Information based on query as of Wednesday, June 26, 2024.
Permit Information
Permit NumberELE18-03476
StatusFinaled
Name QUALITY ELECTRIC INC
Site Address 711 N CURTIS RD
Project Name 
Customer Number18048
ePlanReviewNo
Description
New: Furnish and install electrical package for new hospital, include power, lighting, fire alarm, comm / data and access control, per approved plans.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final8/1/20198/2/20198/2/2019APASS
DetailsTom Saunders
Zack Phone #: ###-####...
complete...ok to final
card signed
Electrical Rough-In7/22/20197/23/20197/23/2019APASS
DetailsTom Saunders
Zach Phone #: ###-####...heat tap exterior building...ok to cover
Final7/19/20197/19/20197/19/2019PPART
DetailsTom Saunders
Zach Phone #: ###-####...
TCO of building interior ok
remaining work outside...heat trace circuit and material install-requiring inspections
sign wall missing 1 light
Final7/17/20197/17/20197/17/2019PPART
DetailsTom Saunders
Zack- interior inspection Phone #: ###-####... interior complete, roof top complete...exterior perimeter of building and oxygen room remaining for complete final
Electrical Rough-In7/16/20197/17/20197/17/2019PPASS
DetailsTom Saunders
Zack- inspection Electrical, Dat, and roof Phone #: ###-####....areas stated above inspected for completion
Final7/15/20197/16/20197/16/2019PFAIL
DetailsTom Saunders
Zack- Area 4 Phone #: ###-####...
area not complete...practice kitchen not complete
Final7/10/20197/11/20197/11/2019PNR
DetailsTom Saunders
column line 16 to 11 (therapy gym and kitchen) // Zach Phone #: ###-####...changed to rough inspection to keep permit open
Electrical Rough-In7/11/20197/11/20197/11/2019PPASS
DetailsTom Saunders
column line 16 to 11 (therapy gym and kitchen) // Zach Phone #: ###-####...areas marked as complete for occupency...missing GFCIs verified next inspection
Final7/9/20197/10/20197/10/2019PNR
DetailsTom Saunders
Zack- inspection for admond area Phone #: ###-####...
areas checked off in rough inspection...see notes
Electrical Rough-In7/10/20197/10/20197/10/2019PPASS
DetailsTom Saunders
Zack- inspection for admond area Phone #: ###-####...areas approved as finaled...Admin up to line 16 ok to occupy
Electrical Rough-In7/1/20197/2/20197/2/2019APASS
DetailsTom Saunders
Zack Phone #: ###-####...
Area C and D patient rms. nurses station complete
Final6/27/20196/28/20196/28/2019ACANC
DetailsTom Saunders
area A and B - Zack Phone #: ###-####..
see rough in notes...verified areas
Electrical Rough-In6/28/20196/28/20196/28/2019APASS
DetailsTom Saunders
area A and B - Zack Phone #: ###-####...
patient rms, hallway, and pharmacy verified ok
Electrical Rough-In6/13/20196/14/20196/14/2019PPASS
DetailsTom Saunders
Zack Phone #: ###-####...
grid complete...ok to final
Electrical Rough-In6/6/20196/7/20196/7/2019PPASS
DetailsTom Saunders
Zack Phone #: ###-####....
Area3 grid ok line 16 up to 11
Electrical Rough-In5/31/20196/3/20196/3/2019APASS
DetailsTom Saunders
above ceiling - Zach Phone #: ###-####...
Area 3 up to line 16 grid ok to cover
Electrical Rough-In5/13/20195/14/20195/14/2019APASS
DetailsEric Story
above ceiling // Zach Phone #: ###-####
Ceilings as noted on print ok to cover
Electrical Rough-In4/29/20194/29/20194/29/2019PPASS
DetailsTom Saunders
Zack Phone #: ###-####...
area4 walls...walls complete
Rough-In Permanent Service4/17/20194/18/20194/18/2019APASS
DetailsTom Saunders
Zack Phone #: ###-####...
area 1 ceilings and area 3 bath hardlids
Temporary Service4/10/20194/11/20194/11/2019PCANC
DetailsTom Saunders
main switch gear // Zach Phone #: ###-####
wrong inspection
Permanent Service4/11/20194/11/20194/11/2019PPASS
DetailsTom Saunders
main switch gear // Zach Phone #: ###-####
ok to switch meter to main switch gear to power temp power skid...another rough inspection is required to power future panels and transformers
meter at transformer now...ok
Electrical Rough-In4/9/20194/10/20194/10/2019APASS
DetailsTom Saunders
Zack Phone #: ###-####...
Area 1 patient rm grid and hallway perimeter tiles
discussed small perimeter no full tiles
Electrical Rough-In4/4/20194/5/20194/5/2019APASS
DetailsEric Story
Zach Phone #: ###-####
Lobby and entry hard lids and walls as noted on print ok to cover
Electrical Rough-In4/2/20194/3/20194/3/2019APASS
DetailsTom Saunders
Zack Phone #: ###-####...
hard lid area 2
Electrical Rough-In3/11/20193/12/20193/12/2019APASS
DetailsTom Saunders
Zach Phone #: ###-####...
walls section E and partial G...marked plans
Electrical Rough-In3/8/20193/11/20193/11/2019APASS
DetailsTom Saunders
Zack Phone #: ###-####...
Area E admin...as marked on plans
Electrical Rough-In3/5/20193/6/20193/6/2019APASS
DetailsTom Saunders
Zack Phone #: ###-####...
Area A hard lids bathroom, ambulance canopy, and entry ok to cover
Electrical Rough-In2/28/20193/1/20193/1/2019APASS
DetailsEric Story
Zack Phone #: ###-####
Walls as noted on print ok to cover
Electrical Rough-In2/19/20192/20/20192/20/2019APASS
DetailsTom Saunders
Zach...###-####...
wall cover area C marked on plans
minus pony walls nurses station
Electrical Rough-In2/19/20192/19/20192/19/2019PCANC
DetailsTom Saunders
Zack Phone #: ###-####...
oked by contractor to reschedule to next day AM
Electrical Rough-In1/24/20191/25/20191/25/2019APASS
DetailsTom Saunders
Zack Phone #: ###-####...
walls ok to cover...area B as marked on plans
Electrical Rough-In1/10/20191/11/20191/11/2019APASS
DetailsTom Saunders
Zach Phone #: ###-####...
10 rms as marked on plans
Temporary Service1/2/20191/2/20191/2/2019PCANC
DetailsTom Saunders
Zach Phone #: ###-#### Inspection cancelled from web by: Scott Campbell
Electrical Rough-In11/6/201811/7/201811/7/2018APASS
DetailsTom Saunders
Zach Phone #: ###-####...
underground for main electrical rm
discussed city stamped plans on job and wiring to engineers specs...1 change they requesting is use of #10 stranded instead of solid -requirement in notes-will get engineer sign off
Electrical Rough-In10/24/201810/25/201810/25/2018APASS
DetailsTom Saunders
Underground/cover - Zach Phone #: ###-####...utillity feeds into electrical rm ok to cover
Electrical Rough-In10/11/201810/12/201810/12/2018APASS
DetailsTom Saunders
underground // Zack Phone #: ###-####...ok to cover...East end-zone A section 1
Electrical Rough-In10/4/201810/5/201810/5/2018APASS
DetailsRock A. Hudson
Zack-underground Phone #: ###-####
Service entrance conduits modified offsets around drainage to gradual sweeps and a direct line to west electrical room.
Service entrance underground thru court yard rough in ok cover
Electrical Rough-In9/27/20189/28/20189/28/2018APASS
DetailsRock A. Hudson
underground // Zack Phone #: ###-####
Discussed issue of more than 360 degrees of bends in underground feeds for east main electrical room. 1 turning up in east electrical room, 1 turning west mid point, than noticed trench has 2 offsets around drainage. At this point a total of 360 degrees will be in conduit run. Zack has presented issue to general contractor and waiting for responce.
East electrical room underground rough in ok cover.
Electrical Rough-In9/24/20189/25/20189/25/2018PPASS
DetailsJames Ady
underground- Zach Phone #: ###-#### SE corner bus duct ok to cover
Conference9/14/20189/17/20189/17/2018APASS
DetailsRock A. Hudson
Zack Phone #: ###-####
Contact wanted to touch base with inspector to discuss code changes that may affect rehab hospital. Informed of conference rooms, commercial kitchens GFCI protection, type of receptacles for waiting rooms, corridors ect. Duct bank being installed with listed ladder system. OK to back fill areas needed for traffic areas.