Information based on query as of Saturday, July 20, 2024.
Permit Information
Permit NumberELE00-01560
StatusFinaled
Name MTN POWER ELECT CONTR
Site Address 200 W FRONT ST
Project NameCOURTHOUSE-SHELL/CORE
Customer Number 
ePlanReview 
Description
all electrical per approved plan final certificate of value $1,500,000.00 1/8/02-final cert lh
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final2/28/20023/1/20023/1/2002APASS
DetailsMarv Burrus
###-####. completed, 2/28/2002 3:55:02 PM
Electrical Rough-In1/30/20021/31/20021/31/2002APASS
DetailsMarv Burrus
###-#### CONFERENCE. completions necessary for final. 1/31/2002 9:57:39 AM
Final12/20/200112/21/200112/21/2001APART
DetailsMarv Burrus
Scheduled by a contractor via Hello! on 12/20/2001 at 18:12:47. Contact: ###-####. building; temporary occupancy only. 12/21/2001 12:54:53 PM
Final12/19/200112/20/200112/20/2001APART
DetailsMarv Burrus
###-#### DAVE. 1st floor; 5th floor, area 1. temporary occupancy. 12/20/2001 4:20:09 PM
Final12/18/200112/19/200112/19/2001PCANC
DetailsMarv Burrus
DAVE ###-####. kitchen knook area r/i. 12/19/2001 11:26:19 AM--cancel per marv/wrong insp/mls12/19/01
Final12/19/200112/19/200112/19/2001PPART
DetailsMarv Burrus
12/19/2001 12:00:07 PM. 5th floor; area 2: judges chambers, courtrooms temporary occupancy. 12/19/2001 2:45:26 PM
Final12/17/200112/18/200112/18/2001APART
DetailsMarv Burrus
Scheduled by a contractor via Hello! on 12/17/2001 at 10:34:21. Contact: ###-####.. 4th floor; areas 1 and 2; judges chambers, courtrooms. 12/18/2001 10:22:22 AM
Final12/18/200112/18/200112/18/2001PPART
DetailsMarv Burrus
###-####. 4th floor; areas 3 and 4. judges chambers, lobby;s. 12/18/2001 2:10:39 PM
Final12/14/200112/17/200112/17/2001APART
DetailsMarv Burrus
Scheduled by a contractor via Hello! on 12/14/2001 at 15:58:37. Contact: ###-####. areas #3 and 4, third floor; offices, restrooms, equiptment rooms and hall corridor. temporary occupancy. 12/17/2001 10:12:05 AM
Final12/13/200112/14/200112/14/2001PPART
DetailsMarv Burrus
###-#### DAVE. 3rd floor; areas 3 and 4, temporary occupancy. 12/14/2001 3:07:39 PM
Final12/12/200112/13/200112/13/2001APART
DetailsMarv Burrus
###-#### DAVE. 2nd floor; areas 3 and 4. 12/13/2001 10:58:07 AM
Final12/11/200112/12/200112/12/2001APART
DetailsMarv Burrus
Scheduled by a contractor via Hello! on 12/11/2001 at 07:02:52. Contact: .
2nd floor: courtrooms and judges chambers.
12/12/2001 10:56:03 AM
Final12/6/200112/10/200112/10/2001ACANC
DetailsMarv Burrus
###-#### dave. contractors request. will reschedule. 12/10/2001 9:28:24 AM
Electrical Rough-In12/5/200112/6/200112/6/2001PPART
DetailsMarv Burrus
###-#### DAVE. 1st floor; east/west corridor ceiling r/i. 2nd, 3rd, 4th floor elevator lobby ceiling r/i. 12/6/2001 2:35:32 PM
Electrical Rough-In11/21/200111/26/200111/26/2001PPASS
DetailsMarv Burrus
###-#### DAVE. 5th floor; ceiling r/i, lobby and corridorl. 11/26/2001 2:24:24 PM
Electrical Rough-In11/14/200111/15/200111/15/2001APASS
DetailsMarv Burrus
###-#### DAVE. 1st. floor: front lobby ceiling r/i. 3rd floor; computer room ceiling r/i. 4th floor corridor ceiling r/i. ok. 11/15/2001 9:12:02 AM
Electrical Rough-In11/6/200111/6/200111/6/2001PPASS
DetailsMarv Burrus
Added by Inspector: 403 On 11/6/2001 2:24:40 PM 3rd floor corridor ceiling r/i; 5th floor courtrooms ceiling r/i.
Final11/5/200111/6/200111/6/2001PCANC
DetailsMarv Burrus
###-#### dave. request should be for r/i. 11/6/2001 2:23:12 PM
Electrical Rough-In11/1/200111/2/200111/2/2001APART
DetailsMarv Burrus
###-####. basemnt. corridor ceiling r/i; 2nd floor corridor ceiling r/i; 2nd floor; mock courtroom ceiling r/i, corrections completed. 11/2/2001 9:36:35 AM
Electrical Rough-In10/31/200111/1/200111/1/2001AFAIL
DetailsMarv Burrus
DAVE ###-#### STAND BY GENERATOR .
no testing laboratory label. field evaluation testing required. corrections posted, 'not approved' red tag applied. 11/1/2001 1:39:09 PM
Electrical Rough-In10/30/200110/31/200110/31/2001APART
DetailsMarv Burrus
###-#### DAVE. 1st floor; wood-counter reception desks r/i. 4th floor ceiling r/i; judges chambers, hallways reception areas. 10/31/2001 10:59:35 AM
Final10/22/200110/23/200110/23/2001PPART
DetailsMarv Burrus
###-#### DAVE . 4th floor courtrooms ceiling r/i, ok. 10/23/2001 2:19:49 PM
Electrical Rough-In10/16/200110/18/200110/18/2001APASS
DetailsMarv Burrus
###-#### DAVE. 3rd floor ceiling r/i, except corridor and lobbyl 10/18/2001 10:59:03 AM
Electrical Rough-In10/11/200110/12/200110/12/2001APART
DetailsMarv Burrus
###-#### JOSH. 5th floor eastend courtroom; raised floor r/i. 10/12/2001 9:02:03 AM
Electrical Rough-In10/10/200110/11/200110/11/2001APASS
DetailsMarv Burrus
###-#### JOSH. conference; grid-wire support, recessed fixtures. 10/11/2001 9:07:53 AM
Electrical Rough-In10/8/200110/8/200110/8/2001PFAIL
DetailsJim Schmer
###-#### second floor ceiling Correction, low voltage wiring attached to conduit & west end court room covered without inspection- UNCOVER. 10/8/2001 11:57:44 AM
Electrical Rough-In10/1/200110/1/200110/1/2001PPASS
DetailsMarv Burrus
5th floor courtroom ###-####. raised floor area r/i. 10/1/2001 3:42:15 PM
Electrical Rough-In9/25/20019/26/20019/26/2001APASS
DetailsMarv Burrus
Scheduled by a contractor via Hello! on 09/25/2001 at 10:20:00. Contact: ###-####. 1st floor; commissioner hearing room, raised floor and ceiling r/i. 4th floor; courtroom eastend, raised floor r/i. 5th floor westend courtroom raised floor r/i. 9/26/2001 9:37:52 AM
Electrical Rough-In9/20/20019/21/20019/24/2001PPASS
DetailsMarv Burrus
Scheduled by a contractor via Hello! on 09/20/2001 at 12:54:14. Contact: ###-####. 9/21/2001 3:19:48 PM. 1st floor; ceiling r/i, areas #1,2,3,&4. 9/24/2001 9:34:10 AM
Electrical Rough-In9/14/20019/17/20019/17/2001APART
DetailsMarv Burrus
###-#### JOSH. bonding of fountail 9/17/2001 9:27:00 AM
Electrical Rough-In9/10/20019/11/20019/11/2001PPART
DetailsMarv Burrus
484- 3156. stairtowers, east and westend r/i.

9/11/2001 11:38:39 AM
Electrical Rough-In9/6/20019/6/20019/6/2001PPART
DetailsMarv Burrus
for conf-- josh- ###-####- . checked fountain testing-laboratory listing. ok 9/6/2001 2:03:51 PM
Electrical Rough-In8/24/20018/27/20018/27/2001APART
DetailsMarv Burrus
Scheduled by a contractor via Hello! on 08/24/2001 at 17:00:25. Contact: ###-####. .2nd floor; bathrooms, shower area-eastend. 8/27/2001 10:59:23 AM
Electrical Rough-In8/21/20018/21/20018/21/2001PPASS
DetailsMarv Burrus
cell ###-####- josh for conf. conference:
4th floor court-room raised floor covering, area #1. 8/21/2001 10:52:59 AM
Electrical Rough-In8/17/20018/20/20018/20/2001APART
DetailsMarv Burrus
Scheduled by a contractor via Hello! on 08/17/2001 at 10:28:20. Contact: ###-####. areas #1 and 2; corridors, lobby, vestibules ceiling r/i 2nd floor thru 5th floors.
areas #1 and 2; courtrooms decking/flooring r/i except area #1, 4th floor (raised floor was covered). 8/20/2001 11:35:20 AM
Electrical Rough-In8/7/20018/8/20018/8/2001PPART
DetailsMarv Burrus
Scheduled by a contractor via Hello! on 08/07/2001 at 15:18:47. Contact: ###-####. basement: 3 elevator lobby's, ceiling hard-lid; exterior soffit light r/i. 1st floor: retail lease area ceiling hard-lid r/i. 8/8/2001 2:22:32 PM
Electrical Rough-In7/30/20018/1/20018/1/2001PPART
DetailsMarv Burrus
Scheduled by a contractor via Hello! on 07/30/2001 at 15:16:20. Contact: ###-####. 1st floor: areas 2 & 3. 2nd floor: area 3 and court room, ceiling r/i only. 8/1/2001 2:16:23 PM
Electrical Rough-In7/30/20017/30/20017/30/2001PFAIL
DetailsJim Schmer
Josh ###-#### couldn't find work, josh didn't answere phone, called 3 times 7/30/2001 1:22:44 PM
Electrical Rough-In6/4/20016/5/20016/5/2001PPART
DetailsMarv Burrus
Scheduled by a contractor via Hello! on 06/04/2001 at 13:27:53. Contact: .
4th floor: area '4' r/i. ok.
6/5/2001 1:57:59 PM
Electrical Rough-In5/7/20015/8/20015/8/2001PPART
DetailsMarv Burrus
Scheduled by a contractor via Hello! on 05/07/2001 at 13:32:07. Contact: .
4th floor; area '3'. walls ele r/i.
5/8/2001 2:09:51 PM
Electrical Rough-In4/30/20015/2/20015/2/2001PPART
DetailsMarv Burrus
Josh ###-####. 5th floor; areas'1 & 2, walls ele r/i. 5/2/2001 3:09:12 PM
Electrical Rough-In4/25/20014/27/20014/27/2001PPART
DetailsMarv Burrus
Scheduled by a contractor via Hello! on 04/25/2001 at 14:18:20. Contact: .
basement: hard-lid ceiling ele r/i. 4/27/2001 1:40:13 PM
Electrical Rough-In4/9/20014/10/20014/10/2001APART
DetailsMarv Burrus
Scheduled by a contractor via Hello! on 04/09/2001 at 11:53:33. Contact: .
3rd floor, area 'e'; bathrooms, ele r/i. 4/10/2001 11:15:14 AM
Electrical Rough-In4/5/20014/9/20014/9/2001APART
DetailsMarv Burrus
###-####. 3rd floor: areas3 & 4. ele r/i, walls.
shall strap cable within 12 inches of boxes, (area 3 only). 4/9/2001 9:46:01 AM
Electrical Rough-In3/27/20013/28/20013/28/2001APART
DetailsJack Frank
josh Miller ###-#### ok 3/28/2001 11:50:12 AM
Electrical Rough-In3/26/20013/27/20013/27/2001APART
DetailsJack Frank
Scheduled by a contractor via Hello! on 03/26/2001 at 12:58:08. Contact: . area 3, 2nd floor only corrections area 4, 2nd floor and area 4 ,1st floor 300-4 and strap within 12 inches of boxes 3/27/2001 10:25:15 AM
Electrical Rough-In2/28/20013/1/20013/1/2001APART
DetailsMarv Burrus
###-####. 1st floor: area'e'. walls ele r/i. ok 3/1/2001 11:29:31 AM
Electrical Rough-In1/18/20011/23/20011/23/2001APART
DetailsMarv Burrus
Scheduled by a contractor via Hello! on 01/18/2001 at 13:31:04. Contact: .
areas #1 & 2; 3rd and 4th floors, walls ele r/i. 1/23/2001 10:51:42 AM
Electrical Rough-In12/12/200012/13/200012/13/2000APART
DetailsMarv Burrus
on the second floor DAve ###-####. 2nd floor, areas 1and2; walls ele r/i. 12/13/2000 11:12:47 AM
Electrical Rough-In11/13/200011/15/200011/15/2000APART
DetailsMarv Burrus
Scheduled by a contractor via Hello! on 11/13/2000 at 11:48:06. Contact: ###-####. areas 1 & 2, first floor ele r/i. 11/15/2000 9:29:38 PM
Electrical Rough-In9/27/20009/27/20009/27/2000PPART
DetailsMarv Burrus
R/I DAVE -###-#### . sub-panel disconnect for crane/elevator. 9/27/2000 10:30:10 PM
Electrical Rough-In9/20/20009/21/20009/21/2000APART
DetailsMarv Burrus
###-#### conf only \\8:00 or 8:30 he says he talked to you about the time. proper grounding of mc/ac cable. 9/22/2000 5:03:52 PM
Permanent Service9/18/20009/18/20009/18/2000PPASS
DetailsMarv Burrus
###-####. main service gear. 9/18/2000 5:48:50 PM
Electrical Rough-In9/7/20009/8/20009/8/2000APART
DetailsMarv Burrus
Scheduled by a contractor via Hello! on 09/07/2000 at 14:11:34. Contact: . conference; branch-circuit raceway use. 9/10/2000 6:02:54 PM
Electrical Rough-In8/31/20009/5/20009/5/2000APART
DetailsMarv Burrus
conference after 10:00 Mike ###-####. discussed clearences for bus-ducting. 9/5/2000 12:57:00 PM
Electrical Rough-In7/7/20007/10/20007/10/2000APART
DetailsMike Kinnear
Josh ###-#### Ok cover floor NW corner 7/10/00 2:51:45 PM
Electrical Rough-In6/8/20006/9/20006/9/2000APART
DetailsMarv Burrus
Josh ###-#### conference, grounding/ufer
Electrical Rough-In5/22/20005/22/20005/22/2000PPASS
DetailsMike Kinnear
underground ###-#### Ok cover underground main feeders conduit 5/23/00 2:28:35 PM
Electrical Rough-In5/3/20005/3/20005/3/2000PPART
DetailsMarv Burrus
for conf-- ###-#### Conference; main service grounding. 5/4/00 4:52:45 PM