/2000 | 1/5/2000 | A | CANC |
Russ Owen
|
|
|
Already done.
|
BLD-Framing/Rough-in | 1/3/2000 | 1/4/2000 | 1/4/2000 | P | PASS |
Wes Worcester
|
|
|
Scheduled by a contractor via Hello! on 01/03/2000 at 10:31:40. Contact: ###-####. Truss engineering.
|
BLD-Framing/Rough-in | 12/13/1999 | 12/14/1999 | 12/14/1999 | A | PASS |
Russ Owen
|
|
|
MARK ###-#### SHEAR NAIL INSP
|
BLD-Foundation | 10/28/1999 | 10/29/1999 | 10/29/1999 | A | PASS |
Wes Worcester
|
|
|
MARK ###-####
|
BLD-Foundation | 9/17/1999 | 9/17/1999 | 9/17/1999 | P | PASS |
Russ Owen
|
|
|
Garage walls- pending letter from soils engineer, which was also required at Last Inpsection
|
INSP - Foundation | 9/9/1999 | 9/10/1999 | 9/10/1999 | A | PASS |
Russ Owen
|
|
|
garage area ok - pending letter from soils engineer
|
INSP - Foundation | 9/9/1999 | 9/9/1999 | 9/9/1999 | P | FAIL |
Russ Owen
|
|
|
|
INSP - Foundation | 8/17/1999 | 8/18/1999 | 8/18/1999 | A | PASS |
Russ Owen
|
|
|
08/18/99 407 - note,corrections had to be made.
|
INSP - Foundation | 7/29/1999 | 7/30/1999 | 7/30/1999 | A | PASS |
Russ Owen
|
|
|
07/30/99 407 - footings
|