Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberESC07-01264
StatusFinaled
Name JAYLEN R WALKER
Site Address 5073 E SAWMILL WAY
Project NameHARRIS RANCH #9
Customer Number 
ePlanReview 
Description
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
DOC - Permit Finaled12/23/200912/23/200912/23/2009PPASS
DetailsTroy James
BMP Violation9/2/20089/5/20089/5/2008APART
DetailsClint A Smith
Need to free up sediment from the gutterpan where the turn around is installed.
CAS
BMP Violation8/27/20089/1/20089/2/2008AFAIL
DetailsClint A Smith
Wattle was installed incorrectly. Still has heavy amounts of sediemnt on the sidewalk.
Left a message with the RP to have it corrected by 9/5/08.
CAS
BMP Violation8/22/20088/27/20088/27/2008AFAIL
DetailsClint A Smith
Notice of Correction.
1. Install sediment protection in the back of the project where the stock pile of dirt is along the road way.
2. Remove all sediment and debris from all hard surface in the back part of the project area.
3. Maintain D.I. throughout the project area.
Failure to complt with the notice will result in a Stop Work Order.
Must be corrected by 8/28/08 PM. Will re-inspect on 7/1/08
CAS
BMP Violation8/20/20088/22/20088/22/2008AFAIL
DetailsClint A Smith
In the process of removing the dirt along the curb. No bmp's in place yet will check on 8/27/08. In not completed a Notice will be written.
CAS
BMP Violation8/14/20088/20/20088/20/2008ADEFR
DetailsClint A Smith
Spoke with RP over the stabilizing. Will be completed by tomorrow at the latest. Will re-inspect on 8/22/08
CAS
BMP Violation8/14/20088/14/20088/14/2008PFAIL
DetailsClint A Smith
In the south wst area of project next to the access road to the dam, thye slope that are sitting more than 2% need to be either stabilized of have some type of approved sediment barrier installed. Left a message with the RP to contact me to discuss the issues. Will re-inspect on 8/20/08
CAS
Random Inspection6/30/20086/30/20086/30/2008PCANC
DetailsClint A Smith
Streets have been cleaned up after the treess were planted.
CAS
General Inspection6/19/20086/19/20086/19/2008PPART
DetailsClint A Smith
Stock pile is going to be used for fill in the phase 10 patrail of the developement. Will be starting soon on the fill part. Told Rp that protection at the bottom of slope will be need, weather permitting.
CAS
#460
General Inspection5/7/20085/7/20085/7/2008APASS
DetailsClint A Smith
Site looks good. Getting ready to pave streets.
CAS
#460
Conference2/13/20082/13/20082/13/2008APART
DetailsSteven Webb
10:30
Random Inspection2/8/20082/8/20082/8/2008AFAIL
DetailsSteven Webb
Noticed land disturbing activities on 2/7/08: Further investigation revealed working without active permit. ESC plan has been reviewed and pass but has not been picked up by applicant. Applicant was informed that this permit is required to be picked up and plan & conditions implemented prior to further activities can commence.