Information based on query as of Friday, August 16, 2024.
Permit Information
Permit NumberELE19-00747
StatusFinaled
Name PACIFIC SOURCE ELECTRIC LLC
Site Address 2717 S VISTA AVE
Project Name 
Customer Number19BOI-100
ePlanReviewNo
Description
Alteration or Repair: Electrical improvements to each unit
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final8/29/20198/30/20198/30/2019APASS
DetailsTom Saunders
Nick will be on site for unit access. Final inspection for Units 135, 136, 233, 234, 235 and 236. This will complete this final phase of work. No further inspections needed after passing inspection. Phone #: ###-#### Inspection requested via web by Tod Lane...
last 6 units...job complete...ok to final
Final8/10/20198/12/20198/12/2019APASS
DetailsEric Story
Re-inspection of Units 220, 221, 222, 223, 229 and 230 for partial final on these units. Phone #: ###-#### Inspection requested via web by Tod Lane
corrections fixed final ok
Final8/8/20198/9/20198/9/2019AFAIL
DetailsEric Story
Units 220, 221, 222, 223, 229 and 230 ready for final inspection. Nick prieto will be on site for access or questions. Phone #: ###-#### Inspection requested via web by Tod Lane
Unit 221 not accessible
Other units have exposed romex to Ptak units or no abrasion control on other side of flex
Final7/30/20197/31/20197/31/2019APART
DetailsEric Story
Electrical final on Units 120, 121, 122 and 123.
Justin Carbonaro will be on site for access issues. Phone #: ###-#### Inspection requested via web by Tod Lane

Units as requested ok
Electrical Rough-In6/26/20196/27/20196/27/2019APASS
DetailsEric Story
Electrical rough-in inspection on Units 135, 136, 233, 234, 235 and 236. This will be the last set of rough-in inspections for this phase. Phone #: ###-#### Inspection requested via web by Tod Lane
Units as requested ok to cover
Electrical Rough-In6/17/20196/18/20196/18/2019PPASS
DetailsEric Story
Electrical rough-in inspection on Units 220, 221, 222, 223, 229, 230. David Forbes will be on site for questions and access. Phone #: ###-#### Inspection requested via web by Tod Lane
Units as requested ok to cover
Electrical Rough-In6/10/20196/11/20196/11/2019PPASS
DetailsEric Story
Electrical rough in on Units 120, 121, 122 and 123. David Forbes will be on site for access. Phone #: ###-#### Inspection requested via web by Tod Lane
Units as requested ok to cover
Final5/29/20195/30/20195/30/2019APASS
DetailsEric Story
Final on last 3 units for this phase. Units 127, 129, 225. Justin will be available on site for access to units. Phone #: ###-#### Inspection requested via web by Tod Lane
Final for phase ok
Final5/24/20195/24/20195/24/2019PPART
DetailsJames Ady
Reinspection of Unit 137 for missing 2gang plate. Phone #: ###-#### Inspection requested via web by Tod Lane Correction made 137 final ok
Final5/22/20195/24/20195/24/2019APART
DetailsJames Ady
Final inspection on Units 137, 139, 238, 239. Phone #: ###-#### Inspection requested via web by Tod Lane 314.25. All boxes shall have cover plates. (137 missing 2gang cover in Shower room.) 139,238,239 Final ok
Final5/13/20195/14/20195/14/2019APART
DetailsEric Story
Trim inspection on Units 203, 206, 207, 208 and 209. Phone #: ###-#### Inspection requested via web by Tod Lane
Units as requested ok
Final4/29/20194/30/20194/30/2019PPART
DetailsEric Story
Final inspection on Units 105, 107, 108 and 109. Nick Prieto is on site for questions and access. Phone #: ###-#### Inspection requested via web by Tod Lane
Units as requested partial final ok
Electrical Rough-In4/8/20194/9/20194/9/2019APASS
DetailsEric Story
Electrical rough-in on Units 127, 129 and 225. Call Nick Prieto for questions. Phone #: ###-#### Inspection requested via web by Tod Lane
Units as requested ok to cover
Electrical Rough-In4/1/20194/2/20194/2/2019APASS
DetailsEric Story
Electrical rough in inspection on Units 137, 139, 238 and 239. Phone Nick Prieto for questions and access. Phone #: ###-#### Inspection requested via web by Tod Lane
Units as requested ok to cover
Electrical Rough-In3/20/20193/22/20193/22/2019APASS
DetailsEric Story
Rough-in inspection on Units 203, 206, 207, 208, 209. Call Nick Prieto for questions. Phone #: ###-#### Inspection requested via web by Tod Lane
Units as requested ok to cover
Electrical Rough-In3/14/20193/14/20193/14/2019PPASS
DetailsEric Story
Re-inspect Units 105, 107, 108, 109. Phone #: ###-#### Inspection requested via web by Tod Lane
Units as requested ok to cover
Electrical Rough-In3/13/20193/14/20193/14/2019AFAIL
DetailsEric Story
Rough in inspection of Units 105, 107, 108 and 109. Nick Prieto will be on site for questions. Phone #: ###-#### Inspection requested via web by Tod Lane
Type NM cable shall not be installed where subject to physical damage. 1 1/4 from framing member required