Final | 10/18/2018 | 10/18/2018 | 10/19/2018 | P | PASS |
Eric Story
|
|
|
Backup Generator installed Generac service complete and ready for demonstration of generator function and automatic transfer switching operation Final instalation permit inspection requested. Phone #: ###-#### Inspection requested via web by Carl Pelletier Final ok
|
ELE-Request for Extension | 10/2/2018 | 10/2/2018 | 10/2/2018 | P | DONE |
Eric Story
|
|
|
Request 30 day extension to allow for appointment with Generac service technition for generator install and setup endorsement, Boise City final inspection to be scheduled on a following date. Phone #: ###-#### Inspection requested via web by Carl Pelletier 30 Day extension given for generator start up testing
|
Rough-In Permanent Service | 9/24/2018 | 9/25/2018 | 9/25/2018 | P | PASS |
Eric Story
|
|
|
Idaho Power disconnect appointment 11AM-12PM Tuesday. Request inspection of utility service rough-in for permanent service 12PM-3PM. Idaho Power to re-connect service same day. Phone #: ###-#### Inspection requested via web by Carl Pelletier p/s o/h rec ok
|
ELE-Request for Extension | 9/5/2018 | 9/6/2018 | 9/6/2018 | P | PASS |
James Ady
|
|
|
Request for 30 day extension to coordinate service connection, Generac technician appointment to establish settings, and final inspection Phone #: ###-#### Inspection requested via web by Carl Pelletier Request for extension ok
|
Conference | 8/28/2018 | 8/29/2018 | 8/29/2018 | P | PASS |
Eric Story
|
|
|
Rock Hudson, Questions about a standby generator with not separately derived system connection to integrated utility service panel. Carl Phone #: ###-#### Inspection requested via web by Carl Pelletier Discussed termination points for generator hook up in Idaho Powers side
|
ELE-Request for Extension | 3/13/2018 | 3/13/2018 | 3/13/2018 | P | PASS |
Eric Story
|
|
|
My original permit expiration is coming up on 3/17/18, my most recent inspection was 2/12/18 and I am making progress on completion of this permit, I would like to request an extension of time on this permit, and confirm that acceptance. Phone #: ###-#### Inspection requested via web by Carl Pelletier 180 day extension given
|
Electrical Rough-In | 2/9/2018 | 2/12/2018 | 2/12/2018 | P | PASS |
Eric Story
|
|
|
Review underground prep work from generator to house for "stand by generator installation", trenching ; electrical conduit rough-in work, Sch.80 required where emerge from grade. Discussed generator location shall have a min of depth of 36" for work space at generator disconnect. Phone #: ###-#### Inspection requested via web by Carl Pelletier Remaining U/G for generator ok to cover
|
Conference | 10/7/2017 | 10/9/2017 | 10/9/2017 | P | DONE |
Rock A. Hudson
|
|
|
Introduction and review underground prep work for stand by generator instalation, trenching ; electrical conduit rough-in work Phone #: ###-#### Inspection requested via web by Carl Pelletier Discussed generator location shall have a min of depth of 36" for work space at generator disconnect. Sch.80 required where emerge from grade, grounding electrode system for each service all that needed, equipment grounds to generator each with common neutral blocks. Main disconnect for shop to remain inside and house to remain outside. Check for removal of main bonding jumper at generator in future. Will call for underground to house when ready.
|
Electrical Rough-In | 10/9/2017 | 10/9/2017 | 10/9/2017 | P | PASS |
Rock A. Hudson
|
|
|
Introduction and review underground prep work for stand by generator instalation, trenching ; electrical conduit rough-in work Phone #: ###-#### Inspection requested via web by Carl Pelletier Partial underground from generator to shop and corner of shop headed to house rough in ok cover
|