Final | 7/28/2020 | 7/28/2020 | 7/28/2020 | P | PASS |
Mark Moncarr
|
|
|
Final* Phone #: ###-#### Inspection requested via web by Kevin Burke Ok final. Asked contractor to check all ranges that GE installed. Bonding straps needed to be removed. Contractor confirmed that all straps were removed
|
Electrical Rough-In | 7/23/2020 | 7/23/2020 | 7/23/2020 | P | PASS |
Mark Moncarr
|
|
|
Font entry ground work Late afternoon Phone #: ###-#### Inspection requested via web by Kevin Burke Ok cover conduit for flag pole lighting,
|
Final | 7/21/2020 | 7/21/2020 | 7/21/2020 | P | PART |
Mark Moncarr
|
|
|
4th floor units Phone #: ###-#### Inspection requested via web by Kevin Burke Partial for TCO on building. Waiting for parking lot and ground lights to be completed.
|
Final | 7/14/2020 | 7/14/2020 | 7/14/2020 | P | PART |
Mark Moncarr
|
|
|
3rd floor Phone #: ###-#### Inspection requested via web by Kevin Burke Third floor partial. Noticed pigtails for ranges done incorrectly. Kevin said he would go through and check them. If they are not done properly, I will have the appliance company come back and re-do all and make accessible so they can be seen.
|
Electrical Rough-In | 7/8/2020 | 7/8/2020 | 7/8/2020 | A | PASS |
Mark Moncarr
|
|
|
Light pole bases Phone #: ###-#### Inspection requested via web by Kevin Burke Ok cover 4 light pole bases
|
Final | 7/2/2020 | 7/2/2020 | 7/2/2020 | P | PART |
Mark Moncarr
|
|
|
2nd floor. Phone #: ###-#### Inspection requested via web by Kevin Burke Partial for 2nd floor rooms and classroom
|
Final | 7/1/2020 | 7/1/2020 | 7/1/2020 | P | PART |
Mark Moncarr
|
|
|
“Final” 1st floor Phone #: ###-#### Inspection requested via web by Kevin Burke Ok final whole 1st floor
|
Electrical Rough-In | 6/19/2020 | 6/19/2020 | 6/19/2020 | P | PASS |
Eric Story
|
|
|
4th floor ceiling Phone #: ###-#### Inspection requested via web by Kevin Burke 4th floor corridor ok to cover
|
Electrical Rough-In | 6/17/2020 | 6/17/2020 | 6/17/2020 | P | PASS |
Eric Story
|
|
|
3rd floor grid ceiling Phone #: ###-#### Inspection requested via web by Kevin Burke 3rd floor ceiling ok to cover
|
Electrical Rough-In | 6/11/2020 | 6/11/2020 | 6/11/2020 | P | PASS |
Eric Story
|
|
|
2nd floor corridor grid ceiling Phone #: ###-#### Inspection requested via web by Kevin Burke 2nd floor corridor suspended ceiling ok to cover
|
Electrical Rough-In | 5/29/2020 | 5/29/2020 | 5/29/2020 | P | PASS |
Mark Moncarr
|
|
|
1st floor corridor Ceiling grid Phone #: ###-#### Inspection requested via web by Kevin Burke Ok cover 1st floor corridor ceiling
|
Electrical Rough-In | 5/21/2020 | 5/21/2020 | 5/21/2020 | P | PASS |
Mark Moncarr
|
|
|
Hard lid ceiling in front of elevator. Phone #: ###-#### Inspection requested via web by Kevin Burke Ok cover hardlid 1st floor N side
|
Electrical Rough-In | 5/19/2020 | 5/19/2020 | 5/19/2020 | P | PASS |
Mark Moncarr
|
|
|
Underground, communication conduits Phone #: ###-#### Inspection requested via web by Kevin Burke Ok cover ground work
|
Electrical Rough-In | 5/1/2020 | 5/1/2020 | 5/1/2020 | P | PASS |
Mark Moncarr
|
|
|
4th floor hallway light and bathroom light/fan Phone #: ###-#### Inspection requested via web by Kevin Burke Ok cover drops in areas listed.
|
Electrical Rough-In | 4/20/2020 | 4/21/2020 | 4/21/2020 | A | PASS |
Eric Story
|
|
|
1st ; 2nd floor bathroom light and fan Phone #: ###-#### Inspection requested via web by Kevin Burke Areas as requested ok to cover
|
Electrical Rough-In | 4/20/2020 | 4/20/2020 | 4/21/2020 | P | PASS |
Mark Moncarr
|
|
|
3rd floor unit hallway lights Phone #: ###-#### Inspection requested via web by Kevin Burke Ok cover areas listed. Received pics from contractor due to Corona-19.
|
Electrical Rough-In | 4/15/2020 | 4/16/2020 | 4/16/2020 | A | PASS |
Mark Moncarr
|
|
|
Elevator pit/closet inspection Phone #: ###-#### Inspection requested via web by Kevin Burke Ok cover elevator pit and closet.
|
Electrical Rough-In | 4/8/2020 | 4/8/2020 | 4/8/2020 | P | PASS |
Mark Moncarr
|
|
|
1st ; 2nd floor units hallway soffits. Phone #: ###-#### Inspection requested via web by Kevin Burke Ok cover hallway lights in 1st and 2nd floor due to fur down for HVAC.
|
Permanent Service | 3/11/2020 | 3/11/2020 | 3/11/2020 | P | PASS |
Eric Story
|
|
|
AFC calc given is L-L-L 3909 Main is rated at 65K 2 MAins for house panels are 10K
|
Permanent Service | 3/6/2020 | 3/9/2020 | 3/9/2020 | A | PASS |
Eric Story
|
|
|
Phone #: ###-#### Inspection requested via web by Kevin Burke AFC calc required p/s u/g n ok
|
Permanent Service | 3/6/2020 | 3/6/2020 | 3/6/2020 | A | CANC |
Mark Moncarr
|
|
|
Phone #: ###-#### Inspection requested via web by Kevin Burke Waiting on parts for service.
|
Electrical Rough-In | 3/4/2020 | 3/4/2020 | 3/4/2020 | A | PASS |
Mark Moncarr
|
|
|
1st, 3rd, ; 4th floor community areas. Phone #: ###-#### Inspection requested via web by Kevin Burke Ok cover areas listed.
|
Electrical Rough-In | 2/26/2020 | 2/27/2020 | 2/27/2020 | A | PASS |
Mark Moncarr
|
|
|
4th floor units. Phone #: ###-#### Inspection requested via web by Kevin Burke Ok cover 4th floor.
|
Electrical Rough-In | 2/24/2020 | 2/24/2020 | 2/24/2020 | A | PASS |
Mark Moncarr
|
|
|
1st ; 2nd floor corridor walls. Phone #: ###-#### Inspection requested via web by Kevin Burke Ok cover areas listed.
|
Electrical Rough-In | 2/14/2020 | 2/14/2020 | 2/14/2020 | P | PASS |
Mark Moncarr
|
|
|
3rd floor units ; 1st floor south maintenance closet. Phone #: ###-#### Inspection requested via web by Kevin Burke Ok cover 3rd floor.
|
Electrical Rough-In | 2/13/2020 | 2/14/2020 | 2/14/2020 | A | CANC |
Mark Moncarr
|
|
|
3rd floor units, 1st floor south Mechanical room Phone #: ###-#### >> Inspection requested via web by Kevin Burke Inspection cancelled from web by: Kevin Burke
|
Conference | 2/5/2020 | 2/5/2020 | 2/5/2020 | P | DONE |
Mark Moncarr
|
|
|
Conference Phone #: ###-#### Inspection requested via web by Kevin Burke Discussed not having recept in hallway that is under 10' in length, and recept within peninsula footprint covers all of the peninsula even if a sink or something similar is in place. 24" requirement is not used.
|
Electrical Rough-In | 2/3/2020 | 2/3/2020 | 2/3/2020 | P | PASS |
Eric Story
|
|
|
1st ; 2nd Units only Phone #: ###-#### Inspection requested via web by Kevin Burke 1st and 2nd floors-units ok to cover
|
Conference | 12/18/2019 | 12/18/2019 | 12/18/2019 | P | DONE |
Mark Moncarr
|
|
|
Low volt panels Phone #: ###-#### Inspection requested via web by Kevin Burke Talked to contractor about Media panel location and clearences. Will have approximately 26". Ok to locate panels in areas requested. Only work that would need to be done would be to replace a 110v recept if needed.
|
Electrical Rough-In | 10/3/2019 | 10/3/2019 | 10/3/2019 | A | PASS |
Mark Moncarr
|
|
|
Under slab ground work. Phone #: ###-#### Inspection requested via web by Kevin Burke Ok cover grd work from center to W side of slab.
|
Electrical Rough-In | 10/2/2019 | 10/2/2019 | 10/3/2019 | P | PASS |
Mark Moncarr
|
|
|
Under slab Phone #: ###-#### Inspection requested via web by Kevin Burke Ok cover grd work on center to E side of slab
|
Electrical Rough-In | 9/12/2019 | 9/13/2019 | 9/13/2019 | A | PASS |
Mark Moncarr
|
|
|
Ground works through stairwell stem wall. Phone #: ###-#### Inspection requested via web by Kevin Burke Ok cover conduit S side of building.
|
Electrical Rough-In | 8/21/2019 | 8/21/2019 | 8/21/2019 | P | PASS |
Mark Moncarr
|
|
|
Ufer in footing to run up stem wall and CMU wall Phone #: ###-#### Inspection requested via web by Kevin Burke Ok cover ufer. 20ft #4 cu
|