BLD-Final | 3/3/2000 | 3/3/2000 | 3/3/2000 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/03/2000 at 10:57:26. Contact: ###-####. Ok for T/O, has elec. C/N. 3/6/00 11:12:20 AM
|
FIRE-Final Inspection | 3/2/2000 | 3/2/2000 | 3/2/2000 | P | PASS |
Joe Tawney
|
|
|
Gary ###-#### Final ok for perm. occ. 3/3/00 8:41:06 AM
|
BLD-Conference | 3/1/2000 | 3/1/2000 | 3/1/2000 | A | PASS |
Carl Dependahl
|
|
|
W/supt. re: door hdwe.
|
BLD-Other | 2/29/2000 | 2/29/2000 | 2/29/2000 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 02/29/2000 at 10:00:10. Contact: ###-####. Ceiling 3/1/00 11:11:45 AM
|
BLD-Conference | 2/15/2000 | 2/15/2000 | 2/15/2000 | A | PASS |
Carl Dependahl
|
|
|
W/supt. re: correction, ok to cover.
|
BLD-Wall cover | 2/11/2000 | 2/11/2000 | 2/11/2000 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 02/11/2000 at 10:08:51. Contact: ###-####. Ok to cover walls & storefront. 2/14/00 11:53:15 AM
|
FIRE-Sprinkler Rough-in | 2/10/2000 | 2/10/2000 | 2/10/2000 | P | PART |
Joe Tawney
|
|
|
###-####\\UPPER LEVEL ROTH SHOES ok to cover sprinkler r/I
|
BLD-Conference | 2/9/2000 | 2/9/2000 | 2/9/2000 | P | PART |
Carl Dependahl
|
|
|
gary ###-#### c/n re access @ storefront ; ok to cover pend ele
|