Permit Information
Permit NumberESC12-00909
StatusFinaled
Name KENT OLSEN
Site Address 3201 W AIRPORT WAY
Project NameBoise Air Terminal Garage Expa
Customer Number 
ePlanReviewNo
Description
Project scope amended 12/14/12 to include 10.69 acres clean fill dump site on airport-owned property located in the west quadrant of the intersection of Victory and Orchard. Construction of a 325,780 sq. ft., 1015- car, 4-tier, flat plate, post-tensioned, open parking structure addition to the existing Boise Air Terminal open parking structure. The addition shall be served by two existing helix-shaped up- and down- ramps. The top level of the addition is protected by a pre-engineered metal roof structure. Work includes over-roadway signage, wayfinding graphics, hydraulic elevators, landscaping, landscape irrigation, concrete and asphaltic concrete pavement, pavement marking, emergency generator, site lighting, and peripheral construction to accommodate continued site and parking access during and after construction.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
General Inspection1/31/20141/31/20141/31/2014 PASS
DetailsAndy J. Long
Finaled.
DOC - Permit Finaled1/31/20141/31/20141/31/2014PPASS
DetailsAndy J. Long
New garage is open and in use. The south and west sides which were disturbed are now landscaped and stabilized. BMPs have been removed. No further ESC inspections necessary. BLD permit is still.
General Inspection12/16/201312/16/201312/16/2013 PASS
DetailsAndy J. Long
Garage structure is complete. Surrounding area of new garage has had landscaping (trees and curbing) installed and the bare ground has been hydroseeded with tacifier. No corrections at this time. Check status of stabilization next inspection.
General Inspection10/29/201310/29/201310/29/2013 PASS
DetailsAndy J. Long
General Inspection9/13/20139/13/20139/13/2013 CANC
DetailsBill VanDegrift
General Inspection7/29/20137/29/20137/29/2013 CANC
DetailsKimberly M. Johnson
General Inspection6/11/20136/11/20136/13/2013 PASS
DetailsClint A Smith
BMP Violation4/22/20134/25/20134/25/2013APASS
DetailsClint A Smith
General Inspection4/19/20134/19/20134/22/2013 FAIL
DetailsClint A Smith
Verbal to GC;
Place all excess washout into the provided washout pit.
Secure the plastic lining on the secondary containment to where it will not be effected by the wind. Will re-inspect on 4/25/2013
BMP Violation3/4/20133/4/20133/4/2013PPASS
DetailsClint A Smith
All issues corrected`
Random Inspection2/28/20132/28/20132/28/2013APASS
DetailsJim Storey
Random Inspection2/11/20132/11/20132/11/2013PPASS
DetailsJim Storey
General Inspection1/15/20131/17/20131/18/2013APASS
DetailsClint A Smith
Site Preparation1/15/20131/15/20131/15/2013AFAIL
DetailsClint A Smith
Verbal to RP:
1.Post ESC sign where visable from the street.
2. Install a construcution exit per industry standards at the transition point of the disturb soil and the asphalt.
3. Clean up all tracked materials off of the contraction area onto the roadway.
Will re-inspect on 1/17/2013
General Inspection12/21/20121/2/20131/2/2013ACANC
DetailsClint A Smith
Could not reach the RP
General Inspection12/18/201212/18/201212/21/2012 DONE
DetailsClint A Smith
Could not reach RP possibly due to holidays. Re-scheduled for 1/2/2013