Permit Information
Permit NumberESC11-00055
StatusFinaled
Name KENN HARDIN
Site Address 4623 W WILLOW LN
Project NameWILLOW LANE PARK WETLANDS
Customer Number 
ePlanReviewNo
Description
WILLOW LANE PARK WETLANDS
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection6/28/20126/28/20126/29/2012 PASS
DetailsClint A Smith
Permit finaled.
DOC - Permit Finaled6/29/20126/29/20126/29/2012APASS
DetailsClint A Smith
General Inspection6/13/20126/13/20126/13/2012 PASS
DetailsClint A Smith
General Inspection5/29/20125/29/20125/31/2012 PART
DetailsClint A Smith
starting to re establish vegitation.
General Inspection5/14/20125/14/20125/14/2012 PASS
DetailsClint A Smith
Spoke with RP ovr th stabilization methods applid and the re-application after flood waters receed. No violation found or concerns.
General Inspection4/12/20124/12/20124/16/2012 PASS
DetailsClint A Smith
General Inspection3/8/20123/28/20123/28/2012APART
DetailsClint A Smith
RP will be attending the RP class tonight. Making him valid under the assumption that the RP passes the certification class.
General Inspection3/8/20123/8/20123/8/2012 PART
DetailsClint A Smith
Will be checking on the 28th for an upadated RP.
General Inspection2/22/20122/22/20122/22/2012 PASS
DetailsClint A Smith
General Inspection2/7/20122/7/20122/7/2012 DONE
DetailsClint A Smith
Project is temporary stabilized.
General Inspection1/23/20121/23/20121/23/2012 PASS
DetailsClint A Smith
Waiting on stabiliztionto acheive
General Inspection1/8/20121/8/20121/9/2012 CANC
DetailsClint A Smith
weekend
General Inspection12/23/201112/23/201112/23/2011 PASS
DetailsClint A Smith
General Inspection12/8/201112/8/201112/8/2011 PASS
DetailsClint A Smith
General Inspection11/23/201111/23/201111/28/2011 PASS
DetailsClint A Smith
Site is active and contained.
General Inspection11/2/201111/2/201111/2/2011 NR
DetailsDaryl Spivey
no activity...........ds
General Inspection10/18/201110/18/201110/18/2011 DONE
DetailsClint A Smith
NO activity.
General Inspection10/3/201110/3/201110/3/2011 DONE
DetailsClint A Smith
No activity
General Inspection9/16/20119/16/20119/19/2011 PART
DetailsClint A Smith
No activity on that portion.
General Inspection9/1/20119/1/20119/1/2011 PASS
DetailsClint A Smith
General Inspection8/17/20118/17/20118/17/2011 PASS
DetailsSteven Webb
Unchanged, inactive site
General Inspection8/2/20118/2/20118/2/2011 PASS
DetailsSteven Webb
Inactive site currently
General Inspection7/18/20117/18/20117/18/2011 PASS
DetailsSteven Webb
unchanged
General Inspection7/1/20117/1/20117/1/2011 PASS
DetailsSteven Webb
Unchanged, still not active.
General Inspection6/16/20116/16/20116/16/2011 PART
DetailsClint A Smith
Have not achieved stabilization requirements at this time.
General Inspection6/1/20116/1/20116/1/2011 PASS
DetailsSteven Webb
Inactive, former area of disturbance is fully vegetated.
General Inspection5/17/20115/17/20115/17/2011 PASS
DetailsClint A Smith
General Inspection5/2/20115/2/20115/2/2011 PASS
DetailsSteven Webb
Site is not active, talked to RP not sure of the project schedule. RP will inquire and then send an e-mail to SGW with additional information.
General Inspection4/1/20114/1/20114/1/2011 PASS
DetailsClint A Smith
General Inspection3/17/20113/17/20113/17/2011 PASS
DetailsClint A Smith
General Inspection3/2/20113/2/20113/2/2011 PART
DetailsClint A Smith
Waiting on the hydroseeding to occur on all disturbed soil.
General Inspection2/15/20112/15/20112/15/2011PPASS
DetailsSteven Webb
Excavation and transporting of 800 cubic yards plus completed, (soils to Easter Simplot Park Bridge project). Sediment barriers in place.
General Inspection2/11/20112/11/20112/11/2011 PASS
DetailsClint A Smith
General Inspection4/27/20124/27/2012   
DetailsClint A Smith