BLD-Final | 9/6/2000 | 9/7/2000 | 9/7/2000 | A | PASS |
Carl Dependahl
|
|
|
MIKE ###-#### FN OCC, ok for c/o 9/7/2000 11:42:50 AM
|
Permanent Occupancy | | 9/7/2000 | 9/7/2000 | | DONE |
|
|
|
|
FIRE-Final Inspection | 9/5/2000 | 9/6/2000 | 9/6/2000 | A | PASS |
Joe Tawney
|
|
|
mike-- ###-#### fire fn Reinsp OK for permanant occupancy 9/6/2000 12:17:26 PM
|
BLD-Final | 6/13/2000 | 6/14/2000 | 6/14/2000 | P | FAIL |
Jim Sly
|
|
|
Scheduled by a contractor via Hello! on 06/13/2000 at 10:38:07. Contact: ###-####. C/N..letter spec. insp. agency, firestop 1hr. mech. ok for temp. occ. 6/15/00 11:27:03 AM
|
FIRE-Final Inspection | 6/13/2000 | 6/14/2000 | 6/14/2000 | P | PART |
Joe Tawney
|
|
|
mike ###-#### Reinsp. ok for temp. occ. 6/15/00 11:35:11 AM
|
FIRE-Final Inspection | 6/12/2000 | 6/13/2000 | 6/13/2000 | P | FAIL |
Joe Tawney
|
|
|
mike ###-#### Final fail C/N issued. 6/14/00 8:59:56 AM
|
BLD-Framing/Rough-in | 5/19/2000 | 5/22/2000 | 5/22/2000 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 05/19/2000 at 16:24:00. Contact: ###-####. spoke w/cont. (Mike) need resub. for changes clg. ok area B..pend..HVAC 5/23/00 2:34:14 PM
|
BLD-Framing/Rough-in | 5/19/2000 | 5/19/2000 | 5/19/2000 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 05/19/2000 at 07:35:56. Contact: ###-####. Ceiling- need HVAC ok for duct hangers. 5/22/00 11:38:33 AM
|
BLD-Framing/Rough-in | 4/14/2000 | 4/17/2000 | 4/17/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 04/14/2000 at 13:39:50. Contact: ###-####. Grid @ area "A" ok, walls @ "C" ok (to occ. separation) keep C/N. 4/17/00 2:05:00 PM
|
BLD-Framing/Rough-in | 3/24/2000 | 3/24/2000 | 3/24/2000 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/24/2000 at 10:47:44. Contact: ###-####. C/N firestops 3/27/00 9:59:10 AM
|
BLD-Framing/Rough-in | 3/13/2000 | 3/14/2000 | 3/14/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/13/2000 at 17:19:19. Contact: ###-####. B section int. partitions ok; add braces @ wall tops as needed 3/16/00 11:08:49 AM
|
BLD-Framing/Rough-in | 2/21/2000 | 2/22/2000 | 2/22/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 02/21/2000 at 08:07:32. Contact: ###-####. To grid 5- North wing- ok to cover. 2/23/00 11:43:12 AM
|