Final | 5/23/2008 | 5/23/2008 | 5/23/2008 | P | PASS |
Bob Reichert
|
|
|
Phone #: ###-#### Internet Inspection Request from: Scott Abbott called contractor, ok to final
|
Conference | 5/6/2008 | 5/6/2008 | 5/6/2008 | P | DONE |
Bob Reichert
|
|
|
We have made some changes. The riser will only be 9 inches above the tank so we changed out the pvc to ridgid and wraped it with corrision tape they would like to back fill tommorow thanks Scott Phone #: ###-#### Internet Inspection Request from: Scott Abbott talked to contractor, see ri
|
Electrical Rough-In | 5/6/2008 | 5/6/2008 | 5/6/2008 | P | PASS |
Bob Reichert
|
|
|
We have made some changes. The riser will only be 9 inches above the tank so we changed out the pvc to ridgid and wraped it with corrision tape they would like to back fill tommorow thanks Scott Phone #: ###-#### Internet Inspection Request from: Scott Abbott ok to cover raceway at east end
|
Final | 4/25/2008 | 4/25/2008 | 4/25/2008 | P | CANC |
Bob Reichert
|
|
|
this project is at the restroom on the golf coarse Phone #: ###-#### Internet Inspection Request from: Scott Abbott talked to contractor, need to see final grade, see ri
|
Electrical Rough-In | 4/25/2008 | 4/25/2008 | 4/25/2008 | P | PASS |
Bob Reichert
|
|
|
this project is at the restroom on the golf coarse Phone #: ###-#### Internet Inspection Request from: Scott Abbott called contractor, u/g ok to cover, need to see final installation and cover for pull-box
|