Information based on query as of Thursday, June 20, 2024.
Permit Information
Permit NumberELE15-02132
StatusFinaled
Name LEA ELECTRIC LLC
Site Address 1004 W ROYAL BLVD
Project Name 
Customer Number2014-07
ePlanReviewNo
Description
New: Install power and lighting for the West Wing apartment units, including panels, fixtures, wiring devices.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final8/25/20158/26/20158/26/2015APASS
DetailsRex Boyles
Units 5th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo final 100% ok rm 540 and corridors perm. occupancy ok
Final8/24/20158/25/20158/25/2015APART
DetailsRex Boyles
Unit inspections, 5th floor west wing. Phone #: ###-#### Inspection requested via web by Rafael Castillo final 100% except rm 540 and corridors
Final8/14/20158/15/20158/15/2015PCANC
DetailsRex Boyles
Rafial - ###-#### finished in the AM inspection. not needed
Final8/14/20158/15/20158/15/2015APART
DetailsRex Boyles
Rafial - ###-#### still need GFCI breakers for spa and pump inspection. Temp.occupancy ok 1st floor NO SPA USAGE
Final8/14/20158/14/20158/14/2015PPART
DetailsRex Boyles
Units 3rd and 4th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo final ok rms. 322 and 424. Temporary occupancy ok for 2nd floor rooms and corridors and lobbys 100% complete.
Final8/14/20158/14/20158/14/2015APART
DetailsRex Boyles
Unit inspections, 3rd and 4th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo final ok rms. 319, 326, 322 424
Final8/13/20158/13/20158/13/2015PPART
DetailsRex Boyles
Final inspections for units. Phone #: ###-#### Inspection requested via web by Rafael Castillo final ok rms. 421 thru 423, 425 thru 432, 434 thru 442
Electrical Rough-In8/13/20158/13/20158/13/2015APASS
DetailsRex Boyles
Corridor grid ceiling inspection, 5th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok
Final8/10/20158/10/20158/10/2015PPART
DetailsRex Boyles
Unit final inspections 2nd and 3rd floors. Phone #: ###-#### Inspection requested via web by Rafael Castillo all units inspected previously now have CFL lamps to meet 50% energy effiecient lamps, including todays inspections. All exterior receptacles on 2nd floor ok now. final ok rms. 321, 323 thru 325, 327 thru 334, 336 thru 341
Electrical Rough-In8/7/20158/7/20158/7/2015APASS
DetailsRex Boyles
Corridor ceilings 4th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ceilings west wing corridor ok
Electrical Rough-In8/6/20158/6/20158/6/2015PNR
DetailsRex Boyles
4th floor corridor grid ceiling inspection. Phone #: ###-#### Inspection requested via web by Rafael Castillo not ready
Final8/5/20158/5/20158/5/2015PNR
DetailsRex Boyles
Final inspections units 2nd floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo dishwashers not in yet
Final8/5/20158/5/20158/5/2015APART
DetailsRex Boyles
Final inspections units 2nd floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo final ok rms. 221, 224 thru 231, 232 thru 241. exterior receptacles not done in rms. 200, 218, 223 and 233. All rooms still need 50% energy efficient lamps.
Electrical Rough-In7/31/20157/31/20157/31/2015PPASS
DetailsRex Boyles
2nd floor t grid ceiling inspection, corridors only. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok to cover
Electrical Rough-In7/31/20157/31/20157/31/2015APASS
DetailsRex Boyles
3rd floor t grid ceiling inspection, corridors only. Phone #: ###-#### Inspection requested via web by Rafael Castillo 3rd flr corridor ceiling r/i ok
Electrical Rough-In7/31/20157/31/20157/31/2015PCANC
DetailsRex Boyles
3rd floor west corridor grid ceiling. Phone #: ###-#### >> Inspection requested via web by Rafael Castillo Inspection cancelled from web by: Rafael Castillo
Electrical Rough-In7/30/20157/30/20157/30/2015PNR
DetailsRex Boyles
Grid ceiling inspection 3rd floor corridors. Phone #: ###-#### Inspection requested via web by Rafael Castillo not ready
Conference7/23/20157/24/20157/24/2015ADONE
DetailsRex Boyles
Discuss location of receptacles in islands. Phone #: ###-#### Inspection requested via web by Rafael Castillo cut in receptacles under countertop instead of cabinets ok Discuss temp. occupancy status after rooms are finaled is ok per wing
Electrical Rough-In7/23/20157/23/20157/23/2015APASS
DetailsRex Boyles
5th floor drop ceilings. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok drop ceiling in rm. 542
Electrical Rough-In7/22/20157/22/20157/22/2015PNR
DetailsRex Boyles
5th floor drop ceiling. Phone #: ###-#### Inspection requested via web by Rafael Castillo not ready
Electrical Rough-In7/21/20157/21/20157/21/2015PPASS
DetailsRex Boyles
5th floor drop ceiling. Phone #: ###-#### Inspection requested via web by Rafael Castillo R/I OK DROP CEILINGS in rms 534 thru 537, 539 and 541
Electrical Rough-In7/21/20157/21/20157/21/2015APASS
DetailsRex Boyles
Drop ceiling rough in. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok drop ceilings rms 530 and 532
Electrical Rough-In7/15/20157/15/20157/15/2015APASS
DetailsRex Boyles
Drop ceilings 3rd floor, units 5th floor, shafts 4th floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok drop ceilings in rms. 301 thru 304, 332, 335, 338 and 339. r/i ok rms 532,534,535 thru 541. r/i ok vent. shafts in 402 thru 405 and 407
Electrical Rough-In6/30/20156/30/20156/30/2015APASS
DetailsRex Boyles
4th floor drop ceiling. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok drop ceiling rm. 419
Electrical Rough-In6/29/20156/29/20156/29/2015APASS
DetailsRex Boyles
4th floor drop ceilings. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i drop ceilings in rms. 421,422,423,424 and 430
Electrical Rough-In6/26/20156/26/20156/26/2015APASS
DetailsRex Boyles
5th floor shafts, 4th floor drop ceilings, 5th floor corridors. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok 100% vent. shafts on 5th flr., rm. 554, drop ceilings in rms.440,441,425 and426, 5th flr. west wing corridor receptacles and sconces, parking lot u.ground conduits to light poles also ok. (Light poles are pre cast)
Electrical Rough-In6/22/20156/22/20156/22/2015APASS
DetailsRex Boyles
4th floor unit drop ceilings. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok drop ceilings in rms. 401, 408, 410, 411, 413, 414, 416, 443 and 444
Electrical Rough-In6/18/20156/18/20156/18/2015APASS
DetailsDaryl DeGrange
5th floor corridors, stairwell "D" rough-in. Phone #: ###-#### Inspection requested via web by Rafael Castillo rough-in ok cover 5th floor corridors and stairwell "D"
Conference6/15/20156/16/20156/16/2015ADONE
DetailsDaryl DeGrange
Discuss possibility of final on half of the residential units by August 15 and the other half at a later date. Phone #: ###-#### Inspection requested via web by Rafael Castillo Temporary occupancy would require approval from Project Management Ron Hill and Fire Marshall Romeo Gervais
Electrical Rough-In6/15/20156/16/20156/16/2015APASS
DetailsDaryl DeGrange
4th floor corridors, soffit ceilings (drops in units). Phone #: ###-#### Inspection requested via web by Rafael Castillo Rough-in ok cover
Electrical Rough-In6/15/20156/15/20156/15/2015APASS
DetailsDaryl DeGrange
Drop ceilings 3rd floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo Rough-in ok cover drop ceilings in rooms 329,321,325,342 and service feeders shafts 421,425,431,433
Electrical Rough-In6/11/20156/11/20156/11/2015APASS
DetailsRex Boyles
Drop ceilings 3rd floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo already input info. did'nt go away 1st time
Electrical Rough-In6/8/20156/8/20156/8/2015APASS
DetailsRex Boyles
5th floor unit rough in west wing. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok rms. 521 thru 531
Final6/8/20156/8/20156/8/2015ACANC
DetailsRex Boyles
5th floor unit rough in west wing. Phone #: ###-#### Inspection requested via web by Rafael Castillo needed r/i
Electrical Rough-In6/1/20156/1/20156/1/2015APASS
DetailsRex Boyles
Drop ceiling rough in 2nd floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok drop ceilings in rms. 225,231,233,242,344,343 and 309
Electrical Rough-In5/29/20155/29/20155/29/2015APASS
DetailsRex Boyles
4th floor units. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok rms. 421 thru 431, vent. shafts in rms. 422thru424 and 425 thru430
Electrical Rough-In5/27/20155/28/20155/28/2015APASS
DetailsRex Boyles
4th floor units, drop ceilings 2nd and 3rd floors. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok rms. 431 thru 442 and vent. shafts in rms. 436 and 432. Drop ceilings in rms. 305 thru 307, 311 thru313, 314,315,318 and 320.
Electrical Rough-In5/27/20155/27/20155/27/2015APASS
DetailsRex Boyles
2nd floor shaft inspection, 4th floor units inspection. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok vent. shafts in rms. 225,231 and 233
Electrical Rough-In5/22/20155/22/20155/22/2015APASS
DetailsRex Boyles
Stairwell "B" inspection. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok stairwell B 2 thru 5 and vent. shaft 242
Electrical Rough-In5/15/20155/18/20155/18/2015APASS
DetailsRex Boyles
Units rough-in 3rd floor west wing, shafts 2nd and 3rd floor. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok so. west wing rms. 221 thru230, vent. shafts in 232,234 thru 237, 239 and 332,334 thru 337 and 339 also ok
Electrical Rough-In5/15/20155/15/20155/15/2015APASS
DetailsRex Boyles
Rough-in shafts 3rd floor, units 3rd floor west, permanent service MMC#2. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok west wing 3rd flr rms. 331 thru 335, 337 thru 341 and partial on vent. shafts (see plans)
Electrical Rough-In5/12/20155/12/20155/12/2015APASS
DetailsRex Boyles
2nd floor drop ceilings, roof inspection. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok rm. soffits in 212,217,218,220,243 and 244. Also 2nd flr balcony ceiling ok to cover south half of west wing roof complete. OK to install nm cable now.
Electrical Rough-In4/16/20154/16/20154/16/2015APASS
DetailsRex Boyles
Inspection of 2 hour shafts east wing, stairwell "A". Roof over east wing progress. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok shafts in rms. 205, 213 thru 216. roof work on east should be complete friday(tomm). Rafael will keep checking and let us know when it's ready to continue electrical installation.
Electrical Rough-In4/15/20154/15/20154/15/2015APASS
DetailsRex Boyles
Shaft walls on 2nd floor for cover. Look over roof progress over east end of building. Phone #: ###-#### Inspection requested via web by Rafael Castillo partial r/i ok 2 hr vent. shafts in rms. 202 thru 204, 206,211 and 212 NOTE: walk with Rafael to see if roof is complete on east wing and it is not done. No electrical wire in this area or any areas not dried in.
Electrical Rough-In3/20/20153/20/20153/20/2015APASS
DetailsRex Boyles
Rough-in west wing units. Phone #: ###-#### Inspection requested via web by Rafael Castillo r/i ok 2nd floor west wing rooms
Conference1/22/20151/23/20151/23/2015ADONE
DetailsRex Boyles
Discuss waterproofing of 4th level in order to expedite wiring rough in on levels 2 and 3. Phone #: ###-#### Inspection requested via web by Rafael Castillo ok to install nm cable in areas that are going to be waterproofed by McAlvain
Conference1/21/20151/21/20151/21/2015ADONE
DetailsRex Boyles
Discuss panel clearances in units. Phone #: ###-#### Inspection requested via web by Rafael Castillo discuss hvac above loadcenters in each unit. Lea requesting to install nm cable now without roof done.