BLD-Final | 10/25/2000 | 10/25/2000 | 10/25/2000 | P | PASS |
Tony Young
|
|
|
FN OCC BOB-- ###-#### CELL
c of c # 19858 issued 10/25/2000 3:22:13 PM
|
BLD-Final | 10/18/2000 | 10/19/2000 | 10/19/2000 | A | FAIL |
Tony Young
|
|
|
###-####
c/n posted, see owner 10/19/2000 10:32:01 AM
|
FIRE-Final Inspection | 10/18/2000 | 10/18/2000 | 10/18/2000 | P | PASS |
Rick Jackson
|
|
|
Scheduled by Inspector: 409 On 10/18/2000
|
BLD-Grading Inspection | 10/5/2000 | 10/5/2000 | 10/5/2000 | | PASS |
Rita DeYoung
|
|
|
Grading complete and approved
|
FIRE-Supply Line Cover | 7/13/2000 | 7/14/2000 | 7/14/2000 | A | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 07/13/2000 at 14:21:42. Contact: ###-####.; called the number above and they don't know why this was called in
|
FIRE-Supply Line Cover | 7/14/2000 | 7/14/2000 | 7/14/2000 | A | FAIL |
Joe Tawney
|
|
|
Fail uncover thrust blocks at riser.
|
BLD-Energy code compliance | 3/2/2000 | 3/3/2000 | 3/3/2000 | A | PASS |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 03/02/2000 at 19:35:42. Contact: ###-####.
|
BLD-Energy code compliance | 3/1/2000 | 3/2/2000 | 3/2/2000 | A | NR |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 03/01/2000 at 18:24:57. Contact: ###-####. Still need to complete upper floor vapor burrier. 3/2/00 2:26:06 PM
|
BLD-Energy code compliance | 3/2/2000 | 3/2/2000 | 3/2/2000 | P | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 03/02/2000 at 11:15:42. Contact: . Still not done upper floor vapor C/N. posted 2nd trip today. 3/3/00 9:05:44 AM
|
BLD-Framing/Rough-in | 2/22/2000 | 2/23/2000 | 2/23/2000 | A | FAIL |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 02/22/2000 at 08:21:15. Contact: ###-####. Fireblocking at upper floor area, fire sprinkler approval. 2/24/00 1:26:37 PM
|
BLD-Framing/Rough-in | 1/18/2000 | 1/19/2000 | 1/20/2000 | A | PART |
Jim Sly
|
|
|
###-#### Keep C/N; need eng's ok for drag strut & blocking 342 area. Shear nails ok. 1/20/00 8:56:18 AM
|
BLD-Framing/Rough-in | 1/19/2000 | 1/19/2000 | 1/19/2000 | A | PART |
Carl Dependahl
|
|
|
"Shear Insp." nailing ok; C/N: need eng's ok for blocking attachment @ drag strut & extend hold downs.
|
BLD-Foundation | 11/10/1999 | 11/10/1999 | 11/10/1999 | P | PASS |
|
|
|
CHRIS ###-#### FOUND R-bar placed.
|
BLD-Framing/Rough-in | 11/2/1999 | 11/3/1999 | 11/3/1999 | A | PASS |
Wes Worcester
|
|
|
STEVE--- ###-#### RE-BAR Eng. letter recieved by 342.
|
BLD-Footing | 11/2/1999 | 11/2/1999 | 11/2/1999 | P | FAIL |
Wes Worcester
|
|
|
FOR T INSP-- STEVE-- ###-#### Need eng's letter 3, rebar in place.
|