Final | 10/31/2016 | 10/31/2016 | 10/31/2016 | A | PASS |
Eric Story
|
|
|
Final. Contact is Mark Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Floors 2@3 Final ok, signed sign off sheet
|
Final | 8/4/2016 | 8/4/2016 | 8/4/2016 | P | PART |
Rock A. Hudson
|
|
|
###-#### TCO BSU floors 2 and 3 Temp final ok
|
Electrical Rough-In | 8/4/2016 | 8/4/2016 | 8/4/2016 | A | NR |
Rock A. Hudson
|
|
|
TCO for floors 2 and 3. BSU stairway has lighting installed. Contact is Eric Gibson ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves 3rd floor server room door needs to be lockable, install panel in door and locks. Complete center stair lighting and blank off all boxes. Room 368 still has connection issues, wrong whip.
|
Electrical Rough-In | 8/1/2016 | 8/2/2016 | 8/2/2016 | A | PART |
Rock A. Hudson
|
|
|
TCO inspection. Contact is Toby Groves ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Floor 2- complete central stair lighting. Framing at main floor entrance, sconce omitted, flourescent under landings not installed may be omitted. Covers missing for card readers on several walls. Cover gutter i electrical room. 3rd floor- Server room fire suppression, HVAC, rack yet to complete. Door shall be lockable and missing window. Card reader boxes at several locations not covered. Room 368 conference table power supply not compatible with floor box provided. location different. Armored cable whip provided and receptacle installed in floor.
|
Electrical Rough-In | 7/28/2016 | 7/29/2016 | 7/29/2016 | A | CANC |
Rock A. Hudson
|
|
|
Inspect wall trim out on 2nd and 3rd floor. Inspect for remaining items needed for a TCO for this TI space. Contact is Toby Groves ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves Prewalk floors 2 and 3 ok for furniture. Thank you. Check corridor and stair lighting on both floors, remove flexible cord for temp power on 2, open boxes server rm, elec rm, 341, switch cover 342, west patio can trims, 3rd conference rm circiut inop, 368 furniture whip.
|
Electrical Rough-In | 7/28/2016 | 7/28/2016 | 7/28/2016 | P | PASS |
Rock A. Hudson
|
|
|
Ceiling inspection 2nd and 3rd floor. Contact is Toby Groves ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Grid complete floors 2 and 3 rough in ok cover
|
Electrical Rough-In | 7/27/2016 | 7/27/2016 | 7/27/2016 | P | PART |
Rock A. Hudson
|
|
|
Ceiling cover inspection where available. Contact is Toby Groves ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves Grid as noted on contractor print for levels 2 and 3 rough in ok cover. areas not ready are 353, 358, 363, 221 240, 241, 242, 243, open area north side fixture whip.
|
Electrical Rough-In | 7/22/2016 | 7/22/2016 | 7/22/2016 | P | PART |
Rock A. Hudson
|
|
|
Grid ceiling cover inspection floors 2 and 3.Not all rooms are ready, but would like to get as many as we can inspected.Contact is Eric Gibson ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves Grid 2nd floor 245 thru 251, 254 thru 258. Boarder as noted on contractor print only. Grid 3rd floor open offices 325, 326, rms 340, 350, 354, 355, 356, 358, 360, 366, 367. Boarders as noted on contractor print rms 351, 352, 363, 368. Areas noted rough in ok cover
|
Electrical Rough-In | 5/26/2016 | 5/26/2016 | 5/26/2016 | P | PASS |
Rock A. Hudson
|
|
|
BSU TI stairway. 3rd floor ceiling for cover. Contact is Eric Gibson 871 -1363 Phone #: ###-#### Inspection requested via web by Toby Groves discussed door location in 2nd floor electrical room. With 45" width to get to door Chief Electrical inspector ruled unobstructed egress to door was sufficient. Grid 3rd floor stairway rough in ok cover. Book not at desk to mark as inspected.
|
Electrical Rough-In | 5/25/2016 | 5/25/2016 | 5/25/2016 | P | PASS |
Rock A. Hudson
|
|
|
3rd floor wall rough in for cover BSU T.I. Contact is Eric Gibson ###-####. Phone #: ###-#### Inspection requested via web by Toby Groves Perimeter walls accept wall to stair platform not present. Rough in ok cover
|
Electrical Rough-In | 4/15/2016 | 4/15/2016 | 4/15/2016 | P | PASS |
Rex Boyles
|
|
|
2nd and 3rd floor wall inspection. Contact is ERIC Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves r/i ok 3rd floor walls see blue area on plans
|
Electrical Rough-In | 4/13/2016 | 4/13/2016 | 4/13/2016 | P | PASS |
Rex Boyles
|
|
|
Can light inspection for cover in bathroom. Eric Gibson is the Contact ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves r/i ok BSU co ed bath ceiling on 2nd flr
|
Electrical Rough-In | 4/8/2016 | 4/8/2016 | 4/8/2016 | P | PASS |
Rex Boyles
|
|
|
Can lights in ceiling cover inspection. Contact is Eric Gibson ###-#### Phone #: ###-#### Inspection requested via web by Toby Groves r/i vending machine rm. ceiling can lights ok
|
Electrical Rough-In | 4/5/2016 | 4/5/2016 | 4/5/2016 | P | PASS |
Rock A. Hudson
|
|
|
Wall cover inspection 3rd floor Phone #: ###-#### Inspection requested via web by Toby Groves Walls marked in green only rough in ok cover
|
Electrical Rough-In | 4/1/2016 | 4/1/2016 | 4/1/2016 | P | PASS |
Daryl DeGrange
|
|
|
Cover inspections for walls Phone #: ###-#### Inspection requested via web by Toby Groves Rough-in ok cover interior walls highlighted green and dated
|
Conference | 3/9/2016 | 3/9/2016 | 3/9/2016 | A | DONE |
Rex Boyles
|
|
|
Need to verify working clearances for HVAC control boxes above ceilings. Phone #: ###-#### Inspection requested via web by Toby Groves 110.26(A)(1)- Working space for equipment operating at 600 volts or less to ground and likely to require examination, adjustment,service or maintenance while energized shall comply with the deminsions 0f 110.26(A)(1),(A)(2) and (A)(3)
|
Electrical Rough-In | 3/9/2016 | 3/9/2016 | 3/9/2016 | P | PASS |
Rex Boyles
|
|
|
Need to verify working clearances for HVAC control boxes above ceilings. Phone #: ###-#### Inspection requested via web by Toby Groves r/i ok exterior walls on stairwell 3 between parking structure and city center bldg. level 1 thru 4.
|
Electrical Rough-In | 3/2/2016 | 3/2/2016 | 3/2/2016 | P | PASS |
Rex Boyles
|
|
|
Rough in cover inspection. Catch up on inspection binder Phone #: ###-#### Inspection requested via web by Toby Groves Just update ESI binder no r/i insp.
|
Electrical Rough-In | 2/25/2016 | 2/25/2016 | 2/25/2016 | A | PASS |
Rex Boyles
|
|
|
Cover inspection 2nd and 3rd floors East side of building. Phone #: ###-#### Inspection requested via web by Toby Groves partial walls ok see Eric"s E1.2.1 and E.1.3.1 sheets for pink areas only.
|
Electrical Rough-In | 2/16/2016 | 2/16/2016 | 2/16/2016 | P | PASS |
Rex Boyles
|
|
|
Exterior wall cover inspection level 3. Phone #: ###-#### Inspection requested via web by Toby Groves 100% r/i ok exterior walls on 3
|
Final | 2/12/2016 | 2/12/2016 | 2/12/2016 | P | CANC |
Rex Boyles
|
|
|
Cover inspection exterior walls. Phone #: ###-#### Inspection requested via web by Toby Groves needed r/i insp
|
Electrical Rough-In | 2/12/2016 | 2/12/2016 | 2/12/2016 | P | PASS |
Rex Boyles
|
|
|
Cover inspection exterior walls. Phone #: ###-#### Inspection requested via web by Toby Groves r/i exterior walls on level 2 ok. r/i exterior walls level 3 east wall only
|