Final | 12/2/2019 | 12/2/2019 | 12/2/2019 | P | PASS |
James Ady
|
|
|
Jose Phone #: ###-#### Final ok
|
Electrical Rough-In | 11/21/2019 | 11/22/2019 | 11/22/2019 | A | PASS |
James Ady
|
|
|
Jose Phone #: ###-#### Back office area in phase 3 Ceiling only ok to cover
|
Final | 10/31/2019 | 11/1/2019 | 11/1/2019 | A | PART |
Rock A. Hudson
|
|
|
Jose- this is a final for PHASE 2 Phone #: ###-#### Phase 2 TCO ok
|
Electrical Rough-In | 10/30/2019 | 10/30/2019 | 10/30/2019 | P | PASS |
Rock A. Hudson
|
|
|
Jose Phone #: ###-#### Phase 2 grid rough in ok cover
|
Electrical Rough-In | 10/7/2019 | 10/8/2019 | 10/8/2019 | A | PASS |
James Ady
|
|
|
phase 2 // Jose Phone #: ###-#### IT room wall and open office area wals only. OK to replace ceiling tiles
|
Final | 10/1/2019 | 10/2/2019 | 10/2/2019 | A | PART |
Eric Story
|
|
|
Jose- inspection for phase 1 Phone #: ###-#### Phase 1 conference and offices ok to occupy
|
Electrical Rough-In | 9/13/2019 | 9/13/2019 | 9/13/2019 | P | PASS |
James Ady
|
|
|
Jose Phone #: ###-#### Phase "1" only as Designated on site print. Walls and underground for conf. room recep OK to cover
|