BLD-Final | 7/3/2001 | 7/3/2001 | 7/3/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 7/3/2001 2:56:47 PM shell ok for perm...l/c. t/i's need final requests
|
BLD-Final | 6/20/2001 | 6/21/2001 | 6/21/2001 | A | NR |
Carl Dependahl
|
|
|
april ###-####; need verify achd & other ok's; spoke w/ Titan 6/21/2001 11:07:03 AM
|
BLD-Conference | 3/13/2001 | 3/13/2001 | 3/13/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/13/2001 6:41:37 PM need all sign-offs, complete c/n, draft stops at fl/clgs, waterproofing at ext decks, etc.
|
BLD-Conference | 3/8/2001 | 3/8/2001 | 3/8/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/8/2001 9:20:23 AM w/ arch re c/n...need 1hr ext wall per plans at east side; prop. line assumed to be at 10'7"...no protected openings
|
BLD-Conference | 3/6/2001 | 3/6/2001 | 3/6/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 3/6/2001 6:24:09 PM w/arch re 1hr stair ways
|
BLD-Conference | 2/7/2001 | 2/7/2001 | 2/7/2001 | A | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 2/7/2001 11:09:26 AM w/ Carr const re t/i & finals
|
BLD-Conference | 1/29/2001 | 1/29/2001 | 1/29/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 1/29/2001 4:01:16 PM w/ arch onsite re c/n...add gyp at passageway
|
BLD-Conference | 1/25/2001 | 1/25/2001 | 1/25/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 1/25/2001 2:56:06 PM w/ contractor re c/n of 1-9-01. need add gyp at stairs, etc...both sides of assy.
|
BLD-Conference | 1/18/2001 | 1/18/2001 | 1/18/2001 | A | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 1/18/2001 9:54:27 AM w/rick jackson re c/n
|
BLD-Conference | 1/17/2001 | 1/17/2001 | 1/17/2001 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 1/17/2001 4:26:16 PM w/ GS re plans
|
BLD-Final | 1/5/2001 | 1/8/2000 | 1/9/2001 | A | CANC |
Carl Dependahl
|
|
|
DARYL W/TITAN; ###-####.
|
BLD-Final | 1/9/2001 | 1/9/2001 | 1/9/2001 | P | PART |
Carl Dependahl
|
|
|
Darrel ###-####,c/n issued, ok for t/o 1/9/2001 6:02:41 PM
|
FIRE-Final Inspection | 1/9/2001 | 1/9/2001 | 1/9/2001 | A | PASS |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 1/9/2001 8:56:55 AM
|
FIRE-Final Inspection | 1/4/2001 | 1/5/2001 | 1/8/2001 | A | FAIL |
Rick Jackson
|
|
|
DARRELL ###-#### FN FIRE sprinkler problems and alarm problems 1/8/2001 11:19:38 AM
|
BLD-Final | 1/4/2001 | 1/5/2001 | 1/5/2001 | A | NR |
Carl Dependahl
|
|
|
FN OCC- DARRELL ###-####
|
BLD-Final | 1/3/2001 | 1/4/2001 | 1/4/2001 | P | NR |
Carl Dependahl
|
|
|
temp occ- darrell ###-#### need fire, etc. 1/4/2001 4:08:31 PM
|
BLD-Framing/Rough-in | 11/15/2000 | 11/16/2000 | 11/16/2000 | A | PART |
Carl Dependahl
|
|
|
###-####; recd details will review 11/16/2000 4:23:38 PM
|
BLD-Conference | 11/15/2000 | 11/15/2000 | 11/15/2000 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 11/15/2000 5:42:14 PM w/ supt.
|
BLD-Framing/Rough-in | 10/23/2000 | 10/24/2000 | 10/24/2000 | A | PART |
Jim Storey
|
|
|
fr-- darrell ###-#### need flood plian cert. maintane east stair penatration of ele heater. 10/25/2000 11:36:45 AM
|
BLD-Framing/Rough-in | 10/23/2000 | 10/24/2000 | 10/24/2000 | A | PART |
Jim Storey
|
|
|
fr-- darrell ###-#### need flood plian cert. maintane east stair penatration of ele heater. 10/25/2000 11:36:45 AM
|
BLD-Conference | 8/29/2000 | 8/29/2000 | 9/1/2000 | P | PART |
|
|
|
###-#### need fire signoff 8/29/2000 4:21:10 PM wiht darrell on the exit passageway etc 9/1/2000 10:46:01 AM
|
BLD-Framing/Rough-in | 6/20/2000 | 6/21/2000 | 6/21/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 06/20/2000 at 14:14:31. Contact: ###-####. with darrell 6/21/00 11:11:54 AM
|
BLD-Conference | 5/19/2000 | 5/19/2000 | 5/19/2000 | P | PART |
|
|
|
darrell--###-#### for conf with darrell onthe requiremens for a rated shaft for ducts penetrating floors from roof. code says 1 or 2 strys this is3 story building 5/19/00 5:12:56 PM
|