Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberELE07-03315
StatusFinaled
Name HELL'S CANYON ELECTRIC
Site Address 251 W GOWEN RD
Project NameWestern Trailers
Customer Number 
ePlanReview 
Description
All new electrical in a new trailer manufacturing building per initial cert of value $280,000///9/24/07 BAS
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final7/10/20087/10/20087/10/2008PPASS
DetailsMike Kinnear
Matt Phone #: ###-#### ok final note esc permit on hold
Final7/9/20087/9/20087/9/2008PPART
DetailsMike Kinnear
Matt Phone #: ###-#### all inside work completed just needs outside conduit inspection note parcel hold on esc permit
Final7/2/20087/2/20087/2/2008PPART
DetailsMike Kinnear
Matt Phone #: ###-#### ok temp. occ.ok signed card. welders, panel labling, & outside conduit run for parking lot lights.
Electrical Rough-In6/4/20086/4/20086/4/2008PPASS
DetailsMike Kinnear
Matt Phone #: ###-#### ok cover back offices ceiling only note hold on esc permit unable to add inspection
Electrical Rough-In6/3/20086/4/20086/4/2008ANR
DetailsMike Kinnear
Mat; Phone #: ###-#### Internet Inspection Request from: Cathy Weisshaupt t/w mat they resched for this afternoon inspection
Electrical Rough-In5/30/20085/30/20085/30/2008PPASS
DetailsWilliam E Thomas
matt - ###-#### - ceiling cover - as early as possible
. .1. ok to cover cieling. . .
Electrical Rough-In5/27/20085/28/20085/28/2008ANR
DetailsMike Kinnear
Scheduled by a contractor via Hello! on 5/27/2008 at 12:32:02 PM. Contact: ###-####. nec300.11(A)(2) id wires, make needs to be completed, & all wires off ceiling grid
Conference4/25/20084/25/20084/25/2008PDONE
DetailsJack Frank
talked with engneer and contr, 240.21(C) (3) shall provide conductors from X former secondary taps rated for 725 amps or prvide main breaker ahead of 120/208 panel
Conference4/24/20084/24/20084/24/2008PDONE
DetailsJack Frank
met with journeyman and talked with Skip the owner ok ELE contr about overcurrent protection required for secondary side of Xformer
Permanent Service4/23/20084/23/20084/23/2008PPASS
DetailsMike Kinnear
Scheduled by a contractor via Hello! on 4/23/2008 at 6:57:30 AM. Contact: ###-####. p/s u/g n ok note correction on secondary side of transformer NEC240.21(B)(2)(2) secondary conductors shall terminal in the proper size brker or fuses. & grounding properly done
Electrical Rough-In4/21/20084/21/20084/21/2008PPASS
DetailsWilliam E Thomas
Scheduled by a contractor via Hello! on 4/21/2008 at 10:00:11 AM. Contact: ###-####.
. .1. ri ok. . .
Electrical Rough-In4/9/20084/10/20084/10/2008PPART
DetailsMike Kinnear
Scheduled by a contractor via Hello! on 4/9/2008 at 4:24:21 PM. Contact: ###-####. ok cover walls & hard lid ceilings expect second floor stair area & east side of building
Electrical Rough-In4/7/20084/8/20084/8/2008APART
DetailsPat Lass
matt Phone #: ###-####
firsr floor parts room walls ok
Electrical Rough-In11/9/200711/13/200711/13/2007APART
DetailsMike Kinnear
Scheduled by a contractor via Hello! on 11/9/2007 at 3:20:33 PM. Contact: ###-####. ok cover under slab conduit north east side only
Temporary Service11/9/200711/13/200711/13/2007ACANC
DetailsMike Kinnear
Scheduled by a contractor via Hello! on 11/9/2007 at 3:19:37 PM. Contact: ###-####.
Electrical Rough-In11/7/200711/8/200711/8/2007APASS
DetailsMike Kinnear
underground--for temp job shack--gib; Phone #: ###-#### Internet Inspection Request from: Barbara Stitt ok cover underground conduit for temp job shack
Electrical Rough-In10/30/200710/31/200710/31/2007APART
DetailsMike Kinnear
skip Note: cover up for trench Phone #: ###-#### ok cover under ground conduit feeders from transformer & 4inch & 1inch southeast corner parking lot
Electrical Rough-In10/25/200710/26/200710/26/2007APART
DetailsBob Reichert
matt - underground Phone #: ###-#### called contractor, ok to cover 3/4" conduit in center areas only, still needs spacers for service conduit, will leave open, told contractor 2" going out to parking lot lighting out west side building had to be lowered to 2' deep, no plans to sign yet
Electrical Rough-In10/23/200710/24/200710/24/2007APART
DetailsMike Kinnear
matt Note: underground Phone #: ###-#### ok cover conduit feeders from service to middle of building
Electrical Rough-In10/22/200710/23/200710/23/2007APART
DetailsMike Kinnear
justin Note: under/conduit inspect Phone #: ###-#### conf need to see under ground feeders (pot hole) need to uncover service conduits & comply with nec310.15 duct bank requirements
Electrical Rough-In9/24/20079/25/2007 A 
Upher ground inpsection please Justin ###-####