Electrical Rough-In | 8/12/2020 | 8/13/2020 | 8/13/2020 | A | PASS |
Rock A. Hudson
|
|
|
6th floor restroom ceilings. Contact Shawn Evins. Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Areas noted as noted on contractor print rough in ok cover.
|
Electrical Rough-In | 8/11/2020 | 8/12/2020 | 8/12/2020 | A | PASS |
Rock A. Hudson
|
|
|
5th Floor bathrooms hard lids and 9th Floor walls. Contact Shawn Evins. Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Level 1 west entries interior and exterior, Level 5 bathroom hard lids, Level 10 core walls as noted on contractor print rough in ok cover.
|
Electrical Rough-In | 8/10/2020 | 8/10/2020 | 8/10/2020 | A | PASS |
Rock A. Hudson
|
|
|
Rough in for cover for the Ceilings in the 4th Floor bathrooms. Contact Shawn Evins. Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Level 4 bathroom hardlid and level 10 rail bonding rough in ok cover
|
Conference | 8/7/2020 | 8/7/2020 | 8/7/2020 | A | PASS |
Rock A. Hudson
|
|
|
Consultation concerning access panels. Contact Shawn Evins. Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Met with General foreman ESI, Andy, Shawn, Daryl D., Rock H. discussed minimum access size in suspended ceiling for equipment above ceiling. As per 110.26(A)(4)- Limited access shall have opening of 22"x22" minimum confirmed by Daryl DeGrange.
|
Electrical Rough-In | 8/5/2020 | 8/6/2020 | 8/6/2020 | A | PASS |
Rock A. Hudson
|
|
|
3rd floor ceiling in the restrooms Contact electrician onsite Shawn Evins. Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Need to verify listing for level 10 pathway lighting. Accesses for junction boxes shall be a minimum of 22"x22" as per 110.26(A)(4). Level 3 bathroom hardlids, west stair wall from level 5 to lower level 9 and level 10 electrical room walls rough in ok cover.
|
Electrical Rough-In | 8/4/2020 | 8/5/2020 | 8/5/2020 | A | CANC |
Rock A. Hudson
|
|
|
3rd floor ceiling in the restrooms Contact electrician onsite Shawn Evins. Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Wanted request for Thursday, will recall when ready.
|
Electrical Rough-In | 7/21/2020 | 7/22/2020 | 7/22/2020 | A | PASS |
Rock A. Hudson
|
|
|
Rough in Inspection for the 8th Floor Walls. Contact electrician Shawn Evins with any questions. Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Level 8 core walls and stair 2 from level 5 down wall rough in ok cover
|
Electrical Rough-In | 7/16/2020 | 7/16/2020 | 7/16/2020 | A | PASS |
Rock A. Hudson
|
|
|
Wall rough in inspection for the 7th Floor. Contact Shawn Evins Thank you. Phone #: ###-#### Inspection requested via web by Cathy Duchek Level 1, 102, 103, 105, 111 and level 7 core walls as noted on contractor print rough in ok cover.
|
Electrical Rough-In | 7/9/2020 | 7/10/2020 | 7/10/2020 | A | PASS |
Rock A. Hudson
|
|
|
Wall rough-in inspection for the 5th floor. Contact Shawn Evins Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Level 5 core walls as noted on contractor print rough in ok cover.
|
Electrical Rough-In | 7/6/2020 | 7/7/2020 | 7/7/2020 | A | PASS |
Rock A. Hudson
|
|
|
Wall rough-in inspection for the 1st floor corridor and the 6th floor. Contact Shawn Evins. Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Level 1 east corridor and storage room and level 6 core walls as noted on contractor print rough in ok cover.
|
Electrical Rough-In | 6/25/2020 | 6/26/2020 | 6/26/2020 | A | PASS |
Rock A. Hudson
|
|
|
4th Floor Wall Rough In Inspection Contact electrician Shawn Evins Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Levels 3 and 4 Core walls rough in ok cover
|
Electrical Rough-In | 6/25/2020 | 6/26/2020 | 6/25/2020 | P | CANC |
Rock A. Hudson
|
|
|
Wall Rough in inspection for the 4th floor. Contact electrician Shawn Evins. Thank you, Phone #: ###-#### >> Inspection requested via web by Cathy Duchek Inspection cancelled from web by: Cathy Duchek
|
Electrical Rough-In | 6/22/2020 | 6/23/2020 | 6/23/2020 | A | PASS |
Rock A. Hudson
|
|
|
Rough In Wall inspection for the 2nd floor. Contact electrician Shawn Evins with any questions. Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Level 2 core walls rough in ok cover
|
Electrical Rough-In | 6/16/2020 | 6/17/2020 | 6/17/2020 | P | PASS |
Rock A. Hudson
|
|
|
Wall rough-in inspection. Contact electrician Shawn Evins. Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek NW, SW corridors, fire riser rm, generator rm, bike rm, managers office, com rm, walls as noted on contractor print rough in ok cover.
|
Conference | 5/26/2020 | 5/27/2020 | 5/27/2020 | A | CANC |
Rock A. Hudson
|
|
|
Rough in inspection for raceways in shaft walls. Contact Shawn Evins. Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Needed a rough in inspection.
|
Electrical Rough-In | 5/27/2020 | 5/27/2020 | 5/27/2020 | P | PASS |
Rock A. Hudson
|
|
|
Rough in inspection for raceways in shaft walls. Contact Shawn Evins. Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek East and West stairway shafts conduits rough in ok cover
|
Electrical Rough-In | 5/11/2020 | 5/11/2020 | 5/11/2020 | P | PASS |
Rock A. Hudson
|
|
|
Rough In Inspection - Parapet on the roof wall inspection on future lighting boxes and raceways. Contact Shawn Evins. Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Parapet walls rough in ok cover
|
Electrical Rough-In | 4/21/2020 | 4/22/2020 | 4/22/2020 | P | PASS |
Rock A. Hudson
|
|
|
Electrical rough-in inspection for the lightning protection ground grounding on the 9th floor. Contact electrician Shawn Evins with any questions. Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Listing on compnents confirmed. Rough in ok cover.
|
Electrical Rough-In | 3/26/2020 | 3/27/2020 | 3/27/2020 | P | PASS |
Rock A. Hudson
|
|
|
Rough-In inspection 1st floor walls on the west end. Contact Shawn Evins. Thank you Phone #: ###-#### Inspection requested via web by Cathy Duchek Discussed 1 siding and cover pior to inspection, any cover in anyway prior to an electrical inspection will be required to be removed completely until the same has been inspected as per Boise city ordinance 4-05-23. Will verify a city appoved set of prints on site next inspection. As noted on contractor print. Level 1 top-out 4' only and electrical rooms only rough in ok cover.
|
Electrical Rough-In | 1/22/2020 | 1/23/2020 | 1/23/2020 | P | PASS |
Rock A. Hudson
|
|
|
Underground Rough-In Inspection. Contact Shawn Evins. Thank you. Phone #: ###-#### Inspection requested via web by Cathy Duchek Level 1 east floor boxes and under slab rough in ok cover.
|
Electrical Rough-In | 1/7/2020 | 1/7/2020 | 1/7/2020 | P | PASS |
Rock A. Hudson
|
|
|
Underground Inspection Contact electrician on-site Shawn Evins Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Emergency underground conduits for fire pump, automatic transfer switches, connections to grounding electrode system as noted on contractor print rough in ok cover.
|
Electrical Rough-In | 12/26/2019 | 12/26/2019 | 12/26/2019 | P | PASS |
Rock A. Hudson
|
|
|
Electrical underground rough-in inspection. Phone #: ###-#### Inspection requested via web by Cathy Duchek As noted on contractor print in office level 1 south branch circuit underground conduits rough in ok cover.
|
Electrical Rough-In | 12/20/2019 | 12/20/2019 | 12/20/2019 | P | PASS |
Rock A. Hudson
|
|
|
Underground Inspection. Contact Shawn Evins. Thank you Phone #: ###-#### Inspection requested via web by Cathy Duchek Fire pump service entrance and 2nd level under electrical room rough in ok cover
|
Electrical Rough-In | 12/16/2019 | 12/17/2019 | 12/17/2019 | A | PASS |
Rock A. Hudson
|
|
|
Underground Inspection. Contact electrician on-site Shawn Evins. Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek General asked to note print when rough in complete. Electrical room underground service entrance and comm conduits rough in ok cover.
|
Electrical Rough-In | 10/30/2019 | 10/30/2019 | 10/30/2019 | A | PASS |
Rock A. Hudson
|
|
|
Rough-in inspection for lightning ground loop along north side of building. Phone #: ###-#### Inspection requested via web by Cathy Duchek Temp power supply to 50 amp twist locks shall have GFCI protection as per 590.6(B). Lightning loop complete. Rough in ok cover.
|
Electrical Rough-In | 10/23/2019 | 10/23/2019 | 10/23/2019 | P | PASS |
Rock A. Hudson
|
|
|
Underground rough-in inspection Contact Shawn Evins Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek 13 parallel service entrance conduits from Idaho transformer to vault then under building to electrical room rough in ok cover.
|
Electrical Rough-In | 10/17/2019 | 10/17/2019 | 10/17/2019 | P | PASS |
Rock A. Hudson
|
|
|
Rough-in inspection for the lightning protection ground loop Contact Shawn Evins Thank you, Phone #: ###-#### Inspection requested via web by Cathy Duchek Lightning arrest ground ring complete west, south, east sides. Still open from crane base to about 20' in from west corner. West side rough in ok cover.
|
Electrical Rough-In | 10/10/2019 | 10/11/2019 | 10/11/2019 | P | PASS |
Rock A. Hudson
|
|
|
Uffer ground inspection Contact Shawn Evins Thank you Phone #: ###-#### Inspection requested via web by Cathy Duchek Concrete encased electrode rough in ok cover
|