Permit Information
Permit NumberELE20-01794
StatusIssued
Name S & J ELECTRIC
Site Address 700 S CLEARWATER LN
Project Name 
Customer Number 
ePlanReviewNo
Description
Alteration: Electrical remodel
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
Final8/13/20208/13/20208/13/2020PPART
DetailsEric Story
partial final for the lobby and server rooms and janitors closet Phone #: ###-#### Inspection requested via web by Shane Lott
1st floor only MInus electrical rooms (Only accessilble to qualified personnel)
Final8/11/20208/12/20208/12/2020PPART
DetailsRock A. Hudson
partial final for upstairs conference rooms and training room and on 1st floor work lab and downstairs bathroom Tyson is site contact ###-#### Phone #: ###-#### Inspection requested via web by Shane Lott 1 Receptacle in lab requires GFCI, with in 6' of sink as per 210.8(B). Areas noted TCO ok
Final8/11/20208/11/20208/11/2020PPART
DetailsRock A. Hudson
a partial final on the first floor we will be checking the cubicle farm conference rooms and work lab call Tyson for questions 2082516476 Phone #: ###-#### Inspection requested via web by Shane Lott Informed of operating change over starting end of business 8-13-20. Informed of lighting system commissioning report required by the registered sesign professional prior to final. IECC C408.3.1 Lighting controls being covered by cubicals shall be moved or other solution prior to final. Prechecked cubicals, and conference rooms on level 1..... OK
Electrical Rough-In8/7/20208/10/20208/10/2020PPASS
DetailsDaryl DeGrange
Conference rooms ceiling cover Tyson is site contact 2516476 Phone #: ###-#### Inspection requested via web by Shane Lott rough-in ok cover ceiling grids in the eight conference rooms
Electrical Rough-In8/4/20208/4/20208/4/2020PPASS
DetailsJames Ady
2nd floor ceiling inspection for lighting clouds Phone #: ###-#### Inspection requested via web by Shane Lott "Cloud" area drop ceiling only ok to cover. Discussed partial final requirments. (All life safety items shall be completed)
Electrical Rough-In7/27/20207/27/20207/27/2020PPASS
DetailsEric Story
ceiling rough in inspection for "work room" call Tyson for questions ###-#### Phone #: ###-#### Inspection requested via web by Shane Lott
Ceiling in fab room ok to cover
Electrical Rough-In7/23/20207/23/20207/23/2020PPASS
DetailsRock A. Hudson
Ceiling cover Phone #: ###-#### Inspection requested via web by Shane Lott Asked if grid in clean room over assembly table could be covered, explained would need a tile left out so inspector could verify boxes in this area and wiring method to plug mold used comply with code. Partilal grid for clean room, west office space and 2 west hallways grid rough in ok cover.
Electrical Rough-In6/22/20206/22/20206/22/2020PPASS
DetailsJames Ady
Wall cover downstairs bathroom. Tyson is site contact ###-#### Phone #: ###-#### Inspection requested via web by Shane Lott Down Restrooms only ok ot cover
Electrical Rough-In6/9/20206/9/20206/9/2020PPASS
DetailsJames Ady
2nd story wall rough in Tyson is contact Phone #: ###-#### Inspection requested via web by Shane Lott 2nd floor rough in walls only ok to cover
Electrical Rough-In6/3/20206/4/20206/4/2020PPASS
DetailsJames Ady
Wall cover inspection afternoon Phone #: ###-#### Inspection requested via web by Shane Lott 1st floor minus restrooms walls only ok to cover
Electrical Rough-In5/28/20205/29/20205/29/2020APASS
DetailsRock A. Hudson
Underground inspection- City approved plans are on site now. Phone #: ###-#### Inspection requested via web by Shane Lott
General contractor asked about 1 siding walls, informed not to cover in any way prior to a rough in inspection as per BCC 4-05-23.
Underslab rough in ok cover.
Electrical Rough-In5/27/20205/28/20205/28/2020AFAIL
DetailsRock A. Hudson
Underground inspection Phone #: ###-#### Inspection requested via web by Shane Lott City approved set of prints not on site.