Final | 11/16/2009 | 11/17/2009 | 11/17/2009 | A | PASS |
Bob Reichert
|
|
|
steve Phone #: ###-#### ok to final, no card to sign
|
Permanent Service | 10/29/2009 | 10/29/2009 | 10/29/2009 | P | PASS |
Doug A Poedy
|
|
|
Doug/Bob, We are changing out the service on the Boise Rescue Misson Dorm today. Idaho Power is shutting off at 9am. We hope to be complete by 2pm. Please arrive at 1pm if possible. This is a critical change as the service feeds 8 apartments. We have to get it heated up asap! Thanks, Steve Harris ###-#### or Loren Ramsey ###-#### Phone #: ###-#### Internet Inspection Request from: Loren Ramsey. P/S U/G Reconnect ok.
|
Electrical Rough-In | 10/8/2009 | 10/9/2009 | 10/9/2009 | A | PASS |
Doug A Poedy
|
|
|
steve Phone #: ###-####. Ok to cover.
|
Electrical Rough-In | 9/30/2009 | 10/1/2009 | 10/1/2009 | A | PART |
Doug A Poedy
|
|
|
Steve Phone #: ###-####. ok to cover except for electrical room, riser room, and mech. room.
|
Electrical Rough-In | 8/27/2009 | 8/27/2009 | 8/27/2009 | P | PART |
Doug A Poedy
|
|
|
Steve Phone #: ###-####. Ok to cover underground conduit for street lighting.
|
Electrical Rough-In | 8/26/2009 | 8/26/2009 | 8/26/2009 | P | PART |
Doug A Poedy
|
|
|
Steve Phone #: ###-####. Ok to cover driveway section of underground conduit.
|
Conference | 8/25/2009 | 8/26/2009 | 8/26/2009 | P | DONE |
Doug A Poedy
|
|
|
Steve Phone #: ###-####
|
Electrical Rough-In | 8/24/2009 | 8/25/2009 | 8/25/2009 | A | PASS |
Doug A Poedy
|
|
|
Steve-Underground upher inspection please Phone #: ###-####. Concrete encased electrode looks gtood. Ok to cover.
|
Electrical Rough-In | 8/19/2009 | 8/20/2009 | 8/20/2009 | A | PASS |
Doug A Poedy
|
|
|
steve - undergruond Phone #: ###-####. Ok to cover concrete encased electrode with 2 inches of concrete.
|
Electrical Rough-In | 8/19/2009 | 8/19/2009 | 8/19/2009 | P | FAIL |
Doug A Poedy
|
|
|
Steve Harris-underground inspection please Phone #: ###-####. NEC 250.52 3 Concrete encased electrode needs to be on footing.
|