BLD-Final | 8/15/2000 | 8/15/2000 | 8/15/2000 | P | PASS |
Jim Storey
|
|
|
Added by Inspector: 301 On 8/15/2000 ok pending all sign offs. l/c
|
FIRE-Final Inspection | 7/27/2000 | 7/27/2000 | 7/27/2000 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 07/27/2000 at 07:35:12. Contact: ###-####.
|
FIRE-Final Inspection | 7/18/2000 | 7/19/2000 | 7/19/2000 | A | NR |
Rick Jackson
|
|
|
bob wheeler ###-#### fire fn Awaiting sprinkler requirements 7/20/00 8:46:21 AM
|
FIRE-Sprinkler Rough-in | 6/21/2000 | 6/21/2000 | 6/21/2000 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 06/21/2000 at 08:22:58. Contact: ###-####. - hydro okay
|
FIRE-Supply Line Flush | 6/12/2000 | 6/12/2000 | 6/12/2000 | P | PASS |
Rick Jackson
|
|
|
fire--dave 989- 1180===bld #3 Flush ok 6/13/00 2:37:45 PM
|
FIRE-Final Inspection | 5/31/2000 | 5/31/2000 | 5/31/2000 | A | FAIL |
Rick Jackson
|
|
|
David Gates ###-####; not ready for final
|
FIRE-Supply Line Flush | 5/30/2000 | 5/30/2000 | 5/30/2000 | P | NR |
Rick Jackson
|
|
|
###-#### DAve Water valve not accessible- United Water to repair. 5/31/00 9:25:43 AM
|
FIRE-Supply Line Flush | 5/22/2000 | 5/23/2000 | 5/23/2000 | A | FAIL |
Rick Jackson
|
|
|
###-#### Contractor not on site. 5/23/00 2:11:27 PM
|
FIRE-Supply Line Hydro | 5/22/2000 | 5/23/2000 | 5/23/2000 | P | FAIL |
Rick Jackson
|
|
|
###-#### Contractor not available 5/24/00 3:02:57 PM
|
BLD-Framing/Rough-in | 3/16/2000 | 3/17/2000 | 3/17/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 03/16/2000 at 15:29:10. Contact: ###-####.
|
BLD-Framing/Rough-in | 3/9/2000 | 3/10/2000 | 3/10/2000 | P | PASS |
Jim Storey
|
|
|
###-#### Shear ok. 3/14/00 11:27:28 AM
|
FIRE-Supply Line Flush | 2/28/2000 | 2/28/2000 | 2/28/2000 | P | PASS |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 02/28/2000 at 09:17:50. Contact: ###-####. Underground ok to cover. 3/1/00 10:56:17 AM
|
BLD-Framing/Rough-in | 2/2/2000 | 2/3/2000 | 2/3/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 02/02/2000 at 16:21:35. Contact: ###-####.
|
BLD-Framing/Rough-in | 1/31/2000 | 1/31/2000 | 1/31/2000 | P | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 01/31/2000 at 09:44:35. Contact: ###-####. placed with s.i report 2/1/00 9:08:24 AM
|
BLD-Framing/Rough-in | 1/27/2000 | 1/27/2000 | 1/27/2000 | P | PART |
|
|
|
Scheduled by a contractor via Hello! on 01/27/2000 at 10:39:10. Contact: ###-####. made ok to pour with sp insp pending 1/27/00 6:39:12 PM
|
BLD-Framing/Rough-in | 1/25/2000 | 1/26/2000 | 1/26/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 01/25/2000 at 16:57:21. Contact: ###-####. pending sp insp approvals 1/26/00 10:50:05 AM
|
BLD-Foundation | 12/20/1999 | 12/22/1999 | 12/22/1999 | A | FAIL |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 12/20/1999 at 15:18:08. Contact: ###-####. Engineer to address 1906.1-1906.3.12
|