BLD-Final | 12/26/2000 | 12/26/2000 | 12/26/2000 | P | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/26/2000 at 07:52:18. Contact: ###-####.
|
BLD-Conference | 12/22/2000 | 12/22/2000 | 12/22/2000 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 12/22/2000 3:56:02 PM w bldr, call insp for tenants...supply copies of eng's/spec. insp affidavit letters re shell & seismic upgrades,file misplaced??? c/n issued re lobby/ bsmt stair rails
|
BLD-Final | 12/21/2000 | 12/21/2000 | 12/21/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 12/21/2000 at 07:19:02. Contact: ###-####.
|
BLD-Final | 12/20/2000 | 12/20/2000 | 12/20/2000 | P | PART |
Carl Dependahl
|
|
|
fn occ ed ###-#### , c/n issued re stairs at bsmt and smt corridor (airflow above grid clg???); need submittal for rails. ok for t/o 12/20/2000 4:01:54 PM 12/20/2000 4:03:58 PM
|
FIRE-Final Inspection | 12/18/2000 | 12/18/2000 | 12/18/2000 | P | PASS |
Rick Jackson
|
|
|
ED-- ###-#### FIRE FN
|
BLD-Conference | 12/15/2000 | 12/15/2000 | 12/15/2000 | P | PASS |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 12/15/2000 3:17:38 PM w/ bldr re c/n
|
FIRE-Final Inspection | 11/22/2000 | 11/27/2000 | 11/27/2000 | A | FAIL |
Rick Jackson
|
|
|
fire alarm final lyle ###-####////// alarms tested and complete 11/27/2000 10:45:47 AM
|
BLD-Final | 11/16/2000 | 11/17/2000 | 11/17/2000 | P | FAIL |
Carl Dependahl
|
|
|
FN ED-- ###-#### ; c//n issued 11/17/2000 5:03:28 PM
|
FIRE-Final Inspection | 11/16/2000 | 11/17/2000 | 11/17/2000 | P | FAIL |
Rick Jackson
|
|
|
Lyle ###-####
|
BLD-Conference | 11/15/2000 | 11/16/2000 | 11/16/2000 | P | FAIL |
Carl Dependahl
|
|
|
Ed ###-####; c/n re stairs, rails, bsmt corridor not done, etc. 11/16/2000 1:31:46 PM
|
BLD-Conference | 11/15/2000 | 11/15/2000 | 11/15/2000 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 11/15/2000 at 10:46:53. Contact: ###-####.
|
BLD-Conference | 11/15/2000 | 11/15/2000 | 11/15/2000 | P | PART |
Carl Dependahl
|
|
|
Added by Inspector: 340 On 11/15/2000 5:32:08 PM w/ cont & westfall
|
BLD-Final | 11/9/2000 | 11/13/2000 | 11/13/2000 | A | NR |
Carl Dependahl
|
|
|
partail final Ed ###-####, need fire, engs ok. spoke w/ ed ( wensel) 11/13/2000 3:47:26 PM
|
BLD-Framing/Rough-in | 8/16/2000 | 8/16/2000 | 8/16/2000 | P | PART |
|
|
|
ED-- ###-#### FR INSP-FIRE CALUKING ON STAIR with ed and drywaller on the fire caulking of inside of the inner layer 8/16/2000 3:32:35 PM
|
BLD-Framing/Rough-in | 8/10/2000 | 8/11/2000 | 8/11/2000 | A | PART |
|
|
|
ed-- ###-#### partial fr-not between 2:30 & 3:30 ??????? madeok to cover stairs after fire caulking is completed and inspected, need drywall iner inshaft damper penes 8/11/2000 2:58:56 PM
|
BLD-Framing/Rough-in | 8/2/2000 | 8/3/2000 | 8/3/2000 | A | PART |
|
|
|
STAIR TOWER INSP--ED-- ###-#### ok for the install of the outer layers 8/3/2000 3:27:45 PM
|
BLD-Conference | 6/27/2000 | 6/27/2000 | 6/27/2000 | P | PART |
|
|
|
ed ###-#### walked all floors misc q's on the stair 6/27/00 4:36:23 PM
|
BLD-Framing/Rough-in | 5/30/2000 | 5/30/2000 | 5/30/2000 | P | PART |
|
|
|
Ed ###-#### 5thflor ok to cover core walls at the restroom area 6/2/00 4:13:03 PM
|
BLD-Framing/Rough-in | 5/16/2000 | 5/16/2000 | 5/16/2000 | P | PART |
|
|
|
ed ###-#### part fr & energy code walked al floors with all floors with bob and ed checked out fire caulking and framing of the core and infil area, must seperate all hdronics and elec conduits from the stair enlosure. 5/17/00 7:24:50 AM
|
BLD-Framing/Rough-in | 5/10/2000 | 5/12/2000 | 5/12/2000 | A | PART |
|
|
|
###-#### fire caulking verbal corrections and a little destructive lok at the fire caulk not installed per listing 5/12/00 9:43:58 AM
|
BLD-Framing/Rough-in | 5/2/2000 | 5/2/2000 | 5/2/2000 | P | PART |
|
|
|
partial framing and fire caulking ###-#### with all trades on the fire caulking at all levels 5/4/00 5:26:08 PM
|
BLD-Framing/Rough-in | 4/20/2000 | 4/21/2000 | 4/21/2000 | P | PART |
|
|
|
fire caulking\\###-#### ed please call first on firecaulking with all subs 04/24/2000 7:30:24 AM
|
BLD-Conference | 4/19/2000 | 4/19/2000 | 4/19/2000 | A | PART |
|
|
|
ok to cover 1-side of framed walls, still need to onspect the floor ceiling concealed penetrations, drywall is required behind the sheathing on the paraput walls of new infill construction of the building west side infill, per the approved plans 04/20/2000 8:42:42 AM
|
BLD-Framing/Rough-in | 4/12/2000 | 4/17/2000 | 4/17/2000 | A | PART |
|
|
|
Scheduled by Inspector: 338 On 04/12/2000 early as poss. in progress 04/17/2000
|
BLD-Framing/Rough-in | 4/13/2000 | 4/14/2000 | 4/14/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 04/13/2000 at 12:06:00. Contact: ###-####. walked all floors still connecting at ext and covering /patchng old plaster 04/14/2000
|
BLD-Framing/Rough-in | 4/11/2000 | 4/12/2000 | 4/12/2000 | A | FAIL |
|
|
|
ed ###-#### reccheduled to 4/17/00 04/12/2000
|
BLD-Framing/Rough-in | 3/24/2000 | 3/27/2000 | 3/27/2000 | A | PART |
|
|
|
partial framing inspection bob ###-#### made ok to continue on the ceiling cover for the 2nd floor 03/28/2000
|
BLD-Framing/Rough-in | 3/21/2000 | 3/22/2000 | 3/22/2000 | A | PART |
|
|
|
###-#### conf on the perimeter bolt attachmenta and drywall cover on the extisting plaster patches 03/23/2000 8:07:58 AM
|
BLD-Foundation | 3/15/2000 | 3/15/2000 | 3/15/2000 | P | PART |
|
|
|
###-#### Ed made ok with sp insp approvals 03/16/2000 7:55:24 AM
|
BLD-Foundation | 3/13/2000 | 3/14/2000 | 3/14/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 03/13/2000 at 16:30:21. Contact: ###-####. made ok with sp insp approvals 3/14/00 5:12:19 PM
|
BLD-Concrete | 3/8/2000 | 3/8/2000 | 3/8/2000 | P | PART |
|
|
|
r-bar placed 1st lift at ext shear walls
|
BLD-Framing/Rough-in | 3/8/2000 | 3/8/2000 | 3/8/2000 | P | PART |
|
|
|
need eng to signoff strap nailing
|
BLD-Foundation | 3/1/2000 | 3/2/2000 | 3/2/2000 | A | PART |
|
|
|
masonary - ed ###-####-chervon shear wall r-bar placed ok to pour pending sp insp approvals 3/2/00 3:46:43 PM
|
BLD-Concrete | 2/16/2000 | 2/17/2000 | 2/17/2000 | A | PART |
Tom Arcoraci
|
|
|
###-#### Ok pending spec. insp. report. 2/17/00 2:14:37 PM
|
BLD-Concrete | 2/1/2000 | 2/2/2000 | 2/2/2000 | A | PART |
|
|
|
Ed Cuttlers ###-#### made ok to pour with sp insp approvals 2/14/00 10:58:19 AM
|
BLD-Concrete | 1/24/2000 | 1/25/2000 | 1/25/2000 | P | PART |
|
|
|
Ed ###-#### madeok to on r-bar for new columns 1/26/00 8:22:24 AM pending sp insp approvals 1/26/00 8:22:52 AM
|
BLD-Concrete | 1/19/2000 | 1/20/2000 | 1/20/2000 | A | PART |
|
|
|
CONCRETE COLUMS---ED--- CELL ###-#### made ok to pour r-bar placed and sp insp approved 1/20/00 11:48:00 AM
|
BLD-Concrete | 1/13/2000 | 1/13/2000 | 1/13/2000 | P | PART |
Jim Storey
|
|
|
grouting at 2pm john ###-#### Topout & grout lift on e8,e7,e6&e1 ok to first floor elevation. Rebar & form repair pier engineering
|
BLD-Framing/Rough-in | 1/7/2000 | 1/10/2000 | 1/10/2000 | A | PART |
|
|
|
Masonry steel inspection John Carter ###-#### between 8-10 made ok with sp onsp approvals 2/10/00 11:31:21 AM
|
BLD-Concrete | 1/4/2000 | 1/5/2000 | 1/5/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 01/04/2000 at 13:55:10. Contact: ###-####made ok to po0r six columns in lower level for e/w brace frames 2" slump,weel barrow and 6" trinniy used with elec vibrator
|
BLD-Footing | 12/29/1999 | 12/29/1999 | 12/29/1999 | P | PART |
|
|
|
Scheduled by a contractor via Hello! on 12/29/1999 at 10:40:23. Contact: ###-####. Ok for R-bar conc. colums center shear East to West.
|
BLD-Concrete | 12/28/1999 | 12/28/1999 | 12/28/1999 | A | PART |
|
|
|
Spoke with engineer on epoxy bolting @ column to new.
|
BLD-Footing | 12/22/1999 | 12/23/1999 | 12/23/1999 | A | FAIL |
|
|
|
Scheduled by a contractor via Hello! on 12/22/1999 at 17:48:41. Contact: ###-####. R-bar placement must be corrected.
|
BLD-Footing | 12/17/1999 | 12/20/1999 | 12/20/1999 | A | FAIL |
|
|
|
Scheduled by a contractor via Hello! on 12/17/1999 at 17:51:19. Contact: ###-####. R-bar not complete.
|
BLD-Concrete | 2/8/2000 | 2/8/2000 | 2/10/1999 | P | PART |
|
|
|
###-#### ed madeok to pour lower beam s on the east side 2nd floor level walked project with cwestfall observed the attachments at brace frames and drag strut assemblies in progress 2/10/00 10:04:58 AM
|