BLD-Final | 8/22/2000 | 8/22/2000 | 8/22/2000 | P | PASS |
|
|
|
Scheduled by a contractor via Hello! on 08/22/2000 at 10:18:09. Contact: ###-####. signed the perm col of the occ req caed 8/23/00 8:29:53 AM
|
Permanent Occupancy | | 8/22/2000 | 8/22/2000 | | DONE |
|
|
|
|
FIRE-Conference | 8/16/2000 | 8/18/2000 | 8/18/2000 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/16/2000 at 10:45:46. Contact: ###-####.
|
FIRE-Conference | 8/14/2000 | 8/15/2000 | 8/15/2000 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 08/14/2000 at 09:46:22. Contact: ###-####. alarms not ready 8/15/2000 4:49:59 PM
|
BLD-Final | 7/12/2000 | 7/13/2000 | 7/13/2000 | P | FAIL |
|
|
|
Scheduled by a contractor via Hello! on 07/12/2000 at 13:25:39. Contact: ###-####. need fire signoff 7/13/2000 2:06:41 PM
|
FIRE-Conference | 7/12/2000 | 7/13/2000 | 7/13/2000 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 07/12/2000 at 13:24:44. Contact: ###-####.; final inspection c/n issued
|
FIRE-Conference | 5/24/2000 | 5/24/2000 | 5/24/2000 | A | PART |
Rick Jackson
|
|
|
Ok to use Deli Type 1 hood. Suppression system tested ok. 5/24/00 3:03:59 PM
|
BLD-Framing/Rough-in | 5/23/2000 | 5/23/2000 | 5/23/2000 | P | PART |
|
|
|
Scheduled by a contractor via Hello! on 05/23/2000 at 11:08:41. Contact: ###-####. shaft ok with 409 approvals 5/24/00 8:01:34 AM
|
FIRE-Conference | 5/23/2000 | 5/23/2000 | 5/23/2000 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 05/23/2000 at 11:09:33. Contact: ###-####. Electrical work not operating properly 5/24/00 3:02:20 PM
|
BLD-Framing/Rough-in | 5/22/2000 | 5/22/2000 | 5/22/2000 | P | PART |
|
|
|
Scheduled by a contractor via Hello! on 05/22/2000 at 10:12:57. Contact: ###-####. madeok with 409 ok 5/24/00 10:32:31 AM
|
BLD-Other | 5/22/2000 | 5/22/2000 | 5/22/2000 | A | FAIL |
|
|
|
Scheduled by Inspector: 338 On 5/22/00 class 1 hood at the deli not ready for insp other ag not approved 5/22/00 3:42:57 PM
|
FIRE-Conference | 5/22/2000 | 5/22/2000 | 5/22/2000 | P | NR |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 05/22/2000 at 10:12:09. Contact: ###-####. Contractor called to say he wasn't ready for the type I kitchen hood system 5/23/00 2:33:08 PM
|
BLD-Framing/Rough-in | 5/1/2000 | 5/2/2000 | 5/2/2000 | A | PART |
|
|
|
###-#### walk through the project working on the bakery and the deli area also new cart storage, ned perimeter wiring on the ceiling grid this area 5/4/00 5:25:37 PM
|
BLD-Framing/Rough-in | 3/21/2000 | 3/22/2000 | 3/22/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 03/21/2000 at 14:51:26. Contact: ###-####. made ok to stare efis system on the ext front colms and the soffits all to be outside of concealed spaces 03/22/2000 2:01:40 PM
|
BLD-Framing/Rough-in | 2/3/2000 | 2/4/2000 | 2/4/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 02/03/2000 at 15:37:28. Contact: ###-####. ok to cover with other agencies approvals 2/10/00 10:16:44 AM
|
BLD-Other | 1/21/2000 | 1/24/2000 | 1/24/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello!
. ok to start droping in ceiling tiles 1/25/00 7:56:54 AM
|
BLD-Framing/Rough-in | 1/18/2000 | 1/19/2000 | 1/19/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 01/18/2000 at 15:50:24. Contact: ###-####. made ok to cover this portion of the meat section soffits 1/20/00 11:51:26 AM
|
BLD-Framing/Rough-in | 1/6/2000 | 1/7/2000 | 1/7/2000 | P | FAIL |
|
|
|
NOT READYFOR INSP
|
BLD-Framing/Rough-in | 1/3/2000 | 1/4/2000 | 1/4/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 01/03/2000 at 15:06:43. Contact: ###-####.made ok in progress
|
BLD-Other | 12/13/1999 | 12/15/1999 | 12/15/1999 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 12/13/1999 at 13:34:19. Contact: ###-####. Ok to occupy laundry room and lower shower room.
|
FIRE-Sprinkler Rough-in | 12/13/1999 | 12/14/1999 | 12/14/1999 | A | PART |
Rick Jackson
|
|
|
ann ###-#### r/i fire spr Okay to cover new pharmacy only. Requested sprinkler and alarm plans.
|
BLD-Framing/Rough-in | 12/2/1999 | 12/3/1999 | 12/3/1999 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 12/02/1999 at 11:02:43. Contact: ###-####. Ok to cover with Elec. Ok.
|
BLD-Framing/Rough-in | 11/22/1999 | 11/23/1999 | 11/23/1999 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 11/22/1999 at 11:47:44. Contact: ###-####. Made ok with Electrical & Plumbing approval.
|
BLD-Other | 11/16/1999 | 11/17/1999 | 11/17/1999 | A | PASS |
|
|
|
Scheduled by a contractor via Hello! on 11/16/1999 at 12:09:03. Contact: ###-####. Walk through protect w/super.
|
BLD-Framing/Rough-in | 11/12/1999 | 11/12/1999 | 11/12/1999 | P | PART |
|
|
|
fr insp gill ###-#### Ok to cover w/elec. Approval.
|
BLD-Conference | 10/28/1999 | 11/1/1999 | 11/4/1999 | P | PASS |
|
|
|
JIM ###-#### Made ok
|
FIRE-Conference | 10/28/1999 | 11/1/1999 | 11/1/1999 | P | PART |
Rick Jackson
|
|
|
JIM ###-#### Discussed temporary exiting; sprinklers plans submittals; project phasing.
|