Final | 9/26/2019 | 9/26/2019 | 9/26/2019 | P | PASS |
Tom Saunders
|
|
|
Phone #: ###-#### Inspection requested via web by Seth Stears... labelling, disconnect, and OCPD ok
|
Electrical Rough-In | 9/25/2019 | 9/25/2019 | 9/25/2019 | P | PASS |
Tom Saunders
|
|
|
McGuire Phone #: ###-####704... UL lised equipment verified voltage/amperage rating label needed for final breaker installed in panel...no access required for final
|
Final | 9/24/2019 | 9/24/2019 | 9/24/2019 | P | NR |
James Ady
|
|
|
Phone #: ###-#### Inspection requested via web by Seth Stears Solar contractor is no longer involved. Need to pull building permit and adjust ELE to reflect complete solar install.
|
Electrical Rough-In | 9/10/2019 | 9/11/2019 | 9/10/2019 | A | CANC |
Tom Saunders
|
|
|
Phone #: ###-#### >> Inspection requested via web by Seth Stears Inspection cancelled from web by: Seth Stears
|