BLD-Final | 12/4/2001 | 12/5/2001 | 12/5/2001 | P | PASS |
Russ Owen
|
|
|
###-#### MARK CALL FIRST . ok for perm oc, framing has been approved prior. 12/6/2001 9:57:28 AM
|
Permanent Occupancy | | 12/5/2001 | 12/5/2001 | | DONE |
|
|
|
|
BLD-Final | 11/13/2001 | 11/13/2001 | 11/13/2001 | P | CANC |
Dave Hannah
|
|
|
###-####
|
BLD-Final | 11/5/2001 | 11/5/2001 | 11/5/2001 | P | PART |
Russ Owen
|
|
|
###-#### MARK . All signatures on card, no temp oc has ever been issued for this job, no structural signature on card for temp oc, north area walls and doors not per plan at the 1 hr occupancy area need to know if this has been approved will check with 340. 11/5/2001 1:23:45 PM
|
FIRE-Final Inspection | 3/26/2001 | 3/26/2001 | 3/26/2001 | P | PASS |
Joe Tawney
|
|
|
Mark ###-#### Reinsp OK FOR CETIFICATE OF COMPLETION 3/27/2001 8:21:12 AM
|
FIRE-Final Inspection | 3/26/2001 | 3/26/2001 | 3/26/2001 | P | PASS |
Joe Tawney
|
|
|
Mark ###-#### Reinsp OK FOR CETIFICATE OF COMPLETION 3/27/2001 8:21:12 AM
|
FIRE-Final Inspection | 3/22/2001 | 3/22/2001 | 3/22/2001 | P | FAIL |
Joe Tawney
|
|
|
###-#### Reinsp Fail not all c/N items complete 3/23/2001 8:17:21 AM
|
BLD-Conference | 10/19/2000 | 10/20/2000 | 10/20/2000 | A | PART |
Carl Dependahl
|
|
|
mark ###-#### for conf, refire 10/20/2000 3:53:02 PM c/n 10/20/2000 3:53:06 PM
|
BLD-Final | 10/17/2000 | 10/18/2000 | 10/18/2000 | A | NR |
Tom Arcoraci
|
|
|
MARK ###-#### FN OCC no sigs on card 10/18/2000 11:07:21 AM
|
FIRE-Final Inspection | 10/18/2000 | 10/18/2000 | 10/18/2000 | P | FAIL |
Joe Tawney
|
|
|
Robert ###-#### OK on alarm test. Fail on final. C/N issued 10/19/2000 7:46:54 AM
|
BLD-Framing/Rough-in | 6/6/2000 | 6/6/2000 | 6/6/2000 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 06/06/2000 at 09:00:56. Contact: . Gyp @ "foyer" lid ok; need continuous membrane at walls (alarm box, etc.) 6/7/00 10:02:33 AM
|
BLD-Framing/Rough-in | 6/2/2000 | 6/2/2000 | 6/2/2000 | P | PART |
Carl Dependahl
|
|
|
Estap ###-#### Foyer area, shear walls ok to cover 6/5/00 10:47:23 AM
|
BLD-Framing/Rough-in | 6/1/2000 | 6/1/2000 | 6/1/2000 | P | FAIL |
Carl Dependahl
|
|
|
###-#### Recall when arch's detail ready. 6/5/00 10:33:29 AM
|
BLD-Framing/Rough-in | 5/31/2000 | 5/31/2000 | 5/31/2000 | P | FAIL |
Carl Dependahl
|
|
|
Mark Estep ###-#### Foyer area @ front: C/N, need arch's clarification re: shear panel locations. 6/1/00 2:30:48 PM
|
BLD-Framing/Rough-in | 5/30/2000 | 5/30/2000 | 5/30/2000 | P | FAIL |
Jim Sly
|
|
|
Estepp ###-#### NR 5/31/00 4:27:09 PM
|
BLD-Framing/Rough-in | 5/16/2000 | 5/16/2000 | 5/16/2000 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 05/16/2000 at 09:48:37. Contact: ###-####. Unable to contact bldr...recall. 5/17/00 1:57:20 PM
|
BLD-Framing/Rough-in | 5/9/2000 | 5/10/2000 | 5/10/2000 | P | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 05/09/2000 at 15:13:03. Contact: ###-####. Existing int. rooms ok to cover. 5/11/00 11:37:04 AM
|
BLD-Energy code compliance | 3/30/2000 | 3/31/2000 | 3/31/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/30/2000 at 12:01:59. Contact: ###-####. Ok to continue cover @ rear class rms 4/3/00 8:52:23 AM
|
BLD-Framing/Rough-in | 3/30/2000 | 3/31/2000 | 3/31/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/30/2000 at 12:01:16. Contact: ###-####. Rear class room C/N ok; ok to continue 1hr lid 4/3/00 8:52:08 AM
|
BLD-Framing/Rough-in | 3/22/2000 | 3/22/2000 | 3/22/2000 | P | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 03/22/2000 at 07:33:49. Contact: ###-####. 2nd- C/N- ok to continue 1st layer lid. 3/23/00 9:07:20 AM
|
BLD-Framing/Rough-in | 3/16/2000 | 3/17/2000 | 3/17/2000 | P | FAIL |
Carl Dependahl
|
|
|
###-#### C/N; need htg. r/I. 3/20/00 10:18:19 AM
|
BLD-Footing | 2/2/2000 | 2/3/2000 | 2/3/2000 | A | PART |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 02/02/2000 at 16:56:47. Contact: ###-####. FTG's & pads @ "front". 2/4/00 11:50:20 AM
|
BLD-Footing | 1/19/2000 | 1/19/2000 | 1/19/2000 | P | PART |
Carl Dependahl
|
|
|
###-#### Jerry Estep Ext. ftg. @ rear add'n.. no rebar noted on plans. 1/20/00 8:56:56 AM
|
BLD-Framing/Rough-in | 1/11/2000 | 1/11/2000 | 1/11/2000 | P | PART |
Carl Dependahl
|
|
|
jerry-- ###-#### fr insp. Office area only ok to cover, need Add'l fasteners at lid per ICBO T-7-C.
|
BLD-Framing/Rough-in | 1/4/2000 | 1/5/2000 | 1/5/2000 | A | FAIL |
Carl Dependahl
|
|
|
Scheduled by a contractor via Hello! on 01/04/2000 at 13:35:18. Contact: ###-####. Need firestopping @ ceiling lines..."strap" extended studs. Ok to 1st layer lid @ office area only.
|