BLD-Final | 12/21/2000 | 12/21/2000 | 12/21/2000 | A | PASS |
Tony Young
|
|
|
Rec'd special inspection letter and ok for perm. occ. cert.
|
Permanent Occupancy | | 12/21/2000 | 12/21/2000 | | DONE |
|
|
|
|
BLD-Final | 12/7/2000 | 12/8/2000 | 12/8/2000 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 12/07/2000 at 14:48:49. Contact: ###-####.
temp. c of o signed, pending final letter of compliance from special inspection co.,, letter from arch. on fire damper in mech. room,, and threshholds on area seperation wall doors. 12/8/2000 12:56:14 PM
|
FIRE-Final Inspection | 12/5/2000 | 12/7/2000 | 12/7/2000 | P | PASS |
Rick Jackson
|
|
|
###-####
|
FIRE-Final Inspection | 12/4/2000 | 12/5/2000 | 12/5/2000 | P | FAIL |
Rick Jackson
|
|
|
Scheduled by a contractor via Hello! on 12/04/2000 at 09:19:28. Contact: ###-####.////// c/n issued - alarm and sprinkler issues; fire lane painting; exit sign 12/5/2000 3:54:29 PM
|
BLD-Framing/Rough-in | 10/20/2000 | 10/23/2000 | 10/23/2000 | A | PART |
Tony Young
|
|
|
###-####
ceiling grid in gym locker rooms 10/23/2000 9:02:55 AM
|
BLD-Framing/Rough-in | 9/18/2000 | 9/19/2000 | 9/19/2000 | A | PART |
Tony Young
|
|
|
Kelly ###-####
ROUGH FRAME OK IN LIBERARY CAREER CENTER S.E. CORNER... W/ # 338 9/19/2000 11:10:25 AM
|
BLD-Framing/Rough-in | 8/17/2000 | 8/18/2000 | 8/18/2000 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/17/2000 at 15:38:55. Contact: ###-####.
firewall where 2 rooflines meet on south-east side, perpandicular of gym wall 8/18/2000 3:14:09 PM
|
BLD-Framing/Rough-in | 8/16/2000 | 8/17/2000 | 8/17/2000 | P | FAIL |
Tom Arcoraci
|
|
|
KELLY ###-#### FR needs detail for occ sep wall jamb has been fire chalked 8/17/2000 4:54:58 PM
|
BLD-Conference | 8/14/2000 | 8/14/2000 | 8/14/2000 | P | PART |
|
|
|
Added by Inspector: 338 On 8/14/2000 with 415 and the super on a revision of the construction of the 1-hour occ sep wall
|
BLD-Framing/Rough-in | 8/14/2000 | 8/14/2000 | 8/14/2000 | P | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 08/14/2000 at 07:45:51. Contact: ###-####. conference on 1 hr. wall 8/14/2000 2:06:51 PM
|
BLD-Framing/Rough-in | 7/6/2000 | 7/7/2000 | 7/7/2000 | A | PART |
Tony Young
|
|
|
Scheduled by a contractor via Hello! on 07/06/2000 at 07:04:56. Contact: ###-####. Need approved plans- roof framing from gym to existing roof. 7/10/00 9:49:30 AM
|
BLD-Framing/Rough-in | 6/29/2000 | 7/3/2000 | 7/3/2000 | A | CANC |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 06/29/2000 at 14:03:08. Contact: ###-####. forgot to call and cancle insp. n/r 7/3/00 10:22:45 AM
|
BLD-Foundation | 5/30/2000 | 6/1/2000 | 6/1/2000 | A | PART |
|
|
|
Scheduled by a contractor via Hello! on 05/30/2000 at 14:00:39. Contact: ###-####. with sp insp aprovals 6/5/00 6:55:07 AM
|
BLD-Footing | 5/4/2000 | 5/5/2000 | 5/5/2000 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 05/04/2000 at 10:18:39. Contact: ###-####. Subject to special inspection, footing at area east wall, was access. 5/8/00 9:17:16 AM
|
BLD-Footing | 4/28/2000 | 5/2/2000 | 5/2/2000 | A | PART |
Russ Owen
|
|
|
Scheduled by a contractor via Hello! on 04/28/2000 at 12:32:02. Contact: ###-####. Need engineers clarification for verticals, called him and he is calling job foreman. 5/3/00 3:27:53 PM
|
BLD-Foundation | 4/25/2000 | 4/27/2000 | 4/27/2000 | A | PART |
Jim Storey
|
|
|
Scheduled by a contractor via Hello! on 04/25/2000 at 12:36:19. Contact: ###-####. 4 hr wall line west and north rebar ok pending special insp. report. 4/27/00 11:42:25 AM
|
BLD-Footing | 4/21/2000 | 4/24/2000 | 4/24/2000 | A | PASS |
|
|
|
Scheduled by a contractor via Hello! on 04/21/2000 at 16:10:32. Contact: ###-####. made ok 4/27/00 11:03:54 AM
|