BLD-Final | 7/19/2000 | 7/20/2000 | 7/20/2000 | A | PASS |
|
|
|
harvey ###-#### fn occ signed the perm col 7/20/2000 2:30:10 PM
|
Permanent Occupancy | | 7/20/2000 | 7/20/2000 | | DONE |
|
|
|
|
BLD-Final | 7/13/2000 | 7/14/2000 | 7/14/2000 | P | PART |
|
|
|
Scheduled by a contractor via Hello! on 07/13/2000 at 16:07:20. Contact: ###-####. temp occ ok for the wash tunnel and the vac bays only until compressor is taged by u.l. letter on file from owner that power will be terminated in 2-weeks if lable is not on compressor 7/14/2000 4:37:51 PM
|
FIRE-Final Inspection | 6/29/2000 | 6/30/2000 | 6/30/2000 | A | PASS |
Rick Jackson
|
|
|
steve ###-####
|
BLD-Framing/Rough-in | 5/24/2000 | 5/24/2000 | 5/24/2000 | P | PART |
|
|
|
###-#### information on the truss brace changes ok 5/26/00 6:57:54 AM
|
BLD-Framing/Rough-in | 5/19/2000 | 5/22/2000 | 5/22/2000 | A | PART |
|
|
|
rod ###-#### fr need desgn chang 5/24/00 2:55:57 PM rod ###-#### fr need design changes from arch submitted sealed by arch and engneed desgn chang 5/24/00 2:55:57 PM 5/24/00 2:56:31 PM
|
FIRE-Supply Line Hydro | 4/12/2000 | 4/13/2000 | 4/13/2000 | A | FAIL |
Rick Jackson
|
|
|
building not sprinklered - contractor to request plumbing inspection
|
BLD-Foundation | 4/4/2000 | 4/5/2000 | 4/5/2000 | P | PASS |
Jim Storey
|
|
|
###-####
|
BLD-Foundation | 3/24/2000 | 3/27/2000 | 3/27/2000 | A | PASS |
Russ Owen
|
|
|
###-#### Reinsp. at PM walls at mechanical room 3/28/00 9:14:57 AM
|
BLD-Footing | 3/22/2000 | 3/23/2000 | 3/23/2000 | A | PASS |
|
|
|
rod ###-#### r-bar placed in the footings 03/23/2000 12:57:14 PM
|
BLD-Footing | 3/21/2000 | 3/22/2000 | 3/22/2000 | A | NR |
Russ Owen
|
|
|
###-#### Need compaction report, need vent's tied up and need approved plans, notified person on site. 3/22/00 1:45:36 PM
|
BLD-Footing | 3/20/2000 | 3/21/2000 | 3/21/2000 | P | CANC |
Russ Owen
|
|
|
###-####
|
BLD-Foundation | 3/15/2000 | 3/16/2000 | 3/16/2000 | A | PASS |
Russ Owen
|
|
|
rod ###-#### Walls (West) side 3/16/00 2:27:48 PM
|
BLD-Foundation | 3/13/2000 | 3/14/2000 | 3/14/2000 | A | PART |
Tom Arcoraci
|
|
|
Rod ###-#### Soils report ok for West footing. 3/14/00 2:01:40 PM
|
BLD-Foundation | 3/9/2000 | 3/13/2000 | 3/13/2000 | A | FAIL |
Wes Worcester
|
|
|
Rejected MTI report, need scope of work letter & log in sheet, compaction report required- DO NOT POUR 3/24/00 1:57:13 PM
|
BLD-Concrete | 3/7/2000 | 3/7/2000 | 3/7/2000 | P | PART |
Russ Owen
|
|
|
early pm Rod ###-#### Walls. 3/8/00 10:36:55 AM
|
BLD-Foundation | 3/2/2000 | 3/3/2000 | 3/3/2000 | A | FAIL |
Russ Owen
|
|
|
###-#### rod\\Rebar Need ok for the center pit, not constructed per plan, as shown as Mono Pour. 3/6/00 1:44:58 PM
|
BLD-Concrete | 2/24/2000 | 2/25/2000 | 2/25/2000 | A | PART |
Russ Owen
|
|
|
###-#### early am Footings, partial on west side. 2/25/00 3:05:24 PM
|
BLD-Footing | 2/16/2000 | 2/17/2000 | 2/17/2000 | A | PART |
Russ Owen
|
|
|
###-#### Footings at carbays and fence on property line, soils ok by engineers compaction report. 2/18/00 3:24:54 PM
|
BLD-Footing | 2/15/2000 | 2/16/2000 | 2/16/2000 | A | CANC |
Russ Owen
|
|
|
rod ###-#### Will recall when ready. 2/16/00 2:34:17 PM
|
BLD-Conference | 2/8/2000 | 2/8/2000 | 2/8/2000 | P | PART |
Russ Owen
|
|
|
Rod ###-#### just need to submit for a permit addemdum to demolish existing mech room.
|