General Inspection | 3/27/2013 | 3/27/2013 | 3/27/2013 | | DONE |
Clint A Smith
|
|
|
Permit finaled
|
DOC - Permit Finaled | 3/27/2013 | 3/27/2013 | 3/27/2013 | P | PASS |
Clint A Smith
|
|
|
|
General Inspection | 3/12/2013 | 3/12/2013 | 3/14/2013 | | PART |
Kimberly M. Johnson
|
|
|
No veg yet
|
General Inspection | 2/22/2013 | 2/22/2013 | 2/22/2013 | | PART |
Clint A Smith
|
|
|
Waiting on vegitation to setablish.
|
General Inspection | 2/7/2013 | 2/7/2013 | 2/7/2013 | | PART |
Clint A Smith
|
|
|
Waiting on vegitation to setablish.
|
General Inspection | 1/23/2013 | 1/23/2013 | 1/23/2013 | | PART |
Clint A Smith
|
|
|
Waiting on thaw to final out the permti.
|
General Inspection | 1/8/2013 | 1/8/2013 | 1/8/2013 | | PART |
Clint A Smith
|
|
|
Temporary stabilization methods applied prior to the winter. Site is covered in snow.
|
General Inspection | 12/21/2012 | 12/21/2012 | 12/21/2012 | | PASS |
Clint A Smith
|
|
|
All area of disturbed soil have had mulch, seed and tachifier applied.
|
Conference | 12/5/2012 | 12/6/2012 | 12/12/2012 | P | CANC |
Clint A Smith
|
|
|
test permit
|
General Inspection | 12/5/2012 | 12/5/2012 | 12/5/2012 | | PASS |
Clint A Smith
|
|
|
Will be inspecting the project with the RP to address any area that still need to be staabilized on 12/6/2012
|
General Inspection | 11/20/2012 | 11/20/2012 | 11/20/2012 | | PART |
Clint A Smith
|
|
|
Must maintain concrete washout prior to next pour in the Spring time of 2013
|
BMP Violation | 10/30/2012 | 11/2/2012 | 11/2/2012 | A | PART |
Clint A Smith
|
|
|
Discussed with the RP over stabilization practices and that compacted pitrun is not considered an acceptable stabilization practice.
|
BMP Violation | 10/26/2012 | 10/30/2012 | 10/30/2012 | A | CANC |
Clint A Smith
|
|
|
Re sheduled for 11/2/2012
|
General Inspection | 10/24/2012 | 10/24/2012 | 10/26/2012 | | FAIL |
Clint A Smith
|
|
|
Verbal to RP: Maintain sediment controls along the west end of the project area. Will re-inspect on 10/30/2012
|
Random Inspection | 10/9/2012 | 10/9/2012 | 10/9/2012 | P | PART |
Kimberly M. Johnson
|
|
|
BMPs not sufficient in narrow areas. Blade for grading too wide and soil was being pushed on top of and some instances over the the wattle. Contractor had already called out RP group to widen perimeter controls to edge of disturbance (barb wire fence line) and to install sandbags along narrow areas where height of wattle is not sufficient.
|
General Inspection | 10/3/2012 | 10/4/2012 | 10/5/2012 | P | PASS |
Clint A Smith
|
|
|
|
General Inspection | 10/3/2012 | 10/3/2012 | 10/3/2012 | P | CANC |
Clint A Smith
|
|
|
no activity
|
General Inspection | 10/2/2012 | 10/3/2012 | 10/3/2012 | A | DONE |
Clint A Smith
|
|
|
Went over certain points of concerns with the project along the Boise River side. Also explained to the contractor (Syman Company) over deficencies with the installtion of the sediment barriers being installed incorrectly. Will follow up this afternoon.
|
Site Preparation | 10/1/2012 | 10/1/2012 | 10/2/2012 | | PART |
Clint A Smith
|
|
|
WOrking with he ESC contractor, we discussed over the area on the ESC plan where it was impossible for the installation of a "trenched" sediment barrier. Told the contractor to look at other options like "weighted" products. Will follow up on 10/3/2012AM.
|