Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberELE12-01410
StatusFinaled
Name TRI STATE ELECTRIC
Site Address 7210 W BARRISTER DR
Project Name 
Customer Number 
ePlanReviewNo
Description
Electrical Permit - Addition: Ada County Jail POD D Expansion
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final6/6/20136/7/20136/7/2013PPASS
DetailsDaryl DeGrange
Contact: Clay Freinwald Phone #: ###-#### >> Inspection requested via web by Deb Gooden final ok
Final4/26/20134/29/20134/29/2013APART
DetailsDaryl DeGrange
Contact: Clay Freinwald Phone #: ###-#### >> Inspection requested via web by Deb Gooden temporary occupancy ok
Electrical Rough-In4/9/20134/10/20134/10/2013APASS
DetailsDaryl DeGrange
Contact: Clay Freinwald - ceiling inspection please Phone #: ###-#### >> Inspection requested via web by Deb Gooden rough-in ok cover ceiling grid 1500,1600,1700, and control room
Electrical Rough-In3/13/20133/15/20133/15/2013PPASS
DetailsDaryl DeGrange
Contact: Clay Freinwald - ceiling rough-in please Phone #: ###-#### >> Inspection requested via web by Deb Gooden rough-in ok cover ceiling grid as per highlighted in green and dated
Electrical Rough-In3/12/20133/12/20133/12/2013PPASS
DetailsDaryl DeGrange
Contact: Clay Freinwald, ceiling rough-in inspection please Phone #: ###-#### >> Inspection requested via web by Deb Gooden rough-in ok cover areas as per highlighted in blue and dated on plan
Electrical Rough-In1/25/20131/29/20131/29/2013APASS
DetailsDaryl DeGrange
Contact: Clay Freinwald Phone #: ###-#### >> Inspection requested via web by Deb Gooden rough-in ok 2 rooms as highlighted and dated on plans
Electrical Rough-In10/9/201210/9/201210/9/2012PPASS
DetailsDaryl DeGrange
2ND FLOOR CONCRETE SLAB INSPECTION PLEASE Phone #: ###-#### >> Inspection requested via web by Deb Gooden rough-in ok pour slab 2nd floor
Electrical Rough-In9/28/20129/28/20129/28/2012PPASS
DetailsDaryl DeGrange
Contact: Clat Freinwald. 2nd floor slab inspection please Phone #: ###-#### >> Inspection requested via web by Deb Gooden rough-in ok cover conduits in 2nd floor slab
Electrical Rough-In8/24/20128/27/20128/27/2012AFAIL
DetailsBob Reichert
NEC 352.26 there shall not be more than 360 degrees total bends between pull points
Electrical Rough-In8/13/20128/15/20128/15/2012APASS
DetailsDaryl DeGrange
Contact: Clay Frienwald - underground inspection please Phone #: ###-#### >> Inspection requested via web by Deb Gooden rough-in ok cover heat cable two locations SW &SE corners concrete pour
Electrical Rough-In8/13/20128/14/20128/14/2012APASS
DetailsDaryl DeGrange
Contact: Clay Frienwald - underground inspection please Phone #: ###-#### >> Inspection requested via web by Deb rough-in ok cover NW corner underground
Electrical Rough-In8/10/20128/13/20128/13/2012APASS
DetailsDaryl DeGrange
Contact: Clay Frienwald underground inspection please Phone #: ###-#### >> Inspection requested via web by Deb Gooden rough-in ok cover east half concrete slab
Electrical Rough-In8/7/20128/8/20128/8/2012APART
DetailsBob Reichert
Contact: Clay Frienwald, underground inspection please Phone #: ###-#### >> Inspection requested via web by Deb Gooden u/g from transformer ok towards building only, will see rest out of building later