Permanent Occupancy | | 3/7/2000 | 3/7/2000 | | DONE |
|
|
|
|
BLD-Final | 1/3/2000 | 1/3/2000 | 1/3/2000 | P | PART |
|
|
|
tom ###-#### signed the temp col as mech is still temp.
|
FIRE-Final Inspection | 1/3/2000 | 1/3/2000 | 1/3/2000 | A | PASS |
Rick Jackson
|
|
|
|
FIRE-Final Inspection | 12/27/1999 | 12/28/1999 | 12/28/1999 | P | NR |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/27/1999 at 14:08:29. Contact: ###-####. Alarm panel problems.
|
FIRE-Final Inspection | 12/6/1999 | 12/7/1999 | 12/7/1999 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/06/1999 at 11:44:16. Contact: ###-####. Exit signs as beam detector.
|
FIRE-Final Inspection | 11/12/1999 | 11/12/1999 | 11/12/1999 | A | FAIL |
Rick Jackson
|
|
|
C/N issued
|
FIRE-Final Inspection | 11/4/1999 | 11/8/1999 | 11/8/1999 | A | FAIL |
Rick Jackson
|
|
|
JEFF-- PAGER ###-#### FIRE FN Alarm plans; sprinkler problems.
|
BLD-Framing/Rough-in | 10/29/1999 | 10/29/1999 | 10/29/1999 | P | PART |
|
|
|
PER LINDA R/I INSP Cabo And. Issues
|
BLD-Conference | 10/25/1999 | 10/25/1999 | 10/25/1999 | P | PASS |
|
|
|
jeff ###-#### pager hand rails @ ramps and ramp curbing
|
FIRE-Conference | 10/5/1999 | 10/6/1999 | 10/6/1999 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 10/05/1999 at 13:54:02. Contact: . Not a fire conference
|
BLD-Framing/Rough-in | 10/1/1999 | 10/4/1999 | 10/4/1999 | A | PART |
|
|
|
Tad ###-#### made ok for the restroom area only
|
INSP - Foundation | 9/2/1999 | 9/2/1999 | 9/2/1999 | P | FAIL |
Wes Worcester
|
|
|
09/02/99 342 - tad house--###-#### pager-ramp .... met w/Perry, no found
|