Information based on query as of Tuesday, July 16, 2024.
Permit Information
Permit NumberELE18-02286
StatusFinaled
Name NEW LEAF ELECTRIC AND GEN
Site Address 10853 W ALLIANCE ST
Project Name 
Customer Number 
ePlanReviewNo
Description
Alteration or Repair: Replace main breaker panel
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final8/5/20188/6/20188/6/2018APASS
DetailsTom Saunders
I completed this work on Friday afternoon, bonding the bushing inside the breaker panel, and installing the intersystem bonding termination. I can text pictures, or I can meet there to open the panel, just let me know in plenty of time to get there (I expect to be at the base of Bogus Basin Rd.) Let me know what you''d like and I will accomodate. Thanks ~ Dan Phone #: ###-#### Inspection requested via web by Dan Hilke...
corrections made...ok to final
Final8/1/20188/2/20188/2/2018AFAIL
DetailsRock A. Hudson
Just call before you get there and I''ll meet you so I can remove the panel cover for you. Phone #: ###-#### Inspection requested via web by Dan Hilke 250.92- Metal nipple entering thru concentric KO from meter shall have a bonding bushing bonding complete. Bonding bushing installed, no lug on bonding bushing.
250.94- Bonding strap installed on service lateral riser, informed a llisted intersystem bond bar shall be installed.
2 ground rods installed on fence line, rest of corrections ok.
Permanent Service8/2/20188/2/20188/2/2018PPASS
DetailsRock A. Hudson
Just call before you get there and I''ll meet you so I can remove the panel cover for you. Phone #: ###-#### Inspection requested via web by Dan Hilke p/s u/g rec ok
Final7/31/20187/31/20187/31/2018PNR
DetailsTom Saunders
This is for changing out an old panel. It''s in back corner of the garage. I live nearby, please call when you''re on your way and I should be able to meet you there. Thanks ~ Dan Phone #: ###-#### Inspection requested via web by Dan Hilke...
ID Power turned power on before perm service inspection scheduled...job completed past 5 pm...temped in service to get power back on...few additional requirements need done before can final
multiple branch circuits in panel need to be on 2 pole breaker
grounding needs brought up to code-2 rods
intersysytem bond needs installed
platform will be installed to satisfy highest breaker highth code requirement
romex under panel needs fixed to code with outside outlet as well...romex protected from physical damage and exterior outlet needs GFI protection, W/R outlet and inuse H/D cover