BLD-Final | 4/27/2000 | 4/28/2000 | 4/28/2000 | A | PASS |
Jim Storey
|
|
|
Dan ###-#### final ok 4/28/00 9:21:59 AM
|
Permanent Occupancy | | 4/28/2000 | 4/28/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 3/29/2000 | 3/29/2000 | 3/29/2000 | P | PASS |
Rick Jackson
|
|
|
###-####
|
FIRE-Final Inspection | 3/24/2000 | 3/27/2000 | 3/27/2000 | A | FAIL |
Rick Jackson
|
|
|
Dan ###-#### Security egress doors not working. 3/28/00 8:52:34 AM
|
BLD-Final | 3/23/2000 | 3/24/2000 | 3/24/2000 | P | PART |
Jim Storey
|
|
|
Dan ###-#### ada signage at restarooms , pending other sign offs. temp occ ok 3/24/00 2:50:08 PM
|
FIRE-Final Inspection | 3/24/2000 | 3/24/2000 | 3/24/2000 | P | FAIL |
Rick Jackson
|
|
|
###-#### Egress doors not working. 3/27/00 10:08:41 AM
|
FIRE-Final Inspection | 3/22/2000 | 3/22/2000 | 3/22/2000 | P | FAIL |
Rick Jackson
|
|
|
###-#### Egress doors not working. 3/23/00 9:03:04 AM
|
FIRE-Conference | 2/28/2000 | 2/28/2000 | 2/28/2000 | P | PART |
Rick Jackson
|
|
|
Dan ###-#### Exit lights; duct detectors; egress controls on exit. 2/29/00 3:04:41 PM
|
BLD-Framing/Rough-in | 2/22/2000 | 2/23/2000 | 2/23/2000 | A | PART |
|
|
|
###-#### dan madeok to drop in the ceiling tiles 2/23/00 11:00:51 AM
|
BLD-Framing/Rough-in | 2/11/2000 | 2/14/2000 | 2/14/2000 | A | PASS |
Jim Storey
|
|
|
ceiling \\###-#### Beam covered w/gyp. ok. 2/14/00 2:27:40 PM
|
BLD-Conference | 2/1/2000 | 2/2/2000 | 2/2/2000 | A | PART |
Jim Storey
|
|
|
Dan ###-#### fire collors on piping ok thru 1 hr roof syst. c\n pending on how gib is to be 1 hr protected as wellas sadles for beams, subital reg for approval 2/3/00 9:44:36 AM
|
BLD-Framing/Rough-in | 1/18/2000 | 1/18/2000 | 1/18/2000 | P | PART |
Jim Storey
|
|
|
FIRE CAULKING--RE-INSP- DAN-- ###-#### Waiting for submittal for column & beam 1hr protection/ plumbing penetration 1 ok 2 failed at ceiling collor not installed correctly. 1/19/00 10:54:06 AM
|
BLD-Framing/Rough-in | 1/7/2000 | 1/11/2000 | 1/11/2000 | A | PART |
Jim Storey
|
|
|
Dan CM company ###-#### Fire damper/beam & co lwrap/ plastic pipe 3 loc.
|
BLD-Framing/Rough-in | 12/15/1999 | 12/15/1999 | 12/15/1999 | A | PART |
Jim Storey
|
|
|
SHEETROCK DAN ###-#### Received eng. Letter to address C/N ok archived letter.
|
BLD-Framing/Rough-in | 12/10/1999 | 12/13/1999 | 12/13/1999 | P | FAIL |
Jim Storey
|
|
|
###-####-dan fr insp C/N.
|
BLD-Framing/Rough-in | 12/6/1999 | 12/8/1999 | 12/8/1999 | A | NR |
Russ Owen
|
|
|
nailing\###-#### Frost on roof, will recall when complete.
|
BLD-Framing/Rough-in | 12/8/1999 | 12/8/1999 | 12/8/1999 | P | PART |
Jim Storey
|
|
|
ROOF NAILING-- ###-####-DAN Deck nailing on roof deck ok.
|
BLD-Framing/Rough-in | 12/3/1999 | 12/3/1999 | 12/3/1999 | A | PART |
Jim Storey
|
|
|
Exterior shear nailing ok per approved plan ok to cover exterior of Bld.
|
BLD-Framing/Rough-in | 12/2/1999 | 12/2/1999 | 12/2/1999 | P | FAIL |
Jim Storey
|
|
|
shear wall dan ###-#### voice pager Sheer nailing C/N.
|
BLD-Footing | 10/15/1999 | 10/19/1999 | 10/19/1999 | A | PART |
Wes Worcester
|
|
|
dan ###-#### Met w/contractor; MTI onsite.. 301 area.
|