Information based on query as of Tuesday, July 23, 2024.
Permit Information
Permit NumberELE18-03966
StatusFinaled
Name KC ENTERPRISES
Site Address 2604 W PLEASANTON AVE
Project Name 
Customer Number 
ePlanReviewNo
Description
Alteration or Repair: Remove existing service riser and meter, install new meter at correct height, extend new service riser conduit and service conductors so they will be 8'' above new patio cover. Connect new meter to the existing main panel.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final12/20/201812/21/201812/20/2018APASS
DetailsMark Moncarr
Job is ready for final inspection. Panel schedule is complete on new panel and reworked for existing house panel. Phone #: ###-#### Inspection requested via web by Kurt Carlson Ok final. Looked at on 10/22. This is to close out permit.
Permanent Service10/22/201810/23/201810/23/2018APASS
DetailsMark Moncarr
Service was relocated to shop, feeder was then routed underground to the existing house panel. Idaho Power would not allow service on house, due to clearance and non accessibility issues. Existing house panel was turned into a 4 wire sub panel. Existing neutral and grounds were separated and isolated at existing panel. New ground rods installed at new service panel at shop. Main bonding done at new service. I will be on site earlier in the morning and can meet you there if needed. Phone #: ###-#### Inspection requested via web by Kurt Carlson Drop to new service location on detached shop. p/s o/h rec ok
Permanent Service10/17/201810/17/201810/17/2018PCANC
DetailsMark Moncarr
Idaho power will be on site at 10;30 to shut down, work should be done by 2:00 ready for inspection, Idaho power will turn back on after inspection. Phone #: ###-#### >> Inspection requested via web by Kurt Carlson Inspection cancelled from web by: Kurt Carlson