Information based on query as of Friday, June 28, 2024.
Permit Information
Permit NumberELE14-02710
StatusFinaled
Name PRIORITY ELECTRIC
Site Address 5701 W ALBATROS ST
Project Name 
Customer Number 
ePlanReviewNo
Description
Electrical Permit - New: Two new metal buildings for Idaho Power. New service and branch circuits.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final6/23/20156/24/20156/24/2015APASS
DetailsRex Boyles
Phone #: ###-#### Inspection requested via web by Thomas Jenkins final ok
Final4/23/20154/23/20154/23/2015PPART
DetailsRex Boyles
Temporary final for job. Looking for final on metal building wash bay to be done at later time. Phone #: ###-#### Inspection requested via web by Thomas Jenkins 406.8(B)-15 and 20 amp exterior receptacles shall be UV rated. 110.16-All electrical equiptment , loadcenters,etc shall have arc flash label clearly visable. HVAC equiptment "maximum fuse" exceeded on some equiptment. Panel directory not accurate.TEMP. OCCUPANCY OK. REX GAVE THE OK TO CHANGE TO A PART blh 5-1-15
Electrical Rough-In2/18/20152/19/20152/19/2015APASS
DetailsRex Boyles
underground Phone #: ###-#### Inspection requested via web by Thomas Jenkins r/i u.ground ok to car chargers and grounding electrode conductor at wash bay ok
Electrical Rough-In2/13/20152/13/20152/13/2015APASS
DetailsRex Boyles
Underground Phone #: ###-#### Inspection requested via web by Thomas Jenkins r/i u.ground to wash bay and R&D area ok
Electrical Rough-In2/11/20152/12/20152/12/2015APASS
DetailsRex Boyles
underground and uffer fix. Phone #: ###-#### Inspection requested via web by Thomas Jenkins r/i u.ground east outside slab ok. Look for #4 ufer on next insp. to bldg. footing
Permanent Service2/2/20152/3/20152/3/2015APASS
DetailsRex Boyles
Phone #: ###-#### Inspection requested via web by Thomas Jenkins p/s u/g n ok verify ground conductor to bldg. steel and water pipe and plastic bushings inside transformer upon return. Also picture of grounding electrode to concrete footing connection.
Electrical Rough-In2/2/20152/3/20152/3/2015APASS
DetailsRex Boyles
Rough for change order work. Phone #: ###-#### Inspection requested via web by Thomas Jenkins r/i main bldg. walls ok r/i underground ok inside wash bay bldg.
Electrical Rough-In1/15/20151/16/20151/16/2015APASS
DetailsRex Boyles
Phone #: ###-#### Inspection requested via web by Thomas Jenkins r/i walls ok
Electrical Rough-In10/8/201410/8/201410/8/2014APASS
DetailsRock A. Hudson
Please call 30 min before you get there so someone can meet you there to let you in. Phone #: ###-#### Inspection requested via web by Thomas Jenkins All underground in main bldg and 1 in small pull thru bldg rough in ok cover
Conference10/6/201410/6/201410/6/2014PDONE
DetailsRock A. Hudson
Conference to figure out ufer ground Phone #: ###-#### Inspection requested via web by Thomas Jenkins Concrete encased and building steel are grounding electrodes for this service. 250.52 Grounding Electrodes.
(A) Electrodes Permitted for Grounding
(3) Concrete-Encased Electrode. A concrete-encased electrode
shall consist of at least 6.0 m (20 ft) of either (1) or (2):
(1) One or more bare or zinc galvanized or other electrically
conductive coated steel reinforcing bars or rods of
not less than 13 mm (1/2 in.) in diameter, installed in
one continuous 6.0 m (20 ft) length, or if in multiple
pieces connected together by the usual steel tie wires,
exothermic welding, welding, or other effective means
to create a 6.0 m (20 ft) or greater length; or
(2) Bare copper conductor not smaller than 4 AWG