BLD-Final | 2/11/2000 | 2/11/2000 | 2/11/2000 | P | PASS |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 02/11/2000 at 11:19:13. Contact: ###-####. Card to cont. 2/14/00 11:52:30 AM
|
Permanent Occupancy | | 2/11/2000 | 2/11/2000 | | DONE |
|
|
|
|
BLD-Final | 2/9/2000 | 2/10/2000 | 2/10/2000 | P | FAIL |
Carl Dependahl
|
|
|
###-#### need eng'r ok and all other insp's
|
FIRE-Final Inspection | 2/9/2000 | 2/10/2000 | 2/10/2000 | A | PASS |
Joe Tawney
|
|
|
###-#### reinspection ok for perm occ
|
BLD-Final | 2/8/2000 | 2/9/2000 | 2/9/2000 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 02/08/2000 at 15:19:20. Contact: . Still has fire correction, no further inspections performed.
|
FIRE-Final Inspection | 2/8/2000 | 2/9/2000 | 2/9/2000 | A | FAIL |
Joe Tawney
|
|
|
Scheduled by a contractor via Hello! on 02/08/2000 at 15:17:30. Contact: . Reinpsection failed duct detectors.
|
BLD-Final | 2/4/2000 | 2/7/2000 | 2/7/2000 | P | PASS |
Tom Arcoraci
|
|
|
Michael-###-####
|
FIRE-Final Inspection | 2/4/2000 | 2/7/2000 | 2/7/2000 | A | FAIL |
Joe Tawney
|
|
|
Michael-###-#### Reinsp. fail C/N not completed. 2/7/00 1:29:52 PM
|
BLD-Final | 1/28/2000 | 1/28/2000 | 1/28/2000 | P | FAIL |
Tom Arcoraci
|
|
|
Micheal ###-#### not ready no fire insp 1/31/00 8:32:02 AM
|
FIRE-Final Inspection | 1/28/2000 | 1/28/2000 | 1/28/2000 | P | FAIL |
Joe Tawney
|
|
|
Micheal ###-#### smoke, fire damper 1/31/00 8:26:43 AM
|
BLD-Framing/Rough-in | 11/26/1999 | 11/29/1999 | 11/29/1999 | A | PART |
Carl Dependahl
|
|
|
bill ###-#### Need firestops & top-of-wall @ rated walls.
|
BLD-Framing/Rough-in | 11/19/1999 | 11/22/1999 | 11/22/1999 | A | PART |
Carl Dependahl
|
|
|
BILL-- ###-#### R/I Add'l C/N; need manue's rep. To verify retro. Tek EFIS & certify per ICBO er: 5245
|
BLD-Framing/Rough-in | 11/18/1999 | 11/19/1999 | 11/19/1999 | A | PART |
Carl Dependahl
|
|
|
BILL ###-#### Rec'd. eng's clarification for walls ok to insul. & cover exc. Grid "C" @ eng'd wall section. Awaiting further EFIS info (Er. Report)
|
BLD-Framing/Rough-in | 11/15/1999 | 11/16/1999 | 11/16/1999 | A | FAIL |
Carl Dependahl
|
|
|
BILL ###-#### FR INSP 2nd C/N; weather barrier/listed EFIS system; Add'l calrification by engr (stamped) req'd.
|
BLD-Conference | 11/15/1999 | 11/15/1999 | 11/15/1999 | A | PASS |
Carl Dependahl
|
|
|
Reviewed correction notice. Keep C/N.
|
BLD-Framing/Rough-in | 11/9/1999 | 11/10/1999 | 11/10/1999 | P | FAIL |
Carl Dependahl
|
|
|
bill ###-#### C/N.. Need eng'r. to inspect. Multiple errors in framing.
|
BLD-Framing/Rough-in | 10/8/1999 | 10/11/1999 | 10/11/1999 | | PART |
Carl Dependahl
|
|
|
bill ###-#### pouring at 8am not frame insp … masonary : ok pending spec. insp. Report.
|
BLD-Framing/Rough-in | 10/11/1999 | 10/11/1999 | 10/11/1999 | P | PART |
Carl Dependahl
|
|
|
Bill ###-#### masonary/ grout… pend. Spec. insp. Report
|
BLD-Framing/Rough-in | 10/7/1999 | 10/8/1999 | 10/8/1999 | A | PART |
Carl Dependahl
|
|
|
BILL-- 59-9616---REBAR REPLACEMENT not fram, ext. masonry walls… pend. Spec. insp.
|
BLD-Framing/Rough-in | 10/7/1999 | 10/7/1999 | 10/7/1999 | P | PART |
Carl Dependahl
|
|
|
bill--- ###-#### --cmu wall insp 1st lift east wall ; special insp
|
BLD-Foundation | 9/24/1999 | 9/24/1999 | 9/24/1999 | P | PART |
Carl Dependahl
|
|
|
Bill ###-#### Spec. insp. Report pending
|
BLD-Footing | 9/22/1999 | 9/23/1999 | 9/23/1999 | A | PART |
Carl Dependahl
|
|
|
bill ###-#### NW corner
|
BLD-Foundation | 9/17/1999 | 9/20/1999 | 9/20/1999 | A | PART |
Carl Dependahl
|
|
|
Spec insp report pending
|
INSP - Foundation | 9/9/1999 | 9/10/1999 | 9/10/1999 | A | PART |
Carl Dependahl
|
|
|
met supt. & spec insp onsite . ftgs ok to pour
|