BLD-Final | 1/24/2000 | 1/24/2000 | 1/24/2000 | P | PASS |
Carl Dependahl
|
|
|
bob ###-#### cn ok ok to sign for co 1/31/00 9:00:36 AM
|
Permanent Occupancy | | 1/24/2000 | 1/24/2000 | | DONE |
|
|
|
|
Permanent Occupancy | | 1/24/2000 | 1/24/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 12/22/1999 | 12/22/1999 | 12/22/1999 | P | PASS |
Joe Tawney
|
|
|
Final, Bob ###-#### - Lyle Pearson Acura. Reinsp. ok for permanent occupancy.
|
BLD-Conference | 11/30/1999 | 11/30/1999 | 11/30/1999 | A | PASS |
Carl Dependahl
|
|
|
w/supt. keep C/N.
|
BLD-Final | 11/24/1999 | 11/29/1999 | 11/29/1999 | A | FAIL |
Carl Dependahl
|
|
|
BOB ###-####
|
BLD-Final | 11/24/1999 | 11/24/1999 | 11/24/1999 | P | FAIL |
Carl Dependahl
|
|
|
C/N; listed firestop/ Top-of-wall; hand rails ok for T/O.
|
FIRE-Final Inspection | 11/24/1999 | 11/24/1999 | 11/24/1999 | P | PART |
Joe Tawney
|
|
|
bob ###-#### Final ok for temp. occ. Rotate hydrant, provide approved exit sign.
|
BLD-Other | 11/22/1999 | 11/23/1999 | 11/23/1999 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 11/22/1999 at 16:17:05. Contact: ###-####. Ceiling, ok; keep C/N.
|
FIRE-Conference | 11/22/1999 | 11/23/1999 | 11/23/1999 | A | PART |
Joe Tawney
|
|
|
Bob ###-#### Conf. Pre-final.
|
BLD-Framing/Rough-in | 11/2/1999 | 11/2/1999 | 11/2/1999 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 11/02/1999 at 07:23:44. Contact: ###-####. Keep C/N
|
BLD-Framing/Rough-in | 10/29/1999 | 11/1/1999 | 11/1/1999 | A | FAIL |
Carl Dependahl
|
|
|
bob ###-#### C/N; ok to cover int. wall except as noted.
|
BLD-Conference | 10/25/1999 | 10/25/1999 | 10/25/1999 | A | PASS |
Carl Dependahl
|
|
|
Met w/supt. re: spec. insp. req's
|
INSP - Concrete | 9/7/1999 | 9/8/1999 | 9/8/1999 | P | PART |
Carl Dependahl
|
|
|
greg ###-#### -grout pour --concrete; KLEINFELDER ONSITE, W.I.P.
|
INSP - Concrete | 9/7/1999 | 9/7/1999 | 9/7/1999 | P | PART |
Carl Dependahl
|
|
|
greg-- ###-#### masonary grout pour; 9/7 spec insp onsite, grouting. jrb
|
INSP - Concrete | 9/3/1999 | 9/3/1999 | 9/3/1999 | P | PART |
Carl Dependahl
|
|
|
09/03/99 340 - for concrete grout-greg ###-####; pend report
|
INSP - Concrete | 9/1/1999 | 9/2/1999 | 9/2/1999 | A | PART |
Tom Arcoraci
|
|
|
09/02/99 408 - spec insp
|
INSP - Concrete | 9/1/1999 | 9/1/1999 | 9/1/1999 | P | PART |
Carl Dependahl
|
|
|
09/01/99 340 - MASONRY GROUT POUR. GREGG ###-####; mti onsite
|
INSP - Concrete | 8/31/1999 | 8/31/1999 | 8/31/1999 | P | PART |
Carl Dependahl
|
|
|
08/31/99 340 - ###-####- greg-concrete-grout pour; KLEINFELDER ONSITE
|
INSP - Concrete | 8/30/1999 | 8/30/1999 | 8/30/1999 | P | PART |
Carl Dependahl
|
|
|
08/30/99 340 - GREG ###-#### MASONRY, GROUT WORK
|
INSP - Foundation | 8/26/1999 | 8/27/1999 | 8/27/1999 | P | FAIL |
Carl Dependahl
|
|
|
08/27/99 340 - MASONARY POUR GREG ###-####; nobody onsite?
|
INSP - Foundation | 8/26/1999 | 8/26/1999 | 8/26/1999 | P | PART |
Carl Dependahl
|
|
|
08/26/99 340 - THEY ARE POURING AT ONE PM GREG ###-####
|
INSP - Concrete | 8/24/1999 | 8/25/1999 | 8/25/1999 | A | PART |
Carl Dependahl
|
|
|
08/26/99 340 - BOB ###-#### MASONRY spec insp onsite
|
INSP - Concrete | 8/24/1999 | 8/24/1999 | 8/24/1999 | P | PART |
Tom Arcoraci
|
|
|
08/24/99 408 - spec insp on site
|
INSP - Framing/Rough-in | 8/23/1999 | 8/24/1999 | 8/24/1999 | A | PART |
Carl Dependahl
|
|
|
08/24/99 340 - bob ###-#### masonary insp; KLEINFELDER ONSITE, NEED AGRE
|
INSP - Foundation | 8/9/1999 | 8/9/1999 | 8/9/1999 | | FAIL |
Carl Dependahl
|
|
|
/ / 340 - FND POURED; PENDING ENG'S OK. SUPT. NOTIFIED
|
INSP - Foundation | 7/28/1999 | 7/29/1999 | 7/29/1999 | A | PART |
Tom Arcoraci
|
|
|
07/29/99 408 - spec insp on site
|
INSP - Foundation | 7/27/1999 | 7/27/1999 | 7/27/1999 | P | PART |
Carl Dependahl
|
|
|
07/27/99 340 - int & isolated ftgs only; keep c/n re other fnd walls: ne
|
INSP - Framing/Rough-in | 7/27/1999 | 7/27/1999 | 7/27/1999 | P | CANC |
Carl Dependahl
|
|
|
07/27/99 340 - footing inspection curtis ###-####
|
INSP - Foundation | 7/23/1999 | 7/26/1999 | 7/27/1999 | P | FAIL |
Carl Dependahl
|
|
|
07/26/99 340 - CURTIS ###-####; poured w/o insp. c/n, need eng's ok. not
|
INSP - Foundation | 7/21/1999 | 7/22/1999 | 7/22/1999 | A | PART |
Carl Dependahl
|
|
|
07/22/99 340 - CURTIS ###-#### FOOTINGS. BEFORE 10 AM PLEASE. cn, ftgs o
|